
Jagdish Chander Singal filed a consumer case on 26 Sep 2019 against M/s Emaar MGF Land Limited in the StateCommission Consumer Court. The case no is CC/13/2018 and the judgment uploaded on 30 Sep 2019.
STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
U.T., CHANDIGARH
Complaint case No. | : | 13 of 2018 |
Date of Institution | : | 10.01.2018 |
Date of Decision | : | 26.09.2019 |
Jagdish Chander Singal S/o Late Sh.Hant Ram Singal, residing at: 502, GH-34, Sector 5, MDC, Panchkula-134114.
……Complainant
Site Address:- 40, Central Plaza, The Views at Mohali Hills, Sector 105, Mohali-160062.
….Opposite Parties
Complaint under Section 17 of the Consumer Protection Act, 1986.
BEFORE: JUSTICE RAJ SHEKHAR ATTRI, PRESIDENT.
MRS. PADMA PANDEY, MEMBER.
Argued by: Sh.Jagdish Chander Singal, complainant in person.
Sh.Ashim Aggarwal, Advocate for the opposite parties.
JUSTICE RAJ SHEKHAR ATTRI, PRESIDENT
The complainant has filed this complaint, seeking refund of amount of Rs.50,21,500/- paid by him, to the opposite parties, towards purchase of plot bearing No.104-EP-3-250, measuring 250 square yards, in their project named ‘Mohali Plots’. Mohali Hills, Sector 104, Mohali, Punjab (in short, the project). Total price of the said plot was fixed at Rs.52,34,000/-. It is specific case of the complainant that despite making payment of substantial amount equal to about 95% of the total sale consideration, the opposite parties failed to offer possession of the said plot on or before 12.12.2012 as committed vide Clause 8 of the ‘Plot-Buyer`s Agreement’ dated 13.12.2011 i.e. within a period of 12 months from the date of execution thereof. A number of visits were made by the complainant to the project site and also the office of the opposite parties, to know the reason of delay in offering and delivering possession of the plot in question but of no avail. Later on, it transpired that there was some issue with regard to road in front of the plot in question. Number of emails were written by the complainant to the opposite parties, requesting them to complete development work; deliver possession of the plot to him; and also, to pay compensation for the period of delay but of no avail. On the other hand, vide letter dated 05.08.2016 (Annexure C-21) it was informed to him that the area of the plot stands revised to 250.05 square yards as a result whereof, the price thereof stood increased to Rs.56,71,205/-. In the said letter, it was also informed that process to hand over possession of the plot will commence within 60 days. He was asked to make payment of Rs.13,99,711/- on or before 05.09.2016. It has been pleaded that the opposite parties charged various illegally charges. Upon receipt of letter dated 05.08.2016, the complainant visited the project site and found that basic amenities such as club, hospitals, schools, connectivity to the roads, electricity, water etc. were not in existence. As such, he challenged the demand raised by the opposite parties, by way of writing number of letters/emails and also requested them to complete the development work and provide basic amenities but of no avail. He also met various Officials/Officers of the opposite parties, to whom photographs showing incomplete development at the project site were also handed over but his grievance was not redressed. It has been stated that during visits of the complainant, in the years 2016 and 2017, it was found that entry/main access to the project site has been sealed by the Forest Department. Left under no choice, the complainant sought refund of the amount paid alongwith interest but of no avail.
It has been averred that the aforesaid act of the opposite parties caused lot of harassment, mental agony and financial loss to the complainant, as he has been paying heavy installments to the HDFC Limited, from which he had raised loan for making payment towards price of the said plot. Hence, the present complaint has been filed by the complainant, seeking refund of amount paid alongwith interest, compensation etc.
As such, objection raised by the opposite parties, in this regard, stands rejected.
According to Section 17 (2) of the Act, a consumer complaint can be filed, by the complainant, before the State Consumer Disputes Redressal Commission, within the territorial Jurisdiction whereof, a part of cause of action arose to him. We have gone through the record and it is evident that the Plot Buyer’s Agreement dated 13.12.2011 (Annexure C-4) has been executed between the parties at Chandigarh. Apart from this, there are number of documents placed on record, including the payment receipts, which reveal that the correspondence took place between the complainant and the Company, at its Chandigarh Office. Under these circumstances, since part of cause of action accrued to the complainant at Chandigarh, as such, this Commission has got territorial jurisdiction to entertain the present complaint, in view of the provisions of Section 17 (2) of the Act. Objection taken by the opposite parties, in this regard, therefore, being devoid of merit stands rejected.
Under above circumstances, we are fully satisfied with the clarification given by the complainant, in the replication filed. Furthermore, there is nothing, on the record, that the complainant is a property dealer and deals in the sale and purchase of property, on regular basis. Mere fact that the family members of complainant have also purchased properties in their names, is not sufficient to debar him from the purview of a ‘consumer’. A person cannot be said to have purchased a house for a commercial purpose only by proving that he/she has purchased more than one houses or plots. Separate plots may be purchased by a person for the individual use of his/her family members. A person may buy more than one house as per his requirements. Thus, in the absence of any cogent evidence, in support of the objection raised by the opposite parties, mere bald assertion to that effect, cannot be taken into consideration. Apart from it, the opposite parties failed to adduce an iota of evidence to recluse the complainant from the definition of ‘consumer’ under the Act. Otherwise also, in a case titled as Kavita Ahuja Vs. Shipra Estate Ltd. and Jai Krishna Estate Developer Pvt. Ltd. 2016 (1) CPJ 31, decided by the National Consumer Disputes Redressal Commission, New Delhi, it was held that the buyer(s) of the residential unit(s), would be termed as consumer(s), unless it is proved that he or she had booked the same for commercial purpose. Similar view was reiterated by the National Commission, in DLF Universal Limited Vs Nirmala Devi Gupta, 2016 (2) CPJ 316 and Aashish Oberai Vs. Emaar MGF Land Limited, Consumer Case No. 70 of 2015, decided on 14 Sep 2016. The principle of law, laid down, in the aforesaid cases, is fully applicable to the present case. In the opinion of this Commission, the complainant falls within the definition of a ‘consumer’, as defined under Section 2(1)(d) of the Act. Such an objection, taken by the opposite parties, therefore, being devoid of merit and stands rejected.
As such, under these circumstances, the question under our consideration is as to whether if the Developer fails to deliver possession of the allotted plot within the stipulated time, the allottee is under obligation to accept the same, or he/she can seek refund of the amount paid. It may be stated here that it is well settled law that non-delivery of possession of plot(s)/unit(s) in a developed project by the stipulated date, is a material violation on the part of a builder and in those circumstances, the allottee is well within his/her right to seek refund of the amount paid. It was so said by the National Commission, in a case titled as Aashish Oberai Vs. Emaar MGF Land Limited, Consumer Case No. 70 of 2015, decided on 14 Sep 2016, wherein, it was held as under:-
“I am in agreement with the learned senior counsel for the complainants that considering the default on the part of opposite parties no.1 and 2 in performing its contractual obligation, the complainants cannot be compelled to accept the offer of possession at this belated stage and therefore, is entitled to refund the entire amount paid by him along with reasonable compensation, in the form of interest.”
The above view taken by the National Commission, has been reiterated by it, in the case titled as Sujay Bharatiya & Anr. Vs. Unitech Reliable Projects Pvt. Ltd., Consumer Case No.1814 of 2017 decided on 05.07.2018. Relevant part of the said order reads thus:-
“This Commission in Emaar MGF Land Ltd. & Anr. V. Amit Puri (First Appeal No.250 of 2014), decided on 30.03.2015, has held that if the Developer fails to deliver possession of the allotted plot/flat within the stipulated time, the allottee is under no obligation to accept an alternative plot. At the cost of repetition, we may reiterate that in the event of Developer failing to deliver possession of the property within the stipulated period, for any reason, save and except a force majeure condition, agreed to between the contracting parties, an allottee cannot be compelled to accept an alternate site/plot and he would be within his rights to seek refund of the amount deposited with the Developer against allotment”.
The above view taken is further supported by the principle of law laid down by the Supreme Court of India in the case titled as Pioneer Urban Land & Infrastructure Ltd. Vs. Govindan Raghavan, Civil Appeal No.12238 of 2018, decided on 02.04.2019. In that case, possession of the unit had been offered during pendency of the complaint after obtaining occupation certificate, though after a delay of 2 years of the stipulated date. The Supreme Court upheld the order of refund of amount paid alongwith interest, passed by the National Commission, while holding as under:-
“In the present case, admittedly the Appellant – Builder obtained the Occupancy Certificate almost 2 years after the date stipulated in the Apartment Buyer’s Agreement. As a consequence, there was a failure to hand over possession of the flat to the Respondent – Flat Purchaser within a reasonable period. The Occupancy Certificate was obtained after a delay of more than 2 years on 28.08.2018 during the pendency of the proceedings before the National Commission.
In Lucknow Development Authority v. M.K. Gupta, this Court held that when a person hires the services of a builder, or a contractor, for the construction of a house or a flat, and the same is for a consideration, it is a “service” as defined by Section 2 (o) of the Consumer Protection Act, 1986. The inordinate delay in handing over possession of the flat clearly amounts to deficiency of service.
In Fortune Infrastructure & Anr. v. Trevor D’Lima & Ors., this Court held that a person cannot be made to wait indefinitely for possession of the flat allotted to him, and is entitled to seek refund of the amount paid by him, along with compensation.
The Respondent – Flat Purchaser has made out a clear case of deficiency of service on the part of the Appellant –
Builder. The Respondent – Flat Purchaser was justified in terminating the Apartment Buyer’s Agreement by filing the Consumer Complaint, and cannot be compelled to accept the possession whenever it is offered by the Builder. The Respondent – Purchaser was legally entitled to seek refund of the money deposited by him along with appropriate compensation.”
In the present case also, there has been an inordinate delay in offering possession of the plot in question. Had the opposite parties placed on record some convincing evidence to prove their case that delay in offering possession occurred on account of force majeure circumstances, the matter would have been different. Since, nothing has been placed on record to substantiate the stand taken by the opposite parties, in that regard, as such, we are of the considered opinion that the complainant is well within his right to terminate the agreement and seek refund of the entire amount paid, by way of filing this complaint. In these circumstances, forfeiture clause contained in the agreement will not be made applicable, as the fault, if any, lays on the part of the opposite parties and not the complainant. The opposite parties cannot be benefited out of the deficiency flown out from their part.
“We have in our Judgment in the case of Ghaziabad Development Authority vs. Balbir Singh reported in (2004) 5 SCC 65 held that in case the amounts have to be refunded, the Interest Act would apply. In our view, in these matters as it is not possible for us to ascertain what was the prevailing rate of interest, we have been directing payment of interest @ 12% from the date the amounts were deposited till repayment.”
Furthermore, the Supreme Court of India in H.P. Housing Board Vs. Janak Gupta, (2009) INSC 627, granted interest @12% p.a. on the amount to be refunded by the builder, while holding as under:-
“We may note that in Haryana Urban Development Authority vs. Darsh Kumar (2005) 9 SCC 449, this Court has said that in future the Forum/Commission will follow the principles laid down by it in the case of Balbir Singh-I(supra).In the light of the aforenoted decisions, the order of the Commission, awarding interest at the rate of 18% per annum cannot be sustained. We are of the view that having regard to the facts and the circumstances of the instant case, award of interest @ 12% per annum would meet the ends of justice. …………………….”.
In view of principle of law laid down by the Supreme Court of India, in the cases referred to in this paragraph, if interest @12% p.a. is awarded to the complainant, from the respective dates of deposits, till realization, that will meet the ends of justice. At the same time, the complainant is also held entitled for compensation towards mental agony and physical harassment, caused to him, at the hands of the opposite parties.
Pronounced.
26.09.2019
Sd/-
[JUSTICE RAJ SHEKHAR ATTRI]
PRESIDENT
Sd/-
(PADMA PANDEY)
MEMBER
Rg
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.