
View 42 Cases Against Samar Estates
Darshna Devi filed a consumer case on 24 Feb 2016 against Samar Estates Pvt Ltd in the DF-II Consumer Court. The case no is CC/135/2014 and the judgment uploaded on 02 Mar 2016.
DISTRICT CONSUMER DISPUTES REDRESSAL FORUM-II
U.T. CHANDIGARH
Consumer Complaint No. | : | 135/2014 |
Date of Institution | : | 19.03.2014 |
Date of Decision | : | 24.02.2016 |
Smt.Darshna Devi w/o Sh.Rakesh Kumar, Kahangarh Road, Patran, District Patiala.
... Complainant.
Versus
Samar Estates Pvt. Ltd., # 254, NAC, Manimajra, Chandigarh through its authorized signatory Sh.Vinod Bagai son of Shri Nand Lal.
BEFORE: SHRI RAJAN DEWAN, PRESIDENT
SHRI JASWINDER SINGH SIDHU, MEMBER
SHRI PRITI MALHOTRA, MEMBER
Argued by: Mohd. Yousaf, Counsel for the complainant.
Sh.Munish Kapila, Counsel for the OP.
PER RAJAN DEWAN, PRESIDENT
“15. For the reasons recorded above, the appeal is accepted. The order impugned is set aside. The case is remanded back, to the District Forum, with a direction to afford one reasonable opportunity, to the Opposite Party/ appellant, to submit its written version, and lead evidence, by way of affidavit(s), thereafter, permit the complainant/respondent, if need be, to lead evidence, in rebuttal, by way of affidavit(s), and then decide the same (case), afresh, on merits, in accordance with the provisions of the Act. The appellant/Opposite Party, is, however, burdened with costs of Rs.10,000/-. Payment of costs, by the appellant/Opposite Party, to the respondent/ complainant, shall be a condition precedent. In other words, the costs shall be paid, before the written version and evidence, are filed, by the appellant/Opposite Party.”
It took about 18 months in getting all the above said approvals from the Competent Authorities. The construction work of the first phase of the project could be started only in the month of October, 2007 and the construction work of Tower E in the second phase in which the complainant has booked the apartment was started on 15.01.2012. It has further been stated that the complainant got transferred the apartment in question on 01.04.2011 on construction linked installments payment plan, already booked by the Realpro Assests Pvt. Ltd. with the OP. It is submitted that as per terms & conditions of the application form for allotment, the complainant was required to make the payment as per payment schedule. It is submitted that roof slab upto 10th floor has been casted upto 12.01.2015 and brick work of the walls has also been completed. It is submitted that 80% of the agreed price has become due from the complainant till 12.01.2015 as no installments have been deposited by the complainant after 10.07.2011 and a sum of Rs.47,38,746/- as on 01.04.2015 was due against the complainant so the complainant has failed to fulfill the necessary terms & conditions of the application form as well as Apartment Buyers Agreement. Accordingly, the complainant is liable to pay 18% interest on delayed payments as per clause 10 of the Apartment Buyers Agreement. It is submitted that in the absence of payment of due installments in time by the allottees to the OP, construction work of the apartments could not be completed in time, therefore, delay in completing the project in time. It is submitted that the OP was making efforts to complete the construction. It is submitted that due to worldwide recession in the market during the last five years, buyers were not coming forward to invest in the real estate market and the buyers who booked the flats were not paying the due amount of the installments in time. It is submitted that as per clause 32 of the Apartment Buyers Agreement, in case of any delay on the part of the promoter/developer/company to complete the construction within the period as specified in the agreement, which was directly due to the fault of the promoter/developer/company, the company should pay penalty @ Rs.7/- per sq. ft. per month for delayed period. It is submitted that the construction of the tower and completion of the development works within three years was subject to the payment of the due installments by the allottees. If the allottees did not pay the due installment in time, the construction of the towers could not be completed within the stipulated period. It is submitted that the complainant should have availed the alternative remedy as provided under clause 46 of the Apartment Buyers Agreement executed by the complainant with the OP which provided that in case of any dispute arising out of or touching upon or in relation to the terms of the complaint and/or Apartment Buyers Agreement including the interpretation and validity of the terms thereof and the respective rights and obligations of the parties should be settled by conciliation failing which the same should be referred to the sole arbitration of the Managing Director of M/s Samar Estates Pvt. Ltd. or the person/officers appointed by him whose decision should be final and binding on the concerned parties. It is submitted that the complainant has failed to deposit due installments despite repeated reminders.. Pleading that there is no deficiency in service on its part, a prayer for dismissal of the complaint has been made.
“4. In our opinion, no part of the cause of action arose at Chandigarh. It is well settled that the expression cause of action means that bundle of facts which gives rise to a right or liability. In the present case admittedly the fire broke out in the godown of the appellant at Ambala. The insurance policy was also taken at Ambala and the claim for compensation was also made at Ambala. Thus no part of the cause of action arose in Chandigarh.
XXX XXX XXX
8. Moreover, even if it had application, in our opinion, that will not help the case of the appellant. Learned Counsel for the appellant submitted that the respondent-Insurance Company has a branch office at Chandigarh and hence under the amended Section 17(2) the complaint could have been filed in Chandigarh. We regret, we cannot agree with the learned Counsel for the appellant. In our opinion, an interpretation has to be given to the amended Section 17(2)(b) of the Act, which does not lead to an absurd consequence. If the contention of the learned Counsel for the appellant is accepted, it will mean that even if a cause of action has arisen in Ambala, then too the complainant can file a claim petition even in Tamil Nadu or Gauhati or anywhere in India where a branch office of the Insurance Company is situated. We cannot agree with this contention. It will lead to absurd consequences and lead to bench-hunting. In our opinion, the expression branch office’ in the amended Section 17(2) would mean the branch office where the cause of action has arisen. No doubt this would be departing from the plain and literal words of Section 17(2)(b) of the Act but such departure is sometimes necessary (as it is in this case) to avoid absurdity [vide G.P Singh’s Principles of Statutory Interpretation, Ninth Edition, 2004 P. 79].”
The principle of law, laid down, in the aforesaid case, is fully applicable to the instant case. Hence, from the above scenario, it is clear that no part of cause of action has accrued at Chandigarh so as to attract the territorial jurisdiction of this Forum.
24.02.2016
Sd/-
(RAJAN DEWAN)
PRESIDENT
Sd/-
(JASWINDER SINGH SIDHU)
MEMBER
Sd/-
(PRITI MALHOTRA)
MEMBER
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.