
Inderjit Verma filed a consumer case on 07 Sep 2016 against Emaar MGF Land in the StateCommission Consumer Court. The case no is CC/160/2016 and the judgment uploaded on 08 Sep 2016.
STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
U.T., CHANDIGARH
Complaint case No. | : | 160 of 2016 |
Date of Institution | : | 22.04.2016 |
Date of Decision | : | 07.09.2016 |
All sons of Sh.Manohar Lal Verma and residents of House No.719, Sector 4, Panchkula, Haryana.
……Complainants
.... Opposite Parties No.1 and 2.
….Performa Opposite Party No.3
BEFORE: JUSTICE JASBIR SINGH (RETD.), PRESIDENT.
MR. DEV RAJ, MEMBER.
MRS. PADMA PANDEY, MEMBER
Argued by:
Sh.Sandeep Bhardwaj, Advocate for the complainants.
Sh.Ashim Aggarwal, Advocate for Opposite Parties No.1 & 2.
Ms.Rupali Shekhar Verma, Advocate for Opposite Party No.3
PER PADMA PANDEY, MEMBER
The facts in brief are that the complainants moved an application for a plot measuring 300 sq. yds., in the project of Opposite Parties No.1 and 2 named as Mohali Hills, Punjab in Sector 105, for which, they paid an amount of Rs.10,35,000/- towards booking amount. However, vide provisional allotment letter dated 11.05.2007 (Annexure C-1), the complainants were allotted plot No.461, in Sector 109, Augusta Park in the said project and not in Sector 105. Total basic sale price of the plot was fixed at Rs.34,50,000/-. The complainants were also to pay External Development Charges (EDC) etc. in addition to the basic price of the plot. It was stated that the complainants, vide letter dated 29.05.2007 (Annexure C-2) requested Opposite Parties No.1 and 2 to change the plot in Sector 105 but instead of change of location of the plot, they sent copy of the Agreement (Annexure C-3) in respect of the unit, in question, and refused to change the location of the plot. Left with no alternative, the complainants had to sign the Plot Buyer’s Agreement dated 04.07.2007. It was further stated that as per Clause 8 of the Agreement, Opposite Parties No.1 and 2 were liable to deliver physical possession of residential plot, within a period of 2 years i.e. upto 03.07.2009. It was further stated that the complainants requested Opposite Parties No.1 and 2 to provide necessary documents, as they wanted to raise loan from Opposite Party No.3 but they filed to do so. It was further stated that surprisingly thereafter, the complainants were relocated to plot No.560 from plot No.461 on the pretext that land under plot no.461 is under litigation due to some dispute with the farmers. Addendum Agreement (Annexure C-10) was executed in respect of plot No.561, Augusta Greens, Mohali Hills, Sector 109. Price of plot No.561 was fixed at Rs.40,50,354/-. It was further stated that as and when demands were made, the complainants made timely payment, as a result whereof, they were given rebate of 5% of the basic sale price. It was further stated that the complainants had paid the entire sale consideration to Opposite Parties No.1 and 2. Despite that Opposite Parties No.1 and 2 failed to give possession of plot to the complainants. It was further stated that vide letter dated 28.12.2009 (Annexure C-15) update of status of development was given to the complainants. It was further stated that possession of the plot was not offered to the complainants by the stipulated date. The complainants kept on approaching Opposite Parties No.1 and 2 for delivery of possession but they failed to do so. On 25.06.2014, Opposite Parties No.1 and 2 sent final settlement dues letter demanding Rs.9,26,136.84 without any justification. It was further stated that the demand made was illegal. It was further stated that the complainants sent letter dated 03.03.2015 (Annexure C-21), wherein, they brought their concern to the notice of the Opposite Parties No.1 and 2 but to no avail. However, vide letter dated 24.03.2015 (Annexure C-23), Opposite Parties No.1 and 2 informed the complainants that they had already offered possession of the plot in December, 2009. It was further stated that when the complainants visited the site to see the progress of development, they were surprised to see the same missing. Even basic amenities were not in existence there. The entries to the project were sealed by the Forest Department. Necessary permission and sanctions were not obtained by Opposite Parties No.1 and 2. It was averred that by neither delivering physical possession of plot, in question, to the complainants, and in the alternative by not refunding the amount deposited with interest, Opposite Parties No.1 and 2 were not only deficient, in rendering service, but also indulged into unfair trade practice. When the grievance of the complainants, was not redressed, left with no alternative, a complaint under Section 17 of the Consumer Protection Act, 1986 (in short the ‘Act’ only), was filed.
“In so far as the question of a remedy under the Act being barred because of the existence of Arbitration Agreement between the parties, the issue is no longer res-integra. In a catena of decisions of the Hon’ble Supreme Court, it has been held that even if there exists an arbitration clause in the agreement and a Complaint is filed by the consumer, in relation to certain deficiency of service, then the existence of an arbitration clause will not be a bar for the entertainment of the Complaint by a Consumer Fora, constituted under the Act, since the remedy provided under the Act is in addition to the provisions of any other law for the time being in force. The reasoning and ratio of these decisions, particularly in Secretary, Thirumurugan Cooperative Agricultural Credit Society Vs. M. Lalitha (Dead) Through LRs. & Others - (2004) 1 SCC 305; still holds the field, notwithstanding the recent amendments in the Arbitration and Conciliation Act, 1986. [Also see: Skypak Couriers Ltd. Vs. Tata Chemicals Ltd. - (2000) 5 SCC 294 and National Seeds Corporation Limited Vs. M. Madhusudhan Reddy & Anr. - (2012) 2 SCC 506.] It has thus, been authoritatively held that the protection provided to the Consumers under the Act is in addition to the remedies available under any other Statute, including the consentient arbitration under the Arbitration and Conciliation Act, 1986.”
In view of the above, and also in the face of ratio of judgments, referred to above, passed by the National Commission and this Commission, the arguments raised by Counsel for Opposite Parties No.1 and 2, stands rejected.
According to Section 17 of the Act, a consumer complaint can be filed, by the complainants, before the State Consumer Disputes Redressal Commission, within the territorial Jurisdiction whereof, a part of cause of action arose to them. In the instant case, it is evident from the record, that the Agreement was executed between the parties at Chandigarh. Not only this, even almost all the documents/letters annexed by the complainants with their complaint, were also sent by Opposite Parties No.1 and 2 from their Chandigarh Office, as the same bore the address of the Company as “SCO 120-122, First Floor, Sector 17-C, Chandigarh 160017”. Since, as per the documents, annexed by the complainants, with their complaint, a part of cause of action arose to the complainants, at Chandigarh, this Commission has got territorial Jurisdiction to entertain and decide the complaint. The objection taken by Opposite Parties No.1 and 2, in their written version, in this regard, therefore, being devoid of merit, must fail, and the same stands rejected.
“31. However, the main grouse of the complainant is that, despite relocation to the said units, even then, actual physical possession thereof, was not offered to him, whereas, on the other hand, paper offer was made to him, vide letters dated 25.08.2014 and 07.11.2014, because when he visited the site after receiving the said letters, to see development and basic amenities, the same were found missing and besides that, all entry points of the project, had been sealed by the Forest Department, as opposite parties no.1 and 2, failed to take requisite permissions/sanction from it. Thus, in these circumstances, the principal question, which goes to the root of the case, and falls for consideration, is, as to whether, offer of possession made by opposite parties no.1 and 2, to the complainant, vide letters dated 25.08.2014 and 07.11.2014, in respect of the relocated units, could be said to be genuine offer or not. It is well settled law that the onus to prove that the project had been completed and the area/site, in question, is fully developed is on the builder/opposite parties no.1 and 2. It was so said by the National Commission, in Emaar MGF Land Limited and another Vs. Krishan Chander Chandna, First Appeal No.873 of 2013 decided on 29.09.2014. It is very strange that not even an iota of evidence has been placed, on record, by opposite parties no.1 and 2, to prove that when offer was made to the complainant, in respect of the units, in question, development work was complete and that all the basic amenities were in existence. On the other hand, in case, all the development activities, had been undertaken, and completed at the site, by the said dates, then it was for opposite parties no.1 and 2, which could be said to be in possession of the best evidence, to produce cogent and convincing documentary evidence, in the shape of the reports and affidavits of the Engineers/Architects, as they could be said to be the best persons, to testify, as to whether, all these development activities, had been undertaken and completed at the site or not, but they failed to do so. Opposite parties no.1 and 2 were also required to produce on record, a copy of the Completion Certificate (if obtained), having been issued by the Competent Authority, which could be said to be best evidence, to prove their case, but they miserably failed to do so. It is well settled law that before offering/delivery of possession of unit, in a project, it is mandatory to obtain completion certificate, from the Competent Authority(s), failing which the purchaser is at liberty to say no, to such an offer.
Secondly, the complainant has placed on record, copies of the RTI Information, relating to the said project, in question. Vide RTI Information dated 29.04.2014 Annexure C-31, it was clearly intimated by Greater Mohali Area Development Authority (GMADA), that opposite parties no.1 and 2, had not even applied to them for commission of sewerage treatment plant, water supply, electricity etc. Not only this, it is further evident from RTI Information dated 26.02.2015 Annexure C-30, issued by the Punjab State Power Corporation Limited (PSPCL), that no regular electricity connection has been released in the sector, in question, wherein the plots are situated. The said RTI Information goes unrebutted by opposite parties no.1 and 2. Not even a single document has been brought on record to prove that the information relating to non-existence of basic amenities, mentioned in the said RTI Information is false, or that the said information was fabricated by the complainant. Had the said information been false or fabricated, opposite parties no.1 and 2, could have obtained certificate from the said Authorities, to say that the same had not been supplied from their Department, but they (opposite parties no.1 and 2) failed to do so. Thus, it could safely be said that the complainant has proved his case, that opposite parties no.1 and 2 did not even obtain permission to provide basic amenities such as water, electricity etc., till 29.04.2014 or 26.02.2015, the dates when RTI information aforesaid, was issued by the Authorities concerned.
Not only this, it is also an admitted case, that entry points of the project had been sealed by the Forest Department, as opposite parties no.1 and 2, failed to take requisite permissions/ sanction from it, which fact has also been admitted by them (Opposite Parties no.1 and 2), in paragraph No.26 of their written version. Not only this, the said fact is further corroborated from the letter dated 15.04.2015 Annexure-4 (at page 190 of the file), sent by opposite parties no.1 and 2, to the Chief Administrator, GMADA, requesting it to take up the matter with the Forest Department, regarding sealing of entry points of the project, in question, as the same had been stated to be “illegal access”. It has been clearly mentioned by opposite parties no.1 and 2, in the said letter that “…….we are bound by the agreement to give delivery within time bound manner to our various restive customers, we had applied for grant of access with your good self”. This admission of the opposite parties no.1 and 2, in the letter dated 15.04.2015 written to the Chief Administrator, GAMDA, itself clearly goes to prove that even till that date (15.04.2015), they were not in a position, to deliver possession of the plot(s) to their customers, including the complainant, in the said project, on account of reason that the entries thereof had been sealed by the Forest Department, stating it to be an “illegal access through the Forest Strip”,permissions/sanction, whereof has not been obtained by them. Not even a single piece of evidence has been brought on record, to prove that the said entry points have been got reopened by opposite parties no.1 and 2, after having obtained permission from the Authorities concerned. If it is so, then it remained unclarified by opposite parties no.1 and 2, as to when entry points of the project were sealed, how could they offer possession of the units, to the allottees, including the complainant, in the year 2014.
A plea was also taken by opposite parties no.1 and 2 that only recently the Forest Department has served notice on them, alleging illegal access created by them, through the Forest land. To the contrary, perusal of RTI Information dated 05.05.2015 Annexure C-28 (colly.) (at pages 120 to 127 of the file) issued by the Government of Punjab, reveals that a court case with regard to dispute between the Forest Department and opposite parties no.1 and 2, is pending litigation before the Civil Court Kharar, since 03.07.2012, as opposite parties no.1 and 2 have violated Sections 29,33 and 63 of the Indian Forest Act 1927 and have also violated the directions passed by the Hon'ble Supreme Court of India, vide order dated 12.12.1996. The said RTI Information also goes unrebutted by opposite parties no.1 and 2. Thus, the matter with regard to entry points aforesaid, in respect of the said sector, in dispute, was an old dispute, between the Forest Department and opposite parties no.1 and 2, as they had not taken permission from the Competent Authorities, which fact was not disclosed by them, in their written version, filed before this Commission.
In view of above, it is held that the act of opposite parties no.1 and 2, in offering paper possession of the units, in question, vide letters 25.08.2014 and 07.11.2014, in the absence of development work; basic amenities at the site; non-obtaining of completion certificate, and also entry points of the project being sealed/closed by the Forest Department, amounted to deficiency in providing service and also adoption of unfair trade practice. It is therefore held that the offer of possession made by opposite parties no.1 and 2, vide letters dated 25.08.2014 and 07.11.2014 is nothing, but a paper possession, which is not sustainable, in the eyes of law.
Not only this, since it has been held by this Commission, that offer so made by opposite parties no.1 and 2, was nothing but a paper possession, and till date the complainant is empty handed as neither actual physical possession of the plots was delivered, for want of development work; basic amenities at the site, as also the entry points had been sealed by the Forest Department, as they failed to take requisite permissions/sanction from it, which fact has also been admitted by them (Opposite Parties no.1 and 2), in their written version nor amount deposited was refunded to him alongwith interest, as such, there is continuing cause of action, in favour of the complainant, in view of principle of law laid down, in Lata Construction & Ors. Vs. Dr. Rameshchandra Ramniklal Shah and Anr., II 2000 (1) CPC 269=AIR 1999 SC 380 andMeerut Development Authority Vs. Mukesh Kumar Gupta, IV (2012) CPJ 12 (SC). The principle of law, laid down, in the aforesaid cases, is fully applicable to the facts of the instant case. Under these circumstances, it is held that the complaint was not at all barred by time. The submission of the Counsel for opposite parties no.1 and 2, in this regard, being devoid of merit, must fail, and the same stands rejected.”
Thus it is held that the complaint filed by the complainants is not barred by time. The objection of Opposite Parties No.1 and 2 in this regard is rejected.
Even otherwise, Opposite Parties No.1 and 2 cannot evade their liability, merely by saying that since the word tentative/ proposed/tentative was mentioned in the Agreement, for delivery of possession of the unit, as such, time is not to be considered as essence of the contract. Non-mentioning of exact date of delivery of possession of the unit(s) in the Buyer’s Agreement, is an unfair trade practice, on the part of the Builder. The builder is bound to mention the exact/specific date of delivery of possession of the unit(s) to the allottees thereof. It was so said by the Hon’ble National Commission, in Rajeev Nohwar & Anr. V/S Sahajanand Hi Tech Construction Pvt Ltd, 2016 (2) CPR 769. Relevant portion of the said case reads thus:-
“Merely making possession by a particular date will also not meet the requirement of law and the promotor is under a legal mandate to stipulate a specific date for delivery of possession of the flat in the agreement which he executes with the flat buyer”.
In view of above, the plea of Opposite Parties No.1 and 2 in this regard also stands rejected.
Since we are refunding the whole deposited amount to the complainants alongwith interest, compensation and litigation expenses, therefore, they are not entitled to claim the other relief i.e. to pay the amount of pre EMI, mentioned in the prayer clause of the complaint.
Pronounced.
September 7, 2016
Sd/-
[JUSTICE JASBIR SINGH (RETD.)]
PRESIDENT
Sd/-
(DEV RAJ)
MEMBER
Sd/-
(PADMA PANDEY)
MEMBER
rb
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.