DISTRICT CONSUMER DISPUTES REDRESSAL COMMISSION ERNAKULAM
Dated this the 26th day of May, 2023
Filed on: 02/12/2022
PRESENT
Shri.D.B.Binu President
Shri.V.Ramachandran Member
Smt.Sreevidhia.T.N Member
CC NO. 549/2022
Between
COMPLAINANT
Shyni Sabumon, W/o. Sabumon, Vishnum Nivas, Kutticaud, Kaimanam, pappanamcode, Thiruvanahtapuram, Pin 695018.
(Rep. by Adv. Anitha Mathai Muthirenthy, Chamber No. 556, KHCAA, Chamber complex, Cochin 682031)
VS
OPPOSITE PARTY
Zain Builder Pvt. Ltd., KK Arcade, PJRA 78, Polassery Lane, PJ Antony road, Palarivattom, Ernakulam 682025. Rep. by its Managing Director.
FINAL O R D E R
DB.Binu, President
Complainant absent, represented. Opposite party absent, no representation. Counsel of the Complainant filed a withdrawal memo before the Commission on 26/05/2023. The subject matter of the above case has been amicably settled between the parties as per the terms and condition of the settlement memo.
In the view of the above, this complaint is closed as settled.
Pronounced in the open Commission on this the 26th day of May, 2023
Sd/-
D.B.Binu, President
Sd/-
V.Ramachandran, Member
Sd/-
Sreevidhia T.N., Member
Forwarded/by Order
Assistant Registrar
Despatch date:
By hand: By post
kp/
CC No. 549/2022
Order Date: 26/05/2023