
View 72 Cases Against Manohar Infrastructure And Constructions Private Limited
Jitender Sheokand filed a consumer case on 10 Dec 2018 against M/s Manohar Infrastructure and Constructions Private Limited in the StateCommission Consumer Court. The case no is CC/300/2018 and the judgment uploaded on 19 Dec 2018.
STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
U.T., CHANDIGARH
Complaint case No. | : | 300 of 2018 |
Date of Institution | : | 24.07.2018 |
Date of Decision | : | 10.12.2018 |
……Complainants
.... Opposite Parties
Argued by: Sh.Savinder Singh Gill, Advocate for the complainants.
Sh.I.P. Singh, Advocate for the opposite parties.
===================================================
Complaint case No. | : | 322 of 2018 |
Date of Institution | : | 21.08.2018 |
Date of Decision | : | 10.12.2018 |
……Complainants
M/s Manohar Infrastructure & Constructions Pvt. Limited, Manohar Campus, SCO No. 139-141, Sector 17-C, Chandigarh, through its Managing Director/Authorized Signatory.
.... Opposite Party
Argued by: Sh.Vishal Gupta, Advocate for the complainants.
Sh.I.P. Singh, Advocate for the opposite party.
Complaints under Section 17 of the Consumer Protection Act, 1986.
BEFORE: JUSTICE JASBIR SINGH (RETD.), PRESIDENT.
MRS. PADMA PANDEY, MEMBER.
MR.RAJESH K. ARYA, MEMBER
PER JUSTICE JASBIR SINGH (RETD.), PRESIDENT
By this order, we propose to dispose of the aforesaid two consumer complaints, filed by the respective complainants. Arguments in the complaints were heard in common, on 29.11.2018. In both the complaints, referred to above, issues involved, except minor variations, here and there, of law and facts are the same and also the complainants have sought refund of the amount paid towards price of their respective plots. As such, during arguments, it was agreed by the contesting parties, that both the complaints can be disposed of, by passing a consolidated order.
By stating that the aforesaid act and conduct of the opposite parties amounted to deficiency in providing service and also adoption of unfair trade practice, the present complaint has been filed, with a prayer to issued directions to them (opposite parties) to refund the amount paid, with interest, compensation etc.
According to Section 17 of the Act, a consumer complaint can be filed, by the complainants, before the State Consumer Disputes Redressal Commission, within the territorial Jurisdiction whereof, a part of cause of action arose to them. In the instant case, perusal of almost all the documents placed on record, pertaining to transaction carried out between the parties, reveals that the same have been issued and received from/by Chandigarh Office of the opposite parties i.e. Manohar Infrastructure and Constructions Pvt. Ltd., SCO No.139-141, Sector 17-C, Chandigarh. Even the documents placed on record, which were issued by Controlling Authority of the opposite parties, with regard to approvals qua the project, in question, are also addressed to their Chandigarh Office, meaning thereby that the opposite parties were carrying out their business at the said office for gains. In view of above, it can safely be said that this Commission has got territorial Jurisdiction to entertain and decide this complaint. Objection taken by the opposite parties, in their written version, in this regard, therefore, being devoid of merit, must fail, and the same stands rejected.
It is specifically brought to our notice, at the time of arguments, by Counsel for the complainants that as per Guidelines (Annexure C-6) to launch project in the mega housing project, (Palm Springs situated in mega housing project), it is not open to the project proponent like the opposite parties, to sell the project to general public without getting proper sanctions/approvals from the Competent Authorities. Condition no.4 (at page 47 of the paper book) of the said Guidelines reads thus:-
“4 Conditions for grant of concessions:-
It is mandated that the project can only be launched when layout/zoning plans are cleared from the Competent Authorities and exemption is granted from operation of the provisions of PAPRA, by the Government concerned. It was also so said in the ‘Letter of Intent’ for the Grant of Special Package of Incentives under Industrial Policy 2009, issued on 03.05.2013 (at pages 55 to 61 of the paper book)) issued in favour of the opposite parties, by the Chief Administrator, PUDA, SAS Nagar, Mohali.
At the time of arguments, it has also come to our notice that when the project was advertised and sold in the year 2011, the opposite parties were not even registered with the GMADA, SAS Nagar, as a qualified project proponent, to obtain license under Section 5 of the PAPRA. Certificate of Registration was granted by the GMADA only on 27.06.2014, permitting the opposite parties to setup a colony subject to their obtaining requisite licenses, as mandated under the provisions of PAPRA.
In view of above, contention of Counsel for the complainants that the project, in question, was sold without any permission(s)/sanction(s) from the Competent Authorities and also violating the provisions of Sections 4 (1) (a) and (b) and 6 of the PAPRA appears to be correct. The said provisions reads thus:-
“4. Issuing of advertisement or prospectus:-
(1) No promoter shall issue an advertisement or prospectus, offering for sale any apartment or plot, or inviting persons who intend to take such apartments or plots to make advances or deposits, unless,-
(a) the promoter holds a certificate of registration under sub-section (2) of section 21 and it is in force and has not been suspended or revoked, and its number is mentioned in the advertisement or prospectus; and
(b) a copy of the advertisement or prospectus is filed in the office of the competent authority before its issue or publication………………”.
“6.(1) Notwithstanding anything contained in any other law for the time being in force, a promoter who intends to construct or constructs a building of apartments, all or some of which are to be taken or are taken on ownership basis, or who intends to offer for sale plots in a colony, shall, before he accepts any sum of money as advance payment or deposit, which shall not be more than twenty five per cent of the sale price, enter into a written agreement for sale with each of such persons who are to take or have taken such apartments, or plots, as the case may be, and the agreement shall be in the prescribed for together with prescribed documents and shall be registered under the Registration Act, 1908 (Central Act no. 16 of 1908);”
“The fact that the project was launched without obtaining necessary permissions/sanctions having been obtained from the Competent Authorities, is further fortified from a document of the opposite parties, placed on record as Annexure O-12 (at page 89 of the file), showing in a tabular format, as to by which dates, approvals, NOCs were granted to them, by the Competent Authorities. Relevant part of the said table is reproduced hereunder:-
Sr.No. | Approval | Dated |
Approval of project | 25.04.2013 | |
NOC from Forest Department | 14.07.2014 | |
Approval of layout plan | 06.10.2015 | |
Approval of zoning plan | 24.11.2015 | |
Permission for solid water, sewerage and storm water disposal | 06.07.2015 | |
Approval of detailed project/services plans of roads, water supply, sewerage, storm water drainage, treated water supply and electrification | 27.11.2015 | |
Grant of Consent to Establish (NOC) Water and Air | 1.12.2015 | |
NOC from Pollution Angle | 15.02.2016 | |
Environment Clearance | 03.06.2016 | |
NOC for electricity connection | 15.03.2017 | |
Extension of Grant of Consent (NOC) Water and Air | 17.04.2017 | |
Permission for Solid Waste Disposal and Storm Water Disposal | 19.05.2017 |
Perusal of the aforextracted table clearly reveals that not even a single permission was available with the opposite parties, when the project, in question, was launched and sold to the customers, including the complainants, in March 2011. As such, the project, in question, was launched in complete derogation of the above said provisions.
Collecting money from the perspective buyers without obtaining the required permissions and sanctions is an unfair trade practice on the part of the project proponent. It is well settled law that it is duty of the builder to first obtain the requisite permissions and sanctions and only thereafter collect the consideration money from the purchasers. It was also so said by the National Commission, in a case titled as M/s Ittina Properties Pvt. Ltd. & 3 Ors. Vs. Vidya Raghupathi & Anr., First Appeal No. 1787 of 2016, decided on 31 May 2018. Relevant part of the said order reads thus:-
“…………….This Commission in Brig. (Retd.) Kamal Sood Vs. M/s. DLF Universal Ltd., (2007) SCC Online NCDRC 28, has observed that it is unfair trade practice on the part of the Builder to collect money from the perspective buyers without obtaining the required permission and that it is duty of the Builder to first obtain the requisite permissions and sanctions and only thereafter collect the consideration money from the purchasers.
It is an admitted fact that the sale deeds were executed in the year 2006 and by 2009 the completion certificate was not issued. The Occupancy Certificate was issued only on 25.09.2017 during the pendency of these Appeals before this Commission. Allotting Plots or Apartments before procuring the relevant sanctions and approvals is per se deficiency…………”
However, in the present case, the opposite parties did not place on record all the documents, referred to, in the table aforesaid. As such, an adverse inference can easily be drawn that had all the said documents been placed on record, the same would have gone against the interest of the opposite parties, as it would have been evident therefrom that when huge amount of Rs.16,20,000/- was received from the complainants on 22.03.2011, they were not even owners of the land, whereupon the project was to be developed. This act amounts to grave unfair trade practice on the part of the opposite parties.
Similar controversy came up for consideration before this Commission, qua this project owned by the opposite parties, in the case of Shaminder Walia and another Vs. M/s Manohar Infrastructure and Constructions Pvt. Limited, Consumer Complaint no.918 of 2016, decided on 08.05.2017 (alongwith six connected cases). Noting similar contentions, this Commission observed as under:-
“To get a plot allotted in the project named as ‘Palm Garden’, first payment was received by the opposite party on 11.01.2012. It is virtually admitted on record that when the project was sold, not even a single permission was available with the opposite party. It is admitted in the written version that part of the project of the opposite party was approved much later, in the year March 2013. Formal Agreement was signed with the Govt. of Punjab on 14.06.2013. Thereafter, additional area was added and supplementary agreement was signed on 16.06.2016. Notification granting exemption from the applicability of the provisions of PAPRA was issued only on 25.01.2017. Perusal of the said notification makes it very clear that exemption given was conditional, as has been referred in para no.5 of the said notification. Besides other conditions, condition no.5 (iii to vii), reads thus:-
“(iii). The promoter shall deposit the entire amount in respect of the contribution to the Punjab Urban Development Fund, created under section 32 of the Punjab Apartment and Property Regulations Act, 1995 (Act No.14 of 1995), within a period of 30 days of the sanctioning of their layout plan.
(iv). The promoter shall acquire the ownership of project land in its name including land under agreement to develop and land under agreement to sell. The plots falling under land proposed to be acquired if any through Govt. acquisition, plot through which revenue rasta or khali passes shall not be developed and sold till these pockets are acquired and ownership is transferred in the name of the Promoter.
(v) The plots/land to which the access is proposed through the land to be acquired if any by the Government shall not be developed and sold till that land under the access is acquired and transferred in the name of the promoter and access is provided.
(vi) The promoter shall be responsible for obtaining the final NOC from Punjab Pollution Control Board.
(vii) Before starting the development of the proposed project promoter shall obtain environmental clearance from the Ministry of Environment and Forest Government of India as required under EIA notification dated 14.9.2006 as well as consent to establish (NOC) from the Punjab Pollution Control Board.”
It is specifically mentioned that before starting development of the proposed project, promoter was to obtain environmental clearance from the Ministry of Environment and Forest Government of India, in terms of EIA notification dated 14.09.2006. There is nothing on record that such clearance was obtained by the opposite party. Further, it was also mentioned that requisite amount be paid towards Punjab Urban Development fund, within a period of 30 days, from the date of sanctioning of layout plans. No evidence has been placed on record, showing payment of the aforesaid amount. Furthermore, it is mandated that the promoter shall also be responsible for getting ‘No Objection Certificate’ from Punjab Pollution Control Board. No document exists on record, showing that such approval was obtained by the opposite party.”.
On perusal of the entire record and documents, we are not going to accept the said arguments. In the case of Shaminder Walia (supra), similar contention was raised and the same was rejected by this Commission, by observing as under:-
“It was contended by Counsel for the opposite party that after issuance of notification dated 25.01.2017 exempting applicability of many provisions of PAPRA qua mega project, the irregularities adopted by it qua sale of plots in the year 2012, etc. stands rectified. In para no.16 of its reply, it was specifically stated by the opposite party that irregularity in accepting expression of interest for sale of the plot in the said project, will have no adverse effect.
We are not going to agree with the contention raised. There is nothing on record that the said notification is retrospective in nature. As stated above, when the project was sold, not even a single permission was available with the opposite party. The sale was made in contravention of the provisions of PAPRA and upon issuance of notification in the month of January 2017, violation committed or admitted irregularities made, cannot be rectified. Similar question qua this very project, came up for consideration before this Commission in Sukhvinder Singh Hayer Vs. M/s Manohar Infrastructure and Constructions Pvt. Limited, Complaint case no.775 of 2016 decided on 23.03.2017 (02 connected cases), wherein it was observed as under:-
“It is specifically mentioned that before starting development of the proposed project, promoter was to obtain environmental clearance from the Ministry of Environment and Forest Government of India, in terms of EIA notification dated 14.09.2006. There is nothing on record that such clearance was obtained by the opposite party. Further, it was also mentioned that requisite amount be paid towards Punjab Urban Development fund, within a period of 30 days, from the date of sanctioning of layout plans. No evidence has been placed on record, showing payment of the aforesaid amount. Furthermore, it is mandated that the promoter shall also be responsible for getting No Objection Certificate from Punjab Pollution Control Board. No document exists on record, showing that such approval was obtained by the opposite party. Contention of Counsel for the opposite party that notification dated 25.01.2017 exempting applicability of many provisions of PAPRA qua mega project, the sale of plots in the year 2011 etc. stands rectified. We are not going to agree with the contention raised. There is nothing on record that the said notification is retrospective in nature. When project was sold, not even a single permission was available with the opposite party. The sale was made in contravention of the provisions of PAPRA and upon issuance of notification in the month of January 2017, violation committed cannot be rectified. Similar question qua this very project, came up for consideration before this Commission in Monika Vs. M/s Manohar Infrastructure and Construction Pvt. Limited, Complaint case no.251 of 2016 decided on 27.09.2016, wherein it was observed as under:-
“The pleadings of the parties indicate that when project was marketed and sold, not even a single permission was available with the project proponent/opposite party. There is a complete violation of the provisions of the PAPRA. It is an admitted case of the opposite party that application seeking exemption from the applicability of provisions of PAPRA is still pending under consideration, with the Authorities concerned. Unless exemption is granted, its violation would amount to adoption of an unfair trade practice, which is glaring and vivid on the part of the opposite party, in this complaint.
Qua a similar project launched by the opposite party in the same area, in Appeal No.248 of 2016, decided on 31.08.2016, titled as M/s Manohar Infrastructure and Constructions Pvt. Limited Vs. Sh.Tilak Raj Bakshi, under similar circumstances, this Commission, while dismissing the said appeal, has observed as under:-
“The documents placed on record clearly show that the project was launched without getting any permission from the Competent Authorities. Detailed brochure was issued showing facilities to be made available in the project launched and its layout plan. It is also on record that when it came to the notice of GMADA that the plots/flats are being sold unauthorizedly by the appellant, it gave a notice in the newspaper ‘Hindustan Times’ dated 18.08.2012, which reads thus:-
“PUBLIC NOTICE
This is for the information of one and all that it has come to the notice of the Competent Authority that one company named as M/s Manohar Singh & Co. is allegedly booking/selling plots in the Mullanpur- Siswan region near Chandigarh border in the State of Punjab. This is being intimated that the above said project is not approved by the State Government. The Competent Authority is initiating legal proceedings in this regard.
If anybody has booked or purchased any plot in the locality mentioned above he/she is advised to contact the undersigned along with documentary proof for further legal action against the said promoter. Further, while buying any plot in any locality falling under the jurisdiction of GMADA, all are advised to visit the website www.gmada.gov.in to verify if the colony/project is approved or not.
Chief Administrator
GREATER MOHALI AREA DEVELOPMENT AUTHORITY, PUDA Bhawan, Sector 62, SAS Nagar”.
It is specifically stated in the notice dated 18.08.2012 that the appellant was allegedly booking/selling the plots in Mullanpur, near Chandigarh Border, in the State of Punjab, unauthorizedly. It was further stated that the project is not approved by the Competent Authority and it (Competent Authority) is initiating legal proceedings against the project proponent for its activity. Above said notice makes it very clear that when the plot was sold on 13.04.2012, the project was not approved by the Competent Authorities. It is also so reflected in the details given by the appellant with this appeal, which is available at page 33 of the paper book. Reading of above said document, makes it very clear that the project was approved by the Government on 25.04.2013; Letter of Intent (LOI) was issued on 03.05.2013; Change of Land Use (CLU) certificate was granted on 31.03.2014; project was registered on 21.06.2014; No Objection Certificate by the District Forest Officer, SAS Nagar, Mohali, was issued on 14.07.2014; Zoning plan was approved by the Chief Town Planner, Punjab on 24.11.2015 and Detailed Project Report (DPR)/Service Plans were approved by the Chief Engineer, GMADA, Mohali, on 27.11.2015. As per established law, if the project proponent sells the project without obtaining necessary permissions or clear title of the acquired land, it would amount to adopting unfair trade practice. It was so said by the Hon’ble National Commission in Atul Maheshwari and ors. Vs. Yamuna Expressway Industrial Development Authority, II (2016) CPJ 623 (NC). Relevant portion of the said judgment reads thus:-
“OP should not have announced the scheme, until or unless they got clear title of the acquired land”.
Similar view was expressed by the National Commission in Emerging India Real Assets Pvt. Ltd. and another vs. Kamer Chand and another, Revision-Petition No.756 of 2016, decided on 30.03.2016. In that case, when upholding the findings given by this Commission, that the project cannot be even marketed before getting approvals/sanctions, from the Competent Authorities, to launch it, it was observed by the National Commission, as under:-
“We are unable to persuade ourselves to agree with the ld. counsel. While affirming the order passed by the District Forum and commenting and deprecating the conduct of the opposite parties in the complaint, in launching the project and selling the farmhouses, even without obtaining sanction/approval from the competent authority, the State Commission has observed as follows:-
If a marketing agency sells out a project, for which, no approvals/sanctions have been granted by the Govt. Authorities, the said agency has to face the music and consequences of duping the gullible buyers, of their hard-earned money. In the public notice, it has specifically been mentioned by the GMADA that respondent no.2 and appellant no.1 are the sister concern. It is also apparent on record that before appellant no.1 started marketing the project, not even an application has been filed by respondent no.2, to get approval/sanction from the competent authorities, to launch the project. The information supplied vide letter dated 26.08.2014, referred to above, clearly states that not even a single application qua granting sanction to the project, has been received and dealt with, by the Competent Authority. In connivance with each other, the appellants and respondent no.2 committed a criminal offence of cheating. As per established law, builder cannot sell its property, unless and until proper approvals/sanctions have been obtained by it, from the Competent Authorities. It appears from the reading of documents on record that instead of selling a unit in a project, respondent no.2 in a very arbitrary manner, sold its share in a joint land measuring approx. 3807 acres, bearing hadbast No.326, Khewat No.92, Khatauni no.254-352, at Village Mirzapur, District Mohali, Punjab. There is nothing on record that said land was ever partitioned.
6. We are in complete agreement with the view taken by the State Commission. As noted above, the petitioners happen to be body corporate. Before offering the farmhouses in the said project as Agent of Respondent No. 2, they must be aware about the status of the sanction for launch of the project. Therefore, it is beyond one’s comprehension that the present Petitioner was not aware about the actual state of affairs for which only the developer could be held responsible.”
In the present case also, there is nothing on record that when expression of interest/applications were invited to sell the said project, clear intimation was given to the intending purchasers that the project sold was in infancy stage and it will take years together before necessary permissions will be provided by the Competent Authorities.”
“It was vehemently contended by Counsel for the opposite party that once exemption from the applicability of the provisions of PAPRA stood granted in the year January 2017, it will relate back to the date of launching of the project, and all irregularities stands rectified. To support above said contention, he has placed reliance on the ratio of judgment passed by the Hon’ble Supreme Court of India, titled as M/s Murudeshwara Ceramics Ltd. Vs. State of Karnataka, 2002 (1) R.C.R. (Civil) 130.
We are not going to accept the arguments raised. It has already been held in Sukhvinder Singh Hayer` case (supra) that upon issuance of notification in the month of January 2017, granting exemption from the applicability of the provisions of PAPRA, violation committed prior thereto, cannot be rectified. To so say, in Sukhvinder Singh Hayer` case (supra), reliance was also placed upon the judgment passed by this Commission in Monika`s case (supra). The said finding was given in consonance with the findings of the National Commission in Emerging India Real Assets Pvt. Ltd. and another vs. Kamer Chand and another`s case (supra).
As far as the reliance placed by Counsel for the opposite party on M/s Murudeshwara Ceramics` case (supra) is concerned, we have gone through the facts of the same very carefully and found that the same were altogether different from the facts of the present case. In the case before the Hon’ble Supreme Court of India, when interpreting the provisions of Section 109 of the Karnataka Land Reforms Act, 1961, it was stated that power of the Government to grant exemption with regard to the land, in any area from operation of some of the provisions of the Act, for using the said land for a particular purpose, are to be seen, not at the time of sale/purchase of the land in dispute, but at the time, when it was going to be put for the said use. It was noted that after sale of the land, in dispute, when it was going to be put for industrial use, exemption already stood granted. The position is altogether different; as in the present case, by indulging into selling the project without any sanctions in its hands, the opposite party has committed unfair trade practice, as defined in Section 2 (1) (c) (i) and (iii) of the CP Act.
It is apparent on record that in the year 2012, activities of the opposite party in selling the project, without any sanction were noticed by the Competent Authorities and on 18.08.2012, as a result whereof, notice was published in a newspaper, stating that such sale was illegal. Copy of newspaper dated 18.08.2012, in which the said public notice was issued by the GMADA, is placed on record as Annexure C-10, in consumer complaint bearing no.890 of 2016, titled as Sheela Devi and another Vs. Manohar Infrastructure and Constructions Private Limited.”.
In the present case, it was fairly admitted by Sh.I.P. Singh, Advocate, that the opposite parties are part and parcel of M/s Manohar Singh and Co. Above fact clearly demonstrates that the GMADA, when came to know about unauthorized sale of a project, issued a notice asking general public not to purchase any property from the opposite parties and also contemplated a legal action. However, it appears that no such legal action was taken against the opposite parties. It may be on account of connivance of the opposite parties with Offices of the said Authority.
“The opposite parties are also guilty of adoption of unfair trade practice. It is on record that the complainant booked the unit, in question, in the project aforesaid, on 16.02.2011. She was allotted unit, vide letter dated 23.02.2011, on which date, she had paid an amount of Rs.4 lacs. Buyer’s Agreement was not put for signing in a reasonable time, say two to three months. She continued to make payment and when Buyer’s Agreement was got signed, on 18.08.2011, she had already paid an amount of Rs.21,68,524/-. By not offering Buyer’s Agreement, for signing in a reasonable time, the opposite parties also committed unfair trade practice. The complainant is a widow. Her interest needs to be protected”.
At the same time, it is also held that merely taking a bald plea, in the absence of any documentary evidence, saying that the complainants were asked, number of times, to come forward for execution of buyer’s agreement, is of no help to the opposite parties. Not even a single document has been placed on record, in this case, by the opposite parties, asking the complainants, to come for signatures of Buyer’s Agreement. However, as far as letters dated 01.05.2014, 02.07.2014 and 29.07.2015 Annexures O-1, O-2 and O-3 are concerned, it may be stated here that vide the said letters, the opposite parties demanded further amount from the complainants. In those letters, there is no mention about the allotment letter or buyer’s agreement. As such, no help therefore can be drawn by the opposite parties from the letters, referred to above. As such, in the present case, by not offering Buyer’s Agreement, for signing in a reasonable time, or even till date, the opposite parties committed unfair trade practice and are also deficient in providing service.
Such a plea has been taken just to raise it without any material on record. It may be stated here that if the application to get necessary permissions, was moved in the year 2011 before the Competent Authorities, what happened thereafter; whether any objection was raised; whether at any point of time, it was taken up with the Authorities concerned, to give permission(s), within three months, as per Rules or not, has not been made clear. There is nothing on record that when the Competent Authorities allegedly did not grant permissions/approvals and delayed the matter, any reminders were sent to them, to do the needful. Not even a single document has been placed on record that the Competent Authorities delayed the matter deliberately, despite the fact that necessary steps were taken at the end of the opposite parties, for obtaining requisite permissions, for launching and selling the said project. At the same time, there is nothing on record, whether any Officer(s) of the Management of this Company was/were the member(s) of any political party; they ever contested any election; and whether question of rivalry causing delay on account of political reasons was ever taken up before the Competent Fora/Court of Law. It is on record that to get necessary permission qua the land in the project, applications were moved in parts. The opposite parties continued to purchase land and continued moving the applications, to the Authorities. In this view of the matter, the plea taken by the opposite parties, stands rejected.
It may be stated here that as regards the alleged shortage of construction material like sand etc. in the market, nothing has been placed on record, by the opposite parties, to prove that it was unable to procure the said construction material, in adequate quantity. There is no evidence of the opposite parties having invited tenders for supply of construction material and there being no response to such tenders. A similar plea for delay in delivery of possession of the units, was taken by a builder, before the Hon`ble National Consumer Disputes Redressal Commission, New Delhi, in Consumer Case No.347 of 2014, titled as Swaran Talwar & 2 others v. M/s Unitech Limited (along three connected complaints), decided on 14 Aug 2015, which was rejected and the complaint was allowed in favour of the complainant. The principle of law, laid down, in the aforesaid case is fully applicable to be present case. In the present case also, the opposite parties failed to convince this Commission, that they actually encountered force majeure circumstances, as a result whereof, delay in handing over possession of the unit occurred. As such, the stand taken by the opposite parties, in this regard, is rejected.
We are not going to accept this contention. In the present case, a specific plea has been taken by the complainants that they being family friends had purchased the plot, in question, with an intention to construct a two storied house, for living together, with their respective families. No law including the CPA Act debars two family friends, to buy one plot and build the same, as per their convenience to reside therein alongwith their families. At the same time, there is nothing on the record that the complainants are property dealers, and deal in the sale and purchase of property, on regular basis, and as such, the plot, in question, was purchased by them, by way of investment, with a view to resell the same, as and when, there was escalation in the prices thereof. They waited for more than six years and have then filed this consumer complaint. Thus, in the absence of any cogent evidence, in support of the objection raised by the opposite parties, mere bald assertion to that effect, cannot be taken into consideration. Since the opposite parties have levelled allegations against the complainants, the onus lay upon them, to place on record, documentary evidence in that regard, which they failed to do so. Otherwise also, in a case titled as Kavita Ahuja Vs. Shipra Estate Ltd. and Jai Krishna Estate Developer Pvt. Ltd. 2016 (1) CPJ 31, by the National Consumer Disputes Redressal Commission, New Delhi, it was held that the buyer(s) of the residential unit(s), would be termed as consumer(s), unless it is proved that he or she had booked the same for commercial purpose. Similar view was reiterated by the National Commission, in DLF Universal Limited Vs Nirmala Devi Gupta, 2016 (2) CPJ 316. Not only as above, recently under similar circumstances, in a case titled as Aashish Oberai Vs. Emaar MGF Land Limited, Consumer Case No. 70 of 2015, decided on 14 Sep 2016, the National Commission, while rejecting similar plea raised by the builder, observed as under:-
“ In the case of the purchase of the houses which a builder undertakes to construct for the buyer, the purchase can be said to be for a commercial purpose where it is shown, by producing evidence, that the buyer is engaged in the business of a buying and selling of houses and or plots as a trading activity, with a view to make profits by sale of such houses or plots. A person cannot be said to have purchased a house for a commercial purpose only by proving that he owns or had purchased more than one houses or plots. In a given case, separate houses may be purchased by a person for the individual use of his family members. A person owning a house in a city A may also purchase a house in city B for the purpose of staying in that house during short visits to that city. A person may buy two or three houses if the requirement of his family cannot be met in one house. Therefore, it would not be correct to say that in every case where a person owns more than one house, the acquisition of the house is for a commercial purpose. In fact, this was also the view taken by this Commission in Rajesh Malhotra & Ors. Vs. Acron Developers Pvt. Ltd. & Ors. First Appeal No. 1287 of 2014 decided on 05.11.2015.”
The principle of law, laid down, in the aforesaid cases, is fully applicable to the present case. The complainants, thus, fall within the definition of a ‘consumer’, as defined under Section 2(1)(d) of the Act. Such an objection, taken by the opposite parties, therefore, being devoid of merit, is rejected.
“I am in agreement with the learned senior counsel for the complainants that considering the default on the part of opposite parties no.1 and 2 in performing its contractual obligation, the complainants cannot be compelled to accept the offer of possession at this belated stage and therefore, is entitled to refund the entire amount paid by him along with reasonable compensation, in the form of interest.”
Not only as above, in a case titled as Brig Ajay Raina (Retd.) and another Vs. M/s Unitech Limited, Consumer Complaint No.59 of 2016, decided on 24.05.2016, wherein possession was offered after a long delay, this Commission, while relying upon the judgments rendered by the Hon`ble National Commission, ordered refund to the complainants, while holding as under:-
“Further, even if, it is assumed for the sake of arguments, that offer of possession, was made to the complainants, in July 2015 i.e. after a delay of about three years, from the stipulated date, even then, it is not obligatory upon the complainants to accept the same.
Furthermore, in another case titled as M/s. Emaar MGF Land Ltd. & Anr. Vs. Dr.Manuj Chhabra, First Appeal No.1028 of 2015, decided on 19.04.2016, the Hon’ble National Commission, under similar circumstances, held as under:-
“I am of the prima facie view that even if the said offer was genuine, yet, the complainants was not obliged to accept such an offer, made after a lapse of more than two years of committed date of delivery”.
The above view taken by the National Commission, has been reiterated by it, recently in the case titled as Sujay Bharatiya & Anr. Vs. Unitech Reliable Projects Pvt. Ltd., Consumer Case No. 1814 of 2017 decided on 05.07.2018. Relevant part of the said order reads thus:-
“This Commission in Emaar MGF Land Ltd. & Anr. V. Amit Puri (First Appeal No.250 of 2014), decided on 30.03.2015, has held that if the Developer fails to deliver possession of the allotted plot/flat within the stipulated time, the allottee is under no obligation to accept an alternative plot. At the cost of repetition, we may reiterate that in the event of Developer failing to deliver possession of the property within the stipulated period, for any reason, save and except a force majeure condition, agreed to between the contracting parties, an allottee cannot be compelled to accept an alternate site/plot and he would be within his rights to seek refund of the amount deposited with the Developer against allotment”.
However, in the present case, as stated above, possession of the unit has not even been offered, what to speak of delay in offering thereof. The complainants, are, thus, entitled to get refund of amount deposited by them. In view of above facts of the case, the opposite parties are also under an obligation to compensate the complainants, for inflicting mental agony and causing physical harassment to them, as also escalation in prices.
First coming to the Supplementary Agreement dated 16.06.2016, it may be stated here that we have gone through the contents thereof, and are of the considered opinion that it is of no help to the opposite parties, as far delay in delivery of possession of the plot, in question, to the complainants is concerned. The said Agreement was signed between the opposite parties and the Govt. of Punjab, only in relation to permission sought by them (opposite parties), vide letter dated 25.08.2015 (after about more than three and a half years of booking of the present plot), for addition of 94.60 acres of more land in the project area. It was on account of this reason, that supplementary agreement was executed.
At the same time, if this plea taken by the opposite parties that since supplementary agreement was executed on 16.06.2016 between them and the Govt. of Punjab and as such, now they (opposite parties) are liable to hand over possession of the plot to the complainants latest by 13.06.2018, is considered in favour of the opposite parties, then it would amount to admittance on their (opposite parties) part that till 16.06.2016, they were not in possession of the land even, but on the other hand, they had booked a plot and received 30% of the price of the plot, as far as back in 2011 and thereafter an amount of Rs.10,80,000/- on 22.08.2013. Furthermore, it is not clarified by the opposite parties that if the land for plot was ultimately got in their hands, by way of supplementary agreement dated 16.06.2016, then for which land, they were talking about in the application acknowledgment receipt dated 22.08.2013 Annexure C-2 issued in favour of the complainants, saying that all layout plans, specification and other details are tentative. If this is so, it amounts to grave unfair trade practice on the part of the opposite parties, as they had received an amount of Rs.16,20,000/- against a plot by March 2011, but on the other hand, till 15.06.2016, they have not even acquired land for the same (plot).
Now coming to the letter dated 13.07.2018, Annexure O-5, we have gone through the same and found that extension has been granted to the opposite parties by RERA only with regard to registration of the project. This letter cannot be made a basis to say that the opposite parties were given any immunity out of the deficiencies and unfair trade practice, adopted by them, in respect of the plot, in dispute. Even otherwise, the said extension of registration has been given in respect of the project namely “The Palm (Palm Downtown/Palm Central Bay)” and not the Palm Springs.
Sequence of events narrated above, clearly goes to prove that the conduct of the opposite parties, throughout remained contumacious. As stated above, not even a single permission to launch the project was available with the opposite parties at the relevant time. As has been discussed in earlier part of this order, permissions continued to pour in, upto the year 2017. Even as on today, there is nothing on record to show that development at the site is complete. It can safely be said that the complainants were well within their right, to file this complaint. It was nowhere agreed to between the parties, at the time of booking of the said plot, that the complainants can be made to wait for an indefinite period.
At the same time, in the face of plea having been taken by the opposite parties that they were required to deliver possession of the plot to the complainants by 13.06.2018, as per the terms and conditions of the supplementary Agreement, or by 31.07.2019, referred to above, as such, in the same breath taking a plea that the present case is beyond limitation or that time is not to be considered as essence of the contract, is not sustainable in the eyes of law and is accordingly rejected. Even otherwise, it is not the proven case of the opposite parties that they were ready with delivery of possession of the plot, within a reasonable period of about two to three years, from the date of booking or say by 13.06.2018 even, but the complainants, failed to take the same, on account of some personal grounds/financial constraints. It is settled law that in the cases, where possession of the residential units is not offered by the builder, there is a continuing cause of action, in favour of the allottee/purchaser.
We are not inclined to accept this argument. At the time of arguments, it is very fairly admitted by Counsel for the contesting parties, that the provisions of RERA are prospective in nature. It was also so said by the High Court of Bombay in the case of NeelKamal Realtors Suburban Pvt. Ltd. and anr. Vs. Union of India and ors. 2018 (1) R.C.R. (Civil) 298. It is an admitted fact that under the RERA, the opposite parties got themselves registered their project, only on 15.09.2017. Some of the provisions of RERA came into operation on 01.05.2016 and even the remaining of it, in May 2017. In all, the grievance has been raised by the complainants qua wrongful act/mistake done leading to deficiency in providing service and adoption of unfair trade practice, in selling the project by the opposite parties without sanctions/approvals, before coming into existence of RERA. Reading of the provisions of Section 88 of RERA makes it very clear that the same are in addition and not in derogation of the provisions of any other law for the time being in force. Section 79 of the RERA further makes it very clear that jurisdiction of only the Civil Court to entertain a suit or proceedings qua action taken as per the provisions of the said Act, is barred.
It may be stated here that the Consumer Foras under the Act, 1986 despite having some trappings of a Civil Court are not the Civil Courts. As such, the jurisdiction of the Consumer Foras is not debarred, to entertain the complaints filed by consumers, alleging deficiency in providing service, negligence and adoption of unfair trade practice against the opposite parties. Intention of the framers of law has been made clear by the concerned Department i.e. Ministry of Housing and Urban Property Alleviation, Government of India in its website “85. Are the civil courts and consumer forums barred from entertaining disputes under the Act? As per section 79 of the Act civil courts are barred from entertaining disputes (suits or proceedings) in respect of matters which the Authority or the adjudicating officer or the Appellate Tribunal is empowered under the Act to determine. However, the consumer forums (National, State or District) have not been barred from the ambit of the Act. Section 71 proviso permits the complainant to withdraw his complaint as regards matters under section 12, 14, 18 and section 19, from the consumer forum and file it with the adjudicating officer appointed under the Act. 86. Can a complainant approach both the Regulatory Authority/adjudicating officer and the consumer forums for the same disputes? The laws of the country do not permit forum shopping, thus, an aggrieved can only approach one of the two for disputes over the same matter.” It was also so said by the State of Punjab in its Official Website Portal rera.punjab.gov.in. The above fact clearly indicates that in the face of provisions of the RERA, any action taken under the provisions of Act 1986 is not debarred. Be that as it may, a similar question came up for consideration, before this Commission, when considering the applicability of the provisions of Section 8 (amended) of Arbitration Act 1996 Act viz a viz CPA 1986, in the case of ‘Sarbjit Singh Vs. Puma Realtors Private Limited’, IV (2016) CPJ 126, wherein, while relying upon ratio of judgments of the Hon’ble Supreme Court, titled as Fair Air Engg. Pvt. Ltd. & another Vs. N. K. Modi (1996) 6 SCC 385, C.C.I Chambers Coop. Housing Society Ltd. Vs Development Credit Bank Ltd. (2003) 7 SCC 233, Rosedale Developers Private Limited Vs. Aghore Bhattacharya and others, (Civil Appeal No.20923 of 2013), Secretary, Thirumurugan Cooperative Agricultural Credit Society v. M. Lalitha (2004) 1 SCC 305 and United India Insurance Co. Ltd. Vs. M/s Pushpalaya Printers, I (2004) CPJ 22 (SC), and LIC of India and another Vs. Hira Lal, IV (2011) CPJ 4 (SC), it was held that even in the face of existence of arbitration clause in an Agreement/Allotment Letter, to settle disputes between the parties through Arbitration, in terms of provisions of Section 8 (amended) of 1996 Act, this Commission has jurisdiction to entertain the consumer complaint. It was authoritatively said that in view of Section 3 of the Act 1986, it is open to the consumers to approach the Consumer Foras, for redressal of their grievance, notwithstanding that he/she can get relief under any other Act. Similar findings, to the effect that an Arbitration Clause in the Agreements between the complainant(s) and the Builder cannot circumscribe the jurisdiction of a Consumer Fora, notwithstanding the amendments made to Section 8 of the Arbitration Act, has been upheld by the Hon’ble Supreme Court of India, in Civil Appeal bearing No.23512-23513 of 2017, vide order dated 13.02.2018. In view of above findings, we can safely say that provision of the RERA and PAPRA will not debar the jurisdiction of this Commission in entertaining the complaints filed by a consumer alleging deficiency in providing service, negligence and adoption of unfair trade practice, on the part of the opposite parties. “Furthermore, as is evident from the documents on record, the appellant is also guilty of violation of Section 6 of the Punjab Apartment and Property Regulation Act, 1995, (in short the PAPRA Act). In a very deceptive manner, an attempt has been made to show actual sale of plot, as an expression of interest. As has been held in earlier part of this order, vide document Annexure C-2, the terms and conditions of sale settled to make payment was also made available. Once it is so, by not offering the Buyers Agreement for signing in a reasonable time, say two to three months but on the other hand, after a lapse of many years of the sale of plot, the appellant has committed an unfair trade practice.” In Consumer complaint bearing no.300 of 2018, opposite parties no.1 to 3, jointly and severally are directed as under:- In Consumer complaint bearing no.322 of 2018, the opposite party is directed as under:- Pronounced. 10.12.2018 Sd/- [JUSTICE JASBIR SINGH (RETD.)] PRESIDENT Sd/- (PADMA PANDEY) MEMBER Sd/- (RAJESH K. ARYA) MEMBER Rg.
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.