ORDER

BEFORE THE RAJASTHAN STATE CONSUMER DISPUTES REDRESSAL COMMISSION, JAIPUR

COMPLAINT CASE NO: 28/2020

 

Sh.Pawan Kumar s/o Manohar Lal r/o 99, 2nd floor, Karuna Kunj, Near Akash Hospital, Sector 3, Dwarka, Delhi-110078.

Vs.

 

1.Sahara Prime City Ltd. (Sahara City Homes)Site office, Sahara Infrastructure & Housing, Opp.Radha Swami Satang Vyas, Village Bilwa, Tonk Road,Jaipur through Manager

2.Sahara Prime City Ltd. (Sahara City Homes) Head office- Sahara India Centre, 2, Kapoorthala Complex, Aliganj, Lucknow through Managing Director.

 

Date of Order 30.3.2021

Before:

Hon'ble Mr. Justice Banwari Lal Sharma-President

Hon'ble Mr.Mahaveer Prasad Sharma-Member

 

Mr.Bhupendra Pareek counsel for the complainant

Mr.Narendra Kumar Sharma counsel for the respondents

 

BY THE STATE COMMISSION ( PER HON'BLE MR. JUSTICE BANWARI LAL SHARMA, PRESIDENT ):

2

The present complaint is filed by the complainant Pawan Kumar against respondents Sahara City Homes stating therein that respondents published advertisement in daily newspapers regarding available flats in township in Tonk Road with huge swimming pool, ideal environment, play ground, securty, communication service, appropriate transport facilities, modern education facilities, modern health care centre, Bharat Maa Naman Sthal, well planned infrastructure, Sahara City Homes Club, Community Centre, Home Plaza, Multiplex, Service Centre, Nature Care Centre and Energy savings etc. After impressing from the given advertisement complainant booked a flat in the aforesaid township on 30.6.2005 and Unit No. B-11/402 type 2 bedroom 4th floor, unit area 88.73 sq.mt. was allotted to the complainant on 1.10.2010 and the total cost was apprised as Rs.17,67,000/- and it was assured that from the date of allotment within 38 months the possession of the flat will be handed over to the complainant and in case of delay in payment the rate of interest will be charged as 15% p.a. The complainant paid all the amount i.e. Rs.18,04,054/- to the respondents according to schedule but respondents failed to construct the flat within stipulated period. Even after depositing the cost of house the possession

3

 

of flat has not been given by the respondents to the complainant till date.

 

The total cost of the flat was told as Rs.17,67,000/- and as per the agreement the amount was deposited in following manner:

Receipt date

Receipt no.

FA code

Tag

Debit

Credit

30.6.2005

10171141890

600002

N

0

11550

30.6.2005

10171141890

600003

N

0

105000

05/05/06

10239494029

600005

R

0

9635

12/05/06

10258967416

600005

R

0

48175

08/08/06

10285654943

600005

R

0

28905

06/09/06

10303097196

600005

R

0

9635

29.9.2006

103030 97918

600005

R

0

9635

17.11.2006

10319940936

600005

R

0

9635

20.12.2006

10313081871

600005

R

0

9635

27.1.2007

10340594379

600005

R

0

9635

25.7.2008

144508335676

600005

R

0

48000

25.7.2008

144508335679

600005

R

0

47360

27.10.2010

49000017113

600005

R

0

38867

27.10.2010

49000017113

600012

T

0

433

27.10.2010

49000017114

600005

R

0

5900

30.11.2010

49000017222

600005

R

0

39300

24.12.2010

49000017318

600005

R

0

39300

25.1.2011

5238

600005

R

0

39300

26.2.2011

49000017532

600012

T

0

178

26.2.2011

49000017532

600005

R

0

39122

31.3.2011

49000017637

600005

R

0

39041

31.3.2011

49000017637

600012

T

0

259

02/05/11

49000017764

600005

R

0

39299

02/05/11

49000017764

600012

T

0

1

30.5.2011

49000017898

600012

T

0

3

30.5.2011

49000017898

600005

R

0

39297

28.6.2011

49000092032

600005

R

0

39300

01/08/11

49000092158

600005

R

0

39299

01/08/11

49000092158

600012

T

0

1

27.8.2011

49000092263

600005

R

0

39298

27.8.2011

49000092263

600012

T

0

2

03/10/11

49000092359

600005

R

0

39295

03/10/11

49000092359

600012

T

0

5

31.10.2011

49000092465

600005

R

0

39293

31.10.2011

49000092465

600012

T

0

7

30.11.2011

49000092602

600005

R

0

39052

30.11.2011

49000092602

600012

T

0

248

05/01/12

49000092704

600005

R

0

39294

05/01/12

49000092704

600012

T

0

6

15.2.2012

49000092922

600005

R

0

40304

15.2.2012

49000092922

600012

T

0

8

15.2.2012

49000092921

600066

T

0

15302

15.3.2012

49000093067

600066

T

0

1012

15.3.2012

49000093066

600005

R

0

39300

16.4.2012

49000093206

600066

T

0

912

16.4.2012

49000093205

600012

T

0

17

16.4.2012

49000093205

600005

R

0

39383

17.5.2012

49000093316

600005

R

0

40279

17.5.2012

49000093316

600012

T

0

33

19.6.2012

49000093437

600005

R

0

40247

19.6.2012

49000093437

600012

T

0

65

19.7.2012

49000093522

600005

R

0

40247

19.7.2012

49000093522

600012

T

0

65

16.8.2012

49000093626

600005

R

0

40295

16.8.2012

49000093626

600012

T

0

17

24.9.2012

49000093764

600066

T

0

1012

24.9.2012

49000093763

600005

R

0

39154

24.9.2012

49000093763

600012

T

0

146

22.10.2012

49000093890

600005

R

0

40198

22.10.2012

49000093890

600012

T

0

114

21.11.2012

49000094007

600005

R

0

40215

21.11.2012

49000094007

600012

T

0

97

24.12.2012

49000094372

600005

R

0

40166

24.12.2012

49000094372

600012

T

0

146

24.1.2013

49000094521

600066

T

0

1012

24.1.2013

49000094520

600012

T

0

146

24.1.2013

49000094520

600005

R

0

39154

20.2.2013

49000094677

600012

T

0

81

20.2.2013

49000094677

600005

R

0

40231

20.3.2013

49000094827

600012

T

0

342

20.3.2013

49000094827

600005

R

0

39970

25.4.2013

49000094934

600005

R

0

40150

25.4.2013

49000094934

600012

T

0

162

21.5.2013

49000095024

600012

T

0

97

21.5.2013

49000095024

600005

R

0

40215

21.6.2013

49000095114

600012

T

0

97

21.6.2013

49000095114

600005

R

0

40215

15.7.2013

49000095209

600005

R

0

40312

23.8.2013

49000095320

600012

T

0

130

23.8.2013

49000095320

600005

R

0

40182

26.9.2013

49000095394

600005

R

0

40134

26.9.2013

49000095394

600012

T

0

178

25.10.2013

49000095468

600005

R

0

25592

25.10.2013

49000095468

600012

T

0

162

25.10.2103

49000095469

600066

T

0

14558

 

 

 

 

 

1804054

 

It is further averred that after depositing the aforesaid huge amount i.e. Rs. 18,04,054/- the respondents failed to perform its part of agreement without any reasonable cause which amounts deficiency in service of respondents and

 

6

 

petitioner prayed for remitting Rs. 18,04,054/- with interest @ 15% p.a. from the date of depositing the amount.

 

Due to deficiency in service and negligence of respondents the complainant suffered mental, physical and economic discomfort, therefore, in this count he prayed for Rs.11 lakhs and Rs. 10 lakhs was claimed on ground that petitioner failed to utilize the aforesaid amount for his personal needs. Rs. 2 lakhs was claimed on account that petitioner has to took several rounds for claiming the amount and Rs. 1 lakh was claimed for advocate fee and other legal expenses. Accordingly total Rs. 42,04,054/- has been claimed with interest.

 

In reply respondents admitted the receiving of aforesaid amount and it is mentioned that due to legal proceedings the property of respondent was attached by SEBI, therefore, respondents could not complete the project. However, they are ready to remit the amount.

 

Heard. Since there is no dispute of respondents regarding aforesaid payment which was deposited by

7

 

complainant before the respondents, however, during course of arguments respondent's counsel proposed before this Commission that respondents are ready to return the principal amount with interest @ 9% p.a. from the date of receipt of each amount within three months. The learned counsel further states that respondents are also agree that if the amount has not been paid within three months then interest will be paid @ 12% p.a. from the date of receiving the each amount.

 

The learned counsel for the petitioner Mr.Bhupendra Pareek also submits that if respondents are ready to return the amount with interest @ 9% p.a. within three months and if they failed to remit the amount within three months then interest @ 12% will be paid from the date of receiving the amount by the respondents then the complaint may be decided accordingly. However, the amount in term of mental and physical agony and legal expenses may also be awarded in favour of the complainant.

 

Since there is no dispute regarding receiving the amount by the respondents for the aforesaid pent house and it is also not disputed that respondents failed to complete the project and

8

 

deliver the possession of allotted pent house to the complainant within stipulated period which is clear cut deficiency in service.

 

Therefore, it is ordered that respondents shall pay the amount which was deposited by the petitioner before them against booking and allotment of flat amounting to Rs.18,04,054/- within three months from today with interest @ 9%p.a. from the date of receiving the each amount . It is made clear that if payment is not being paid within three months from today then the petitioner is entitled to get interest on the aforesaid amount @ 12% p.a. instead of 9% p.a. Apart from it the petitioner is also entitled for Rs. 2 lakhs for mental agony which he suffered due to deficiency in service of the respondents. He is also entitled for legal expenses including advocate's fee in the tune of Rs. 50,000/- from the respondents. It is also directed that the aforesaid amount of mental agony and legal expenses will also be paid within three months otherwise it will also carry interest @ 12% p.a. from today.

 

(Mahaveer Prasad Sharma) (Banwari Lal Sharma)

Member President

 

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties