Date of Filing: 23-07-2019
Date of Order:04 -6-2020
BEFORE THE DISTRICT CONSUMER DISPUTES REDRESSAL FORUM – I, HYDERABAD
P r e s e n t
HON’BLE Sri P.VIJENDER, B.Sc. L.L.B., PRESIDENT
HON’BLE Sri K.RAM MOHAN, B.Sc. M.A L.L.B., MALE MEMBER
HON’BLE Smt. CH. LAKSHMI PRASANNA, B.Sc. LLM.,(PGD (ADR) LADY MEMBER
Thursday, the 4th day of June, 2020
C.C.No.348 /2019
Between
Mohd Arifuddin
S/o.Late Khairuddin,
Aged about 36 years, Occ: Service,
R/o.9-3-239, Regimental Bazar,
Secunderabad – 500025 ……Complainant
And
Mr. T.Shiva Kumar S/o. Late Shivalingam
9-2-157, 1st floor, Above Rohini Acquarium,
Opp: Gopalapuram Police Station,
Regimental Bazar, Secunderabad - 500025 ….Opposite Parties
Counsel for the complainant : M/s.M.A.Madhumathi
Counsel for the opposite Party : Absent
O R D E R
(By Sri P. Vijender, B.Sc., LL.B., President on behalf of the bench)
This complaint has been preferred under Section 12 of C.P. Act 1986 alleging deficiency of service on the part of the opposite party.
- The complainant’s case in brief is that opposite party is a reputed builder and there was an agreement between them for construction of a house consisting of Ground+ 2 Upper floors as per the specifications agreed by both the parties . Both the parties signed on specifications agreement but opposite party did not sign the construction agreement after receipt of initial payment as he backed out with regard to certain items and the complainant went ahead with the payment of amount to the opposite party though opposite party did not sign the contract agreement. As per the agreed terms the opposite party has to complete the construction of the house by July 2018 but opposite party did not complete it in the given time and delivered semi-finished house and it was difficult for the complainant to live in the said house without furnishing works. The request made by the complainant with opposite party to complete all the works was in vain. The complainant intend to let out 1st floor and he was subjected to monetary loss by way of rent of Rs.13,000/- per month and on account of delay caused he could not let out the 1st floor. Therefore complainant entitled for the compensation from the opposite party at the rate of Rs.13,000/- per month and the total amount comes to Rs.1,56,000/-. The opposite party used inferior quality of material and the complainant got estimated the value of the works to be done at Rs.3,50,000/-. The estimate got prepared by the complainant for the value of the inferior quality material to be replaced is Rs.2,00,000/- and entitled for this amount and also compensation of Rs.5,00,000/-. Complainant got issued a legal notice to the opposite party calling upon him to pay the amounts but opposite party unclaimed it. Hence the present complaint to reimburse the amount spent by the complainant and pay loss of rental income and compensation of Rs.5,00,000/- and cost of the complaint at Rs.10,000/- .
- The notice got issued to the opposite party after registering the complaint was returned with an endorsement unclaimed and it amounts to refusal and knowledge of the contents. Hence complaint is proceeded in exparty
- In the enquiry the complainant has got filed his evidence affidavit reiterating the material facts of the complaint and to support the same got exhibited seven (7) documents. Complainant filed written arguments and made oral submissions.
On a consideration of material brought on the record the following points have emerged for consideration .
- Whether the complainant could prove deficiency of service on the part of the opposite party ?
- Whether the complainant is entitled for the amounts claimed in the complaint?
- To what relief?
Point No.1: Among the documents exhibited by the complainant Ex.A1 is the contract for labour and material for construction of the building consisting of Ground + 2 upper floors and it contains details of final specifications dated 10-12-2017. It is signed by both the parties though the complainant could not get the signatures of the opposite party on agreement details of specifications and details of construction . Ex.A1 signified that there was a contract between the parties for house construction Ex.A4 is the document which evidences that building permission was issued by the GHMC Town Planning Division in the name of complainant’s father for construction of the building and it is dated 18-10-2017 i.e., about two months prior to the date of work contract between the parties under Ex.A1. So this document evidences that complainant has a house plot secured permission from the competent authority for construction of the house consisting of Ground + two Upper floors. Ex.A6 is the copy of payment schedule which evidence of payment made to the opposite party for the services agreed to be provided to complainant by way of construction of house and as per this statement the payments made to the opposite party were by way of cheque as well as cash. The document in Ex.A7 shows that whenever complainant paid the amount either cash or cheque they were acknowledged by the opposite party with his signatures and date. Ex.A1 and A7 coupled with Ex.A6 schedule shows there was concluded contract between the parties for construction of house consisting Ground +two upper floors by the opposite party to the complainant and receipt of the payments made by the opposite party. Hence now burden is on the part of the opposite party to prove that he has done work as agreed with specifications mentioned in Ex.A1. The evidence affidavit of the complainant coupled with the estimate copy prepared by 3rd party for unfinished works shows the opposite party did not complete the construction in all aspects. Since opposite party has not chosen to contest the complaint having refused to receive the notice sent by this Forum an inference can be drawn that the opposite party has no material to deny the complainant’s case. The evidence on record both oral and documentary placed on record by the complainant remained un-rebutted hence same is required to be accepted. Thus the complainant has proved that opposite party having agreed to construct house building consisting of Ground + two upper floors with some specifications even after receiving the entire payment failed to complete it in all aspects and thereby caused deficiency of service. Accordingly point is answered infavour of the complainant.
Point No.2: The complainant has filed estimate copy prepared for the unfinished works and for substandard material used by the opposite party for the construction made by him, hence the complainant is entitled an amount of Rs.3,50,000/- towards cost of unfinished works and Rs.2,00,000/- towards substandard material used in the construction work. Though the complainant claimed loss of income of Rs.1,56,000/- he has not placed any evidence on record to show that the 1st floor if delivered in time would have fetched him a rent of Rs.13,000/- per month. In the absence of an evidence it is difficult to accept that complainant has suffered loss of income of Rs.1,56,000/- hence same is rejected. For the inconvenience caused to the complainant on account of non-completion of work by the opposite party an amount of Rs.50,000/- is awarded as compensation. Accordingly point is answered.
Point No.3: In the result, the complaint is allowed in part directing the opposite party
- To pay to the complainant a sum of Rs.5,50,000/- with interest there on at 9% P.A from the date of complaint to the date payment towards cost of unfinished works and substandard material used in the house construction
- To pay a sum of Rs.50,000/- as compensation for mental agony
- To pay a sum of Rs.10,000/- towards cost of legal expenses incurred by the complainant.
Time for compliance : 30 days from the date of service of this order
Dictated to steno, transcribed and typed by her, pronounced by us on this the 4th day of June , 2020.
LADY MEMBER MALE MEMBER PRESIDENT
APPENDIX OF EVIDENCE
EXHIBITS MARKED
For Complainant:
Ex.A1-copy of agreement ( details of final specifications) dt.10-12-2017
Ex.A2- copy of agreement payments
Ex.A3- Statement of construction
Ex.A4- copy of GHMC permit order
Ex.A5- copy of opposite party plan
Ex.A6-copy of payments schedule
Ex.A7-acknowledgements by opposite party
For Opposite party :
Nil
LADY MEMBER MALE MEMBER PRESIDENT