
View 74 Cases Against Omaxe Chandigarh Extension Developers Private Limited
Surinder Kumar Mehta filed a consumer case on 20 Dec 2016 against M/s Omaxe Chandigarh Extension Developers Private Limited & anr. in the StateCommission Consumer Court. The case no is CC/530/2016 and the judgment uploaded on 21 Dec 2016.
STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
U.T., CHANDIGARH
Complaint case No. | : | 530 of 2016 |
Date of Institution | : | 31.08.2016 |
Date of Decision | : | 20.12.2016 |
Surinder Kumar Mehta son of Sh.S.L. Mehta, resident of #5, NAC, Manimajra, Chandigarh.
……Complainant
.... Opposite Parties
Complaint under Section 17 of the Consumer Protection Act, 1986.
BEFORE: JUSTICE JASBIR SINGH (RETD.), PRESIDENT.
MR. DEV RAJ, MEMBER.
MRS. PADMA PANDEY, MEMBER
Argued by: Sh.Neeraj Sobti, Advocate for the complainant.
Sh.Ashim Aggarwal, Advocate for the opposite parties.
PER JUSTICE JASBIR SINGH (RETD.), PRESIDENT
One Mrs.Radhika Goyal, by moving an application on 12.12.2010, registered herself for allotment of a residential plot, measuring 300 square yards, in a project, launched by opposite parties, known as ‘Omaxe Chandigarh Extension’ at Mullanpur, Punjab. She opted for “Down Payment Plan”, to make her eligible to get additional discount, as per plan adopted for payment. 25% of the basic sale price was to be paid at the time of booking, 15% of the basic sale price at the time of allotment and another 55% of basic sale price and 50% of additional costs, was to be paid within 30 days from the date of allotment. Balance 5% was to be paid at the time of offer of possession of the plot, in question. Basic sale price of the plot was fixed at Rs.40,07,456.69Ps. plus PLC to the tune of Rs.2,71,026/-. Over and above, the allottee was to pay additional amount of Rs.80,000/-, towards IFMS and club charges. It is case of the complainant that his son was of marriageable age and with a view to settle him in life, he decided to purchase a residential plot, in the above said project. Accordingly, deal was struck with above named Mrs. Radhika Goyal and he purchased the said plot on 10.10.2011. At that time, Mrs.Radhika Goyal had paid an amount of Rs.15,70,000/-, towards price of the plot, which amount was paid to her, by the complainant. He also paid transfer fee, as demanded by the opposite parties. On making endorsement, in this regard, he stepped into the shoes of the original allottee. Provisional allotment letter was issued on 22.11.2012 Annexure C-5. On demand raised vide letter dated 07.12.2012, he paid an amount of Rs.22,98,110/- to the opposite parties, vide receipts Annexures C-7 and C-8. In a way, 95% of total sale consideration stood paid, towards the plot, in question. Allotment letter/Agreement was issued on 22.01.2013. By 17.12.2012, the opposite parties had already received an amount of Rs.41,18,110/-. It is grievance of the complainant that by issuing allotment letter/agreement after two years from the date of booking and having received Rs.41,18,110/- against basic sale price of Rs.40,07,456.69Ps., the opposite parties had indulged into unfair trade practice, for which they need to be dealt with sternly.
“24(a) The Company shall put its best efforts to complete the development of the Plot/Project within 18 (Eighteen) months or within an extended period of six months from the date of signing of this Allotment Letter by the Allottee(s), subject to force majeure conditions [as mentioned in Clause (b) hereunder] or subject to various Plot Allottee(s) making timely payment or subject to any other reasons beyond the control of the Company. No claim by way of damages/compensation shall lie against the Company in case of delay in handing over the possession on account of any of the aforesaid reasons and the Company shall be entitled to a reasonable extension of time for the delivery of possession of the said Plot to the Allottee(s). The aforesaid period of development shall be computed by excluding Sundays, Bank Holidays, enforced Govt. holidays and the days of cessation of work at site in compliance of order of any Judicial/concerned State Legislative Body.”
In the written reply filed, an attempt has been made by the opposite parties, to defeat prayer made by the complainant, on frivolous grounds, like this Commission has got no territorial and pecuniary jurisdiction; the complaint filed is beyond limitation etc. It was stated that the complainant has also purchased one more plot in the project of the opposite parties. Besides as above, he has a residence at Manimajra, Chandigarh, meaning thereby that he being an investor would not fall within the definition of a “consumer” as defined under Section 2(1)(d) of the Act, as he had purchased the plot, in question, for commercial purpose i.e. for selling the same, as and when there was escalation in the prices of real estate, to gain huge profits. It was also stated that, as per Clause 24 (a) of the Agreement, it was agreed between the parties, that the Company only proposes to deliver possession of the plot, in question, within a maximum period of 24 months (18 plus (+) 6 months), from the date of signing of the Allotment Letter/Agreement, excluding Saturdays, Sundays etc., as such, time was not the essence of contract. It was averred that the allegations levelled in the complaint and also the complaint is time barred.
The same question, came up before this Commission in a case titled as Ankur Gupta Vs. Omaxe Chandigarh Extension Developers Pvt. Ltd. and another, Consumer Case No.309 of 2016 decided on 22.11.2016, wherein also there was a delay in issuance of Allotment Letter/Agreement, by the opposite parties, after accepting booking amount. While dealing with above said contention, it was observed by this Commission, as under:-
“In the first instance, we will deal with an argument, raised by Counsel for the complainant that by offering Agreement for signing after many months of the allotment and receiving huge amount, the opposite parties have indulged into unfair trade practice. It is on record that the complainant purchased the built-up unit by moving an application on 14.03.2011. He paid an amount of Rs.8 lacs, towards booking amount. Thereafter, in terms of letter dated 01.08.2011 Annexure C-2 sent by the opposite parties, an amount of Rs.9,18,951.85Ps., towards price of the said unit, which also includes Rs.23,068.98Ps., towards service tax, was paid by him. After draw of lots, flat was allotted to him on 23.12.2011. It is positive case of the complainant that Agreement was offered for signing on 18.09.2012; he signed and gave it to the opposite parties, on the same day. However, thereafter, to gain time, it was wrongly shown to have been executed on 26.03.2013. To the contrary it is case of the opposite parties that Agreement was signed on the date mentioned above. To support above said contention, no evidence whatsoever, has been placed on record by the opposite parties. As such, it can safely be said that Agreement was got signed belatedly on 26.03.2013 i.e. after a period of about 15 months, from the date of allotment, in the month of March 2011. The said act would amount to unfair trade practice on the part of the opposite parties. It was also so said by this Commission in Sudesh Rani Vs. Omaxe Chandigarh Extension Developers Pvt. Ltd. and another, Consumer Case No.178 of 2016, decided on 16.08.2016.”
It was found as a matter of fact that by issuing Allotment Letter/Agreement after 15 months, from the date of accepting booking amount, the opposite parties have indulged into unfair trade practice. In the present case, situation is worse than that. Admittedly, the plot was booked by Mrs.Radhika Goyal on 12.12.2010, by making payment of amount of Rs.6 lacs. Thereafter, plot was purchased by the complainant on 10.10.2011. By that time, the previous owner had already paid an amount of Rs.18,20,000/-. Provisional letter of allotment was issued in favour of the complainant on 22.11.2012. By 17.12.2012, the complainant had paid an amount of Rs.41,18,110/- i.e. more than the basic sale price of the plot i.e. Rs.40,07,456.69Ps. Final letter of Allotment/Agreement containing terms and conditions was issued only on 22.01.2013 i.e. after about two years of accepting booking amount for the plot, in question. After acceptance of booking amount, it was required of the opposite parties to issue allotment letter/agreement, within a reasonable time, say two or three months. It was also earlier so said by this Commission, in a case titled as Usha Kiran Ghangas Vs DLF Homes Panchkula Private Limited, Complaint Case No.93 of 2016, decided on 02.06.2016. Relevant portion of the said case, reads thus:-
“The opposite parties are also guilty of adoption of unfair trade practice. It is on record that the complainant booked the unit, in question, in the project aforesaid, on 16.02.2011. She was allotted unit, vide letter dated 23.02.2011, on which date, she had paid an amount of Rs.4 lacs. Buyer’s Agreement was not put for signing in a reasonable time, say two to three months. She continued to make payment and when Buyer’s Agreement was got signed, on 18.08.2011, she had already paid an amount of Rs.21,68,524/-. By not offering Buyer’s Agreement, for signing in a reasonable time, the opposite parties also committed unfair trade practice. The complainant is a widow. Her interest needs to be protected”.
As such, by not offering Allotment Letter/Agreement, for signing in a reasonable time, but after a delay of about two years of accepting booking amount, the opposite parties committed unfair trade practice and are also deficient in providing service. In view of above default committed, we are of the considered opinion that compensation to the extent of Rs.1.50 lacs, if granted to the complainant, shall meet the ends of justice.
“We feel that the contention raised is liable to be rejected. In Clause 23(b) of the Agreement, it is stated that possession will be delivered within 24 months, from the date of allotment letter, with six months extension. It is further stated that when computing the said period all Saturdays, Sundays and Bank Holidays will be excluded. A similar issue came up for consideration before this Commission qua another project of the opposite parties, in the case of Dr.Divya Dahiya Vs. M/s Omaxe Chandigarh Extension Developers Private Limited and another, Consumer Complaint No.57 of 2016, decided on 15.07.2016, wherein, it was observed as under:-
“The first question, which falls for consideration, is, as to whether there was delay in offering possession of the plot, in question, and if so, to what extent. The allotment letter for independent floor in Row-Housing Project “Silver Birch” in the project of the Opposite Parties (Annexure C-4) was issued to the complainant on 30.08.2011. As per Clause 31(a) of the allotment letter, the Opposite Parties were to complete the development of the unit within 24 months or within an extended period of six months from the date of start of construction, subject to force majeure conditions. Since allotment letter is dated 30.08.2011, by computing 24 months plus 6 months period, the Opposite Parties were bound to deliver possession of the plot, in question, by 01.03.2014. The Opposite Parties have stated that period was to be computed by excluding Sundays, Bank Holidays, enforced Govt. holidays and the days of cessation of work at site in compliance of order of any Judicial/concerned State Legislative Body. Apparently, for seeking six months extension beyond 24 months or beyond six months extended period, the Opposite Parties owe an explanation, if the delay was on account of force majure conditions but nothing by way of cogent evidence to this effect has been placed on record. Thus, when no explanation for extension of six months period has been furnished, the Opposite Parties at the most could be allowed one out of the two benefits i.e. either six months extension beyond 24 months or period on account of Sundays/Holidays etc. This Commission in Consumer Complaint No.153 of 2015 titled ‘Mr. Madan Lal Taneja and another Vs. M/s Omaxe Chandigarh Extension Developers P. Ltd.’ decided on 03.11.2015, facts of which were almost identical, held that Opposite Parties were to hand over possession within 30 months from the date of start of construction. Thus, the possession of the unit, in question, was to be delivered by 01.03.2014.”
Similar view has also been reiterated by this Commission, in number of cases, thereafter. It was specifically held that when there is no explanation of getting extension of 6 months period to deliver possession beyond the stipulated date, the benefit of exclusion of Saturdays, Sundays, Bank Holidays etc. cannot be given. Out of the two benefits, only one can be made available to the opposite parties. In the present case, Agreement was executed on 22.01.2013. As per admitted terms and conditions, possession of the plot was to be delivered by 21.01.2015. However, it has not been so done. At the time of arguments, no commitment was made, as to, within how much period in future, possession of the plot can be handed over to the complainant. In a very draconian manner, in the Agreement, in Clause 24(a), it has been stated that in case of delay, no claim by way of damages/compensation will be provided to the purchaser of plot(s). It would mean that the opposite parties can delay and hand over possession after unlimited period. Such a situation cannot be appreciated and this would mean to again indulging into unfair trade practice.
“What relief can be granted to a consumer, in case of delay, in offering possession, came up for consideration before the Hon’ble National Commission, in a case titled as Parsvnath Exotica Ghaziabad Resident's Association Vs. Parsvnath Buildwell Pvt. Ltd. & Anr., consumer complaint no.45/2015, decided by the Hon’ble National Commission, on 06.05.2016, wherein, it was argued by the project proponent that at the maximum, as provided in the Agreement, the consumer will be entitled to claim penalty for delayed compensation @Rs.5/- per square feet, per month. Noting that in case of delay in making payment, the project proponent was charging heavy penal interest, instead of penal amount, the interest on the deposited amount, for the period of delay was granted, by holding as under:-
“Though, the Agreement between the developer and the flat buyers provides for payment of compensation in case of delay @ Rs.5/- per square feet of the super area per month, such clauses have been found to be unfair trade practice and have been consistently rejected by this Commission in several decision, including Consumer Complaint No. 427 of 2014 Satish Kumar Pandey & Ors. Vs. Unitech Ltd. and connected matters decided on 08.6.2015. Therefore, the aforesaid clauses cannot be taken into consideration, while determining the compensation payable to the members of the complainant association for the aforesaid delay in completion of construction.”
Not only this, in another case, titled as Capt. Gurtaj Singh Sahni & anr. Vs Manager, Unitech Limited & anr., consumer complaint bearing no.603/2014, decided on 02.05.2016, the Hon'ble National Commission, directed the opposite party/builder to pay interest on the deposited amount, for the period of delay, till delivery of possession of the unit. Relevant contents of the said order reads thus:-
“8. If the compensation for the delay in construction is restricted to what is stipulated in the Buyers Agreement, there will be no pressure upon the builder to complete the construction since he will be more than happy to keep on paying paltry compensation of about 3% per annum of the capital investment, instead of arranging funds at much higher cost, to complete the construction.
9. xxxxxxxxxxxxx
10. For the reasons stated hereinabove, the complaints are disposed of with the following directions:
(1) xxxxxxxxxxxxxx
(2) The opposite party shall pay compensation in the form of simple interest @ 12% per annum from the expected date of possession till the date on which the possession is actually offered to the complainants after completing the construction in all respects and obtaining the requisite completion certificate.”
Thus, keeping in view the principle of law laid down by the Hon'ble National Commission, in the cases, referred to above, if interest @12% on the deposited amount for the period of delay, till delivery of possession of the unit, is awarded, that would meet the ends of justice.”
Taking note of above said proposition of law, in the present case also, ends of justice would meet, if interest is granted for delayed period, to the complainant whereof 21.01.2015.
Besides as above, the mere fact that the complainant has purchased another plot in the project of the opposite parties or that he own a house wherein presently he is residing, in itself, will not disentitle him, to come under the purview of the consumer. Recently, in a case titled as Aashish Oberai Vs. Emaar MGF Land Limited, Consumer Case No. 70 of 2015, decided on 14th Sep. 2016, under similar circumstances, the National Commission negated the plea taken by the builder, while holding as under:-
“In the case of the purchase of the houses which a builder undertakes to construct for the buyer, the purchase can be said to be for a commercial purpose where it is shown, by producing evidence, that the buyer is engaged in the business of a buying and selling of houses and or plots as a trading activity, with a view to make profits by sale of such houses or plots. A person cannot be said to have purchased a house for a commercial purpose only by proving that he owns or had purchased more than one houses or plots. In a given case, separate houses may be purchased by a person for the individual use of his family members. A person owning a house in a city A may also purchase a house in city B for the purpose of staying in that house during short visits to that city. A person may buy two or three houses if the requirement of his family cannot be met in one house. Therefore, it would not be correct to say that in every case where a person owns more than one house, the acquisition of the house is for a commercial purpose. In fact, this was also the view taken by this Commission in Rajesh Malhotra & Ors. Vs. Acron Developers Pvt. Ltd. & Ors. First Appeal No. 1287 of 2014 decided on 05.11.2015.”
The principle of law, laid down, in the aforesaid cases, is fully applicable to the present case. The complainant, thus, fall within the definition of a ‘consumer’, as defined under Section 2(1)(d) of the Act. Such an objection, taken by the opposite parties, in their written reply, therefore, being devoid of merit, is rejected.
According to Section 17 of the Act, a consumer complaint can be filed, by the complainant, before the State Consumer Disputes Redressal Commission, within the territorial Jurisdiction whereof, a part of cause of action arose to him. In the instant case, it is evident from the Allotment Letter/Agreement, containing detailed terms and conditions, is executed between the parties at Chandigarh. Besides as above, all the letters (except few) placed on record, clearly goes to reveal that the same have been issued by Chandigarh Office of the Company, as its first address therein is mentioned as “SCO 143-144, First Floor, Sector 8C, Madhya Marg, Chandigarh. Since, as per the documents, referred to above, a part of cause of action arose to the complainant, at Chandigarh, this Commission has got territorial Jurisdiction to entertain and decide the complaint. The objection taken by the opposite parties, in their written version, in this regard, therefore, being devoid of merit, must fail, and the same stands rejected.
In view of above, the opposite parties are also liable to pay compensation to the complainant, for causing mental agony, physical harassment and deficiency in providing service.
At the same time, it is also submitted that the opposite parties cannot evade their liability, merely by saying that since the word proposed/tentative was mentioned in the Agreement, for delivery of possession of the plot, as such, time is not to be considered as essence of the contract. Non-mentioning of exact date of delivery of possession of the unit(s) in the Buyer’s Agreement, is an unfair trade practice on the part of the Builder. The builder is bound to mention the exact/specific date of delivery of possession of the unit(s) to the allottees/purchasers thereof. It was so said by the Hon`ble National Commission, in Rajeev Nohwar & Anr. V/S Sahajanand Hi Tech Construction Pvt Ltd, 2016 (2) CPR 769. Relevant portion of the said case reads thus:-
“Merely making possession by a particular date will also not meet the requirement of law and the promotor is under a legal mandate to stipulate a specific date for delivery of possession of the flat in the agreement which he executes with the flat buyer”.
In view of above, the plea of the opposite parties in this regard also stands rejected.
To decide above said question, it is necessary to reproduce the provisions of Section 3 of the Consumer Protection Act 1986 (in short the Act), which reads as under;
“3. Act not in derogation of any other law.—
The provisions of this Act shall be in addition to and not in derogation of the provisions of any other law for the time being in force.”
It is also desirable to reproduce unamended provisions of Section 8 of 1996 Act, which reads thus:-
“8. Power to refer parties to arbitration where there is an arbitration agreement.—
(1) A judicial authority before which an action is brought in a matter which is the subject of an arbitration agreement shall, if a party so applies not later than when submitting his first statement on the substance of the dispute, refer the parties to arbitration.
(2) The application referred to in sub-section (1) shall not be entertained unless it is accompanied by the original arbitration agreement or a duly certified copy thereof.
(3) Notwithstanding that an application has been made under sub-section (1) and that the issue is pending before the judicial authority, an arbitration may be commenced or continued and an arbitral award made.”
Many a times, by making reference to the provisions of Section 8 of 1996 Act, in the past also, such objections were raised and the Hon'ble Supreme Court of India, when interpreting the provisions of Section 3 of 1986 Act, in the cases of Fair Air Engg. Pvt. Ltd. & another Vs. N. K. Modi (1996) 6 SCC 385, C.C.I Chambers Coop. Housing Society Ltd. Vs Development Credit Bank Ltd. (2003) 7 SCC 233, Rosedale Developers Private Limited Vs. Aghore Bhattacharya and others, (Civil Appeal No.20923 of 2013) etc., came to a conclusion that the remedy provided under Section 3 of 1986 Act, is an independent and additional remedy and existence of an arbitration clause in the agreement, to settle disputes, will not debar the Consumer Foras, to entertain the complaints, filed by the consumers.
In the year 2015, many amendments were effected in the provisions of 1996 Act. After amendment, Section 8 of 1996 Act, reads as under:-
“8. Power to refer parties to arbitration where there is an arbitration agreement.—
(1) A judicial authority, before which an action is brought in a matter which is the subject of an arbitration agreement shall, if a party to the arbitration agreement or any person claiming through or under him, so applies not later than the date of submitting his first statement on the substance of the dispute, then, notwithstanding any judgment, decree or order of the Supreme Court or any Court, refer the parties to arbitration unless it finds that prima facie no valid arbitration agreement exists.”
“In so far as the question of a remedy under the Act being barred because of the existence of Arbitration Agreement between the parties, the issue is no longer res-integra. In a catena of decisions of the Hon’ble Supreme Court, it has been held that even if there exists an arbitration clause in the agreement and a Complaint is filed by the consumer, in relation to certain deficiency of service, then the existence of an arbitration clause will not be a bar for the entertainment of the Complaint by a Consumer Fora, constituted under the Act, since the remedy provided under the Act is in addition to the provisions of any other law for the time being in force. The reasoning and ratio of these decisions, particularly in Secretary, Thirumurugan Cooperative Agricultural Credit Society Vs. M. Lalitha (Dead) Through LRs. & Others - (2004) 1 SCC 305; still holds the field, notwithstanding the recent amendments in the Arbitration and Conciliation Act, 1986. [Also see: Skypak Couriers Ltd. Vs. Tata Chemicals Ltd. - (2000) 5 SCC 294 and National Seeds Corporation Limited Vs. M. Madhusudhan Reddy & Anr. - (2012) 2 SCC 506.] It has thus, been authoritatively held that the protection provided to the Consumers under the Act is in addition to the remedies available under any other Statute, including the consentient arbitration under the Arbitration and Conciliation Act, 1986.”
In view of the above, objection raised by the opposite parties, that in the face of existence of arbitration clause in the Agreement, to settle disputes between the parties through Arbitration, in terms of provisions of Section 8 (amended) of 1996 Act, this Commission has no jurisdiction to entertain the consumer complaint, being devoid of merit, is rejected.
Pronounced.
20.12.2016
Sd/-
[JUSTICE JASBIR SINGH (RETD.)]
PRESIDENT
Sd/-
(DEV RAJ)
MEMBER
Sd/-
(PADMA PANDEY)
MEMBER
Rg.
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.