West Bengal

Nadia

CC/52/2022

MITHUN DAS - Complainant(s)

Versus

THE DIRECTOR REPRESENTED BY SRI VIVEK PODDAR. MAGNOLIA INFRASTRUCTURE DEVELOPMENT LIMITED - Opp.Party(s)

DEBRAJ DAS

31 May 2024

ORDER

DISTRICT CONSUMER DISPUTES REDRESSAL COMMISSION
NADIA
170,DON BOSCO ROAD, AUSTIN MEMORIAL BUILDING.
NADIA, KRISHNAGAR
 
Complaint Case No. CC/52/2022
( Date of Filing : 17 May 2022 )
 
1. MITHUN DAS
S/O- SATISH DAS, VILL- RATHTALA, P.O- MAJDIA, P.S- KRISHNAGANJ, DIST- NADIA, 741507
NADIA
WEST BENGAL
2. SMT. MAMATA DAS
W/O- MITHUN DAS, VILL- RATHTALA, P.O- MAJDIA, P.S- KRISHNAGANJ, DIST- NADIA, 741507
...........Complainant(s)
Versus
1. THE DIRECTOR REPRESENTED BY SRI VIVEK PODDAR. MAGNOLIA INFRASTRUCTURE DEVELOPMENT LIMITED
OFFICE AT 93. DR. SURESH CHANDRA BANERJEE ROAD, P.S- BELIAGHATA, KOLKATA- 700010
KOLKATA
WEST BENGAL
2. THE DIRECTOR REPRESENTED BY UMANG NEMANI. OMEGA VANIJYA PRIVATE LIMITED
OFFICE AT BLOCK-E, NEW ALIPORE, 12 SHIVNATH SHATRI SARANI P.O & P.S- NEW ALIPORE, KOLKATA- 700053
............Opp.Party(s)
 
BEFORE: 
 HON'BLE MR. HARADHAN MUKHOPADHYAY PRESIDENT
 HON'BLE MR. NIROD BARAN ROY CHOWDHURY MEMBER
 
PRESENT:DEBRAJ DAS, Advocate for the Complainant 1
 BARUN PRASAD, Advocate for the Opp. Party 1
Dated : 31 May 2024
Final Order / Judgement

Ld. Advocate(s)

                                    For Complainant: Debraj Das

                                    For OP/OPs : Barun Prasad

 

            Date of filing of the case                      :17.05.2022

            Date of Disposal  of the case              :31.05.2024

 

Final Order / Judgment dtd.31.05.2024

The concise fact of the case of the complainant briefly narrated  to the effect that the complainants Mithun Das and Mamata Das applied  of

 

(2)

CC/52/2022

 

one 2Bhk flat in the project  of the opposite parties under the name  and style  of “Magnolia Sport City”. On 14.02.2017 they submitted  one application  for one 2Bhk flat at Block-2, 2nd floor, category-E, flat no.20E, area 670 sq.ft.  at a price of Rs.1950/- per Sq.ft.  and made payment of Rs.11,000/- towards booking  charge.  The OP No.2 Director  of Umang Nemani, OMEGA VANIJYA PRIVATE LIMITED purchased from Ghosh Brother  Realtors  Private Limited. Thereafter on 31.03.2017 one agreement  for sale was executed  between the complainants  and OP NO.1 Director through  Vivek Poddar of Mangolia  Infrastructure  Development  Limited  and Director Umang Nemani . The complainants  paid  Rs.90,000/- and 35,529/- on the date of execution  of the agreement for sale . It was agreed  that within three years  from the date of commencement  of the construction  and additional  6 months  may be extended  for unavoidable  circumstances. The original  agreement for sale is deposited to the SBI Rajarhat  Branch  against the loan for purchasing  the flat to the  SBI. The OPs obtained clearance  certificate  of proposed  construction  of G plus 7 storied residential building  plan from  the Government Department. As per the agreement  the date of commencement  of construction  is 26.07.2017 and expiry date  is 26.01.2021 as per  the agreement commenced  on 31.03.2017. The OP started  work  on 31.05.2018. So, one  demand notice  was sent to the  complainants  for Rs. 2,92,656/- on 31.05.2018. On 19.11.2018 the complainants  made payment of Rs.4,38,984/- for completion of foundation  and ground floor  roof casting . The complainants  further made payment  of Rs.1,46,328/- to the OPs  on 26.12.2018. The complainants  made further payment  of Rs.1,46,328/- to the OPs  for third floor  roof casting . He also paid Rs.1,31,956/- to the OPs on 22.05.2019 for completion  of 5th floor  roof casting . Subsequently,  the complainants  further paid Rs.2,63,914/- on 25.05.2019 on completion of brick  work and 7th floor  roof casting . On 11.07.2020 and 22.09.2020 the complainants  issued two letters to the OPs  for delay  in handing over  the said flat and  for expiry of the date  of delivery  of flat. On 13.10.2020 the OPs replied  through e-mail  stating  that due to WB HIRA approval  the time  limit has not expired. The HIRA is not applicable  in the ongoing project  because the WB HIRA was  enacted  after the  execution  of the agreement.  Therefore, the complainants lodged a complaint  to the Consumer Affairs Department North 24 Parganas on 14.05.2021 but the matter was not settled  there. The complainants  made payment  of 95% of the amount as per  the agreement  dated 31.03.2017 but the OPs  delayed  the construction  work. The construction  work has not been  completed  due to negligence of the OPs. The complainants sent one e-mail  notice on 17.12.2021 for registration  of the sale deed.  The

 

(3)

CC/52/2022

 

complainants  also paid Rs.28,462/-  to the OP NO.1 for trans-forma  installation  and Rs.65,977/- on 17.12.2021 for completion  of flooring. He further  paid Rs.1,33,016/- as per the  agreement  and Rs.28,462/- to the OP No.1. So, the present case  is filed. The OPs sent a letter  for making  final payment  of Rs.65,979/-. Finally  the OPs  executed  one deed of conveyance  on 31.05.2023 vide  deed no. 3599 by 2019. The said original deed of conveyance  is submitted  to the SBI Rajarhat  Branch on 19.06.2023 against financing the flat. The OPs has  handed over  the possession  of the flat with a  possession  letter to the complainants.  The complainants  claimed for interest  from the date of expiry  of delivery time  till the date of delivery of physical possession  upto 19.06.2023. The cause of action  for the present case arose on 26.01.2021 and thereafter each date till the filing of this case. The complainants  prayed for an award  for an interest @ 18% p.a from the date of expiry  of the delivery date till the date of delivery of physical  possession  of registered deed, Rs.2,50,000/- compensation  for harassment  and mental pain, agony  and Rs.50,000/- for litigation cost.

Both the OPs  contested the case by filing  W/V wherein they denied  each and every allegation. The OPs  challenged the case as not maintainable  on the ground  that it is bad for  non-joinder  and mis-joinder  of parties and it is not  maintainable  under the law and barred by  jurisdiction.  The positive defence  case of the OPs  in brief is that  for development  of land of OP no.2 one development agreement  date 06.04.2016 was executed  with OP No.1 for construction  of residential multi storied  building.  The OP No.2 executed one power of attorney  in favour of the OP No.1. The complainants  approached  the OP No.1 for purchasing  one flat on 14.02.2017 and the OP No.1 agreed to  allot  and sale  for Rs.1,36,500/- the complainants  paid Rs.1,36,529/- as booking money.  They entered  into an agreement  for sale on 31.03.2017. As per  the HIRA the date of  commencement  was 15.11.2018. It was agreed  that the OPs developer shall hand over  the flat within  the period of three years  from the date of commencement  of construction.  Due to pandemic  situation  of Covid-19 the construction  work  was stopped due to Lock Down  from 24.03.2020 upto 2020. So, WB HIRA by notification  extended  the time limit  upto 01.09.2023 at their website  for completion  of the building.  There is no fault  or delay  in completion  of the building  complex.  The Developer  completed  the building  on 01.09.2023 as the   WB   HIRA   extended   time  limit.  The   complainants    paid   90%   of   total      consideration     money .   The     complainants    should     also    follow      the     rules     of     WB  HIRA.   The   OPs 

 

 

(4)

CC/52/2022

 

claimed that the  complainants  tried to pressure  upon  the OPs to damage  their reputation. The OPs claimed that the case is liable to be dismissed.

The points of conflict between the parties in regard  to the delivery  of possession of the flat  beyond the alleged  time limit for handing over  is the point of contention.  The commission  considers  it necessary  to ascertain  the  following points  for proper adjudication of the case.

 

Points for Determination

Point No.1.

Whether the  present case is legally maintainable.

Point No.2.

Whether the complainant  is entitled to get the relief as prayed for.

Point No.3.

          To what other relief if any the complainant is entitled to get.

 

Decision with Reasons

Point No.1.

The OPs challenged the case  as not maintainable  on the ground that  the case barred by non-joinder and mis-joinder  of parties. In the given facts  and circumstances  since WB HIRA is applicable,  so the complainant has no cause of action.

The OPs claimed that  due to coming into  the force  of WB HIRA the present complaint  is not maintainable  and the complainant does not  have any  cause of action.

Ld. Advocate for the complainant argued that  the Act of WB HIRA came into force  on 17.10.2017. The agreement  between the  parties was executed  on 31.03.2017, so the  Act does not have  any application in the instant case.

After perusing  the documents  filed by the  complainant  it transpires  that the agreement  between the  complainant and the  OPs  was executed  on 31.03.2017. The Act came into force  on 17.10.2017.

 

 

(5)

CC/52/2022

 

Ld. Defence Counsel  could not satisfy the commission  as to how the said  WB HIRA is applicable  in this case.

Accordingly, after  taking into consideration  the  pleadings of the parties and the argument  advanced  by  Ld. Advocate for both the parties  the Commission considers  that the case  is not  barred under any provisions  of law.

Although the complainant  pleaded  that the present  case is bad for defect of parties  yet the OPs  could not specify  as to who others are proper  and necessary parties in this case except  the present OPs.

Accordingly,  there is no material  within the four-corners  of the case  record  to hold that the case is bad for defect of parties. Accordingly,  it is held that the  case is not  bad for defect of parties.

Consequently,  point no.1 is answered  in affirmative  and decided  in favour of the complainant.

 

Point No.2&3.

Both the points have  close nexus with each  other and as such these are  taken up together  for brevity and convenience  of discussion.

It is the admitted case that the  opposite parties  have handed over  the delivery of  possession  of the disputed  flat during the pendency  of the case. The complainants  by  means of amendment of complaint  has pleaded the said fact  in para 13 to the effect that  on 19.06.2023 the opposite parties  have handed over  the physical possession  of the disputed  flat and  issued one possession letter to the complainant . Therefore,  the complainant  has not claimed  for delivery of physical possession  of the flat by executing  registered deed of sale at present . The complainants  have prayed for  interest  from the date of expiry of the delivery  time till the date of delivery of possession that is upto 19.06.2023.

So, the crux  of the case is  that to ascertain  whether the WB HIRA, 2017 is applicable  in this case.

In this regard  annexure-I is the best document. Annexure-I is the  form no. 3, certificate  for extension  of registration  of project dated 15.10.2020 issued by Secretary  WB HIRA, West Bengal.  As per point no.2 of the said annexure-I “Registration  shall be extended  by period of 9 months  ending  on 01.09.2023  and  the   total duration 

 

 

(6)

CC/52/2022

 

of the period of registration  of the project shall be  4.8 years  commencing  from 15.11.2018 ending on 01.09.2023.”

As per  Annexure-I the said HIRA certificate for extension of  the date of commencement  of the said project  is 15.11.2018 but in the instant  case the agreement  between the  complainants and the OPs  is 31.03.2017. So, the said  certificate  for extension  under form no.3 (Annexure-I) does not have  any application in the instant case. So, the complainants rightly  claimed that the  said extension  of time  by virtue  of Annexure-I cannot  bind  and it is not  applicable  to him.

The argument  advanced  by the Ld. Advocate for the  complainant in this regard  is reasonable and acceptable, in as much as  the Ld. Defence counsel  could not satisfy  as to how this  certificate  is applicable  to the complainants.

Annexure-B is the agreement  to sale dated 31.03.2017 which clearly  specify  as per clause IX that the developer shall give  possession within a period  of three years  from the date of commencement  of construction.

Ld. Advocate for the complainant argued  that the OP company got clearance  of the project  on 26.07.2017, so they  ought to  have  commenced  the project immediately  after getting  the clearance.

The complainant  proved one  document  annexure-D being a letter  issued by Special Secretary  to the Government of West Bengal, Panchayet and Rural  Development Department, Kolkata vide letter  reference no. 3883-RD-F/RIDF-IV-41/2017 dated 26.07.2017 stating inter-alia  that “clearance  proposed construction  of G plus 7th storied building  plan,  as regards  the above reference  this department  has no objection  in giving  the clearance  of construction  of the  said residential  building  plan...”.

So, the argument  of the Ld. Advocate  for the complainant  has reasonable force  in as much as  the OPs seems to have  obtained  clearance  certificate  on 26.07.2017 but the  Covid  started  in March, 2020.” So, the OPs  could not  give sufficient  explanation  as to why the project  could not be  completed  or delayed  in the said  project prior  to the said Lock Down  period.

Moreover,  the extension  of time by the HIRA is not  applicable  for the complainant  as stated  hereinabove.

Ld. Advocate  for the  complainant  in order to  strengthen the case referred to one decision reported  in Civil Appeal No.3182 of 2019 passed by  Hon’ble Supreme  Court   wherein  it was held  that it 

 

(7)

CC/52/2022

 

is unjustified  it would be manifestly  unreasonable  to construe  the contract between the parties  as requiring the time to wait  indeifinitely  for  possession. So, an interest  was awarded  for delay in delivery of possession.

The said case law  is applicable  here and as such  relied on.

Ld. Advocate  for the complainant  further referred to one decision  reported in AIR-2018 SC 5351 wherein  interest was  awarded for detailed  delivery of possession.

The said  case law  is also applicable  here.

The aforesaid  misdeeds  on the part of the OPs  tantamount to unfair trade practices  and deficiency in service.

In the backdrop  of the aforesaid  discussion  and observation  made hereinabove  the Commission is of the view that the OPs could not justify  the delay  in  delivery of possession  and the complainants  successfully proved the case upto the hilt.

Point no.2&3 are accordingly,  decided  in favour of the complainants positively.

In the result  the complaint case succeeds  on contest  with cost against the OPs.

Hence,

                              It is

Ordered

 

that the complaint case no.CC/52/2022 be and the same is allowed on contest with cost of Rs.10,000/- (Rupees ten thousand) against the OPs. The complainants Mithun Das & Smt. Mamata Das do get an award for an interest  of 12% p.a  on the total amount of money  paid by the complainants  to the OPs  Rs.13,58,478/- (Rupees thirteen lakhs fifty eight thousand  four hundred seventy eight) from the date of expiry  of the delivery  time to the complainants till the date of delivery of physical possession  of the completed  flat  and execution of the registered deed , Rs. 50,000/- (Rupees fifty thousand) for harassment  and mental pain and agony and Rs.10,000/- (Rupees ten thousand) towards litigation cost. The opposite parties are  jointly and severally  directed to pay the interest  money as above  and Rs.60,000/- (Rupees

 

 

(8)

CC/52/2022

 

sixty thousand) within 30 days  from the date of passing the final order  failing which  the entire award  money shall carry an interest @12% p.a from the date of passing the final award till the date of its realisation.

All Interim Applications  (I.A) stand disposed of  accordingly.

D.A to note in the trial register.

The case is accordingly disposed of.

Let a copy of this final order be supplied to both the parties at free of costs.    

          

Dictated & corrected by me

 

 

 ............................................

                PRESIDENT

(Shri   HARADHAN MUKHOPADHYAY,)                               ................ ..........................................

                                                                                                                          PRESIDENT

                                                                                              (Shri   HARADHAN MUKHOPADHYAY,)

 

I  concur,

 

  ........................................                                                 

          MEMBER                                                                

(SHRI NIROD  BARAN   ROY  CHOWDHURY)                         

 
 
[HON'BLE MR. HARADHAN MUKHOPADHYAY]
PRESIDENT
 
 
[HON'BLE MR. NIROD BARAN ROY CHOWDHURY]
MEMBER
 

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.