West Bengal

Kolkata-III(South)

CC/664/2017

Ratan Nath. - Complainant(s)

Versus

M/S. Chowdhury Enterprise. - Opp.Party(s)

Anandita Kundu.

24 Jun 2019

ORDER

CONSUMER DISPUTE REDRESSAL FORUM
KOLKATA UNIT-III(South),West Bengal
18, Judges Court Road, Kolkata 700027
 
Complaint Case No. CC/664/2017
( Date of Filing : 21 Nov 2017 )
 
1. Ratan Nath.
S/O Lt. D Nath residing at P 70 Jubilee Park K.D. Road, P.S. Sarsuna Kolkata-700061.
2. Tulsi Nath
W/O Lt D Nath residing at P 70 Jubilee Park K.D. Road, P.S. Sarsuna Kolkata-700061.
...........Complainant(s)
Versus
1. M/S. Chowdhury Enterprise.
having its registered office at 95N, K D Road, P.S. Sarsuna Kolkata-700061 represented by its proprietor
2. PARTHA CHOWDHURY
S/o Lt M L Chowdhury 11/23/6, Shiba Priya Chatterjee Road, P.O.- and P.S.-Sarsuna, Kolkata-700061.
............Opp.Party(s)
 
BEFORE: 
 HON'BLE MRS. Sashi Kala Basu PRESIDENT
 HON'BLE MRS. Balaka Chatterjee MEMBER
 HON'BLE MR. Ayan Sinha MEMBER
 
For the Complainant:
For the Opp. Party:
Dated : 24 Jun 2019
Final Order / Judgement

Dt. of filing- 21/11/2017

Dt. of Judgement- 24/06/2019

Mrs. Sashi Kala Basu, Hon’ble President.

       This  complaint is  filed by the complainants  namely  Ratan Nath and Tulsi Nath  under Section 12 of the Consumer Protection Act,  against the Opposite Parties namely M/s. Chowdhury Enterprise   and Partha Chowdhury alleging  deficiency  in service  on their part.

          Case of the complainants in short is that they are the absolute owners of the schedule property and were in possession of the same.  A  Development agreement was executed by and between the complainants and the OPs which was registered on 26.05.2014. As per the terms of the agreement, construction was to be completed   within 18 months from the date of   execution of the agreement but the OP did not show any interest to develop the land. Complainants approached the OP seeking explanation as to why they were not getting the plan sanctioned but OP refused to answer and behaved rudely. Complainants by a letter dated 07.01.2017 requested the OPs to immediately start the  process of developing land but almost  10 months  had been passed, nothing has been done. A Demand Notice  was  also sent  by the  complainants  on 17.11.2017 requesting the OPs to execute a former deed of cancellation of development agreement and to pay the compensation  as agreed  in the development  agreement, but all in vain.  OP also did not pay Rs.30,000/- in cash as agreed. So, present case has been filed by the complainants praying for  directing the  OPs to pay  a sum of Rs. 4,20,000/- towards compensation as agreed,  to pay further compensation of Rs. 2,50,000/- for mental agony  and litigation cost  of Rs. 30,000/-.

          Complainants have annexed   with the complaint petition, copy of the development agreement, copy of the deed of sale, copy of the letters dated 13.11.2017 sent by the complainants to the OPs.

OP No.2 has contested the case  by filing  a Written Version  denying the material allegations  made in the petition of complaint contending inter alia  that he has  paid  advance of Rs. 30,000/- as agreed. It is further contended that despite being aware of defective title, complainants induced the OPs to enter into  the agreement. Due to non-cooperation by the complainants in not providing the necessary documents, OPs could not get the plan sanctioned. OP has suffered loss of Rs. 15,00,000/- and has  become the  victim of circumstances. So, OP has prayed to dismiss the complaint petition.

          During the course of the evidence, both parties adduced their respective evidence by filing affidavit-in-chief followed by filing questionnaire and reply thereto. Ultimately, argument has been advanced by both sides. So, the following points require to be determined.

  1. Whether there has been any deficiency in service on the part of the OPs?
  2. Whether complainants are entitled to relief as prayed for?

Decision with reasons

          Point Nos. 1 & 2 : Both these points  are taken up  together  for discussion  for the sake of convenience  and in order to  avoid the repetition. It is an admitted fact that the development agreement dated 23.05.2014 was executed by and between the parties. By the said agreement, OP agreed to construct and complete a new building in the property as described in the schedule. On perusal of the agreement,  it is evident that the  OP agreed that he shall complete  the building within 18 months from the  date of  sanction of the plan and/or  from the date of  getting  peaceful vacant and khas  property from the  owner  whichever is later. The only contention which has been raised by the OP is that   due to the defective title and also as he was not handed over the proper up-dated tax bill and mutation papers, he could not  get the plan sanctioned. The agreement was executed on 23.05.2014. But it is  strange  that the OP remained silent all along. He has not filed any document  in order to substantiate  his claim that  he  was not handed over the  relevant documents to take step for getting the  plan sanctioned. It is but natural that if no document was handed over, OP either would go for  cancellation of development agreement or  would  ask for the documents  required  for sanction  of the  plan but he  did not take any  such step. No letter has been  sent by the OP  to the complainant at any time.  On the contrary, complainants have stated that they sent  a letter dated 07.01.2017  to the OP requesting to start the process of development but he failed to do so. Another letter dated 13.11.2017 sent  by the complainant, stating that as OP   failed to complete the construction  within the  limitation period of  18 months from the date of execution  of agreement, he was liable to pay the compensation  as agreed. It is also stated in  the said letter dated 13.11.2017 that the complainants have approached him earlier also seeking explanation as to why he was not getting the plan sanction in order  to develop the land. But inspite of getting the said letter, OP did not reply.

 According to OP,  he has suffered  loss of  15,00,000/-  because he had received  advance/earnest  money from the  intending purchasers in respect  of the flats  to be constructed. But the same  contradicts  to the own claim  of the OP that due to  fault on the part of the  complainants for not  handing  over the relevant documents  he could not get the plan sanctioned. In this context,  it may be pertinent to point out  that a developer /builder  has no authority  to collect any money from an intending  buyer without obtaining the sanctioned plan  from the  competent authority. In this case, as absolutely  no document is forthcoming  from the  side of the OP that the  complainants  failed to deliver  him necessary documents, he is liable to pay the  compensation  as per the terms of  the  agreement. It is categorically  mentioned  in the agreement between the parties that if the developer  deliberately  fails and neglects  in completing  the entire  project and/or  to handover  the owner’s allocation within the stipulated  period,  the developer  shall pay  a sum  of Rs. 10,000/-p.m. to the owner  towards the compensation. So, on consideration of the same, OP is liable  to pay the  said compensation from  January  2016,  as there has been deficiency in service  on his part. However, so far as the payment of Rs. 30,000/- by the developer to the owner as non-refundable  consideration, admittedly the same has been paid by the developer.  In their Affidavit-in-reply to the questionnaire  put by the OP, complainants have  admitted that they have  received  Rs.30,000/-. Regarding prayer for further compensation towards mental agony, we find no justification to allow the same in the given circumstances of this case.

          These  points are answered accordingly.

 

Hence,

                            Ordered

          CC/664/2017 is allowed on contest.  OPs are directed to pay compensation of Rs. 10,000, per month as agreed, from the month of January, 2016 to till this date within two months from the date of this order. They are further directed  to pay litigation cost of Rs.10,000/-  within the  aforesaid period of  two months failing which the  entire  sum shall carry  interest @8% p.a. till its realisation.

 
 
[HON'BLE MRS. Sashi Kala Basu]
PRESIDENT
 
[HON'BLE MRS. Balaka Chatterjee]
MEMBER
 
[HON'BLE MR. Ayan Sinha]
MEMBER

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.