Chandigarh

StateCommission

CC/839/2016

Harbrinder Singh Sandhu - Complainant(s)

Versus

Emaar MGF Land Private Limited - Opp.Party(s)

Arif Quershi Adv. & Dushyant Sarvesh Adv.

28 Mar 2017

ORDER

STATE CONSUMER DISPUTES REDRESSAL COMMISSION,

U.T., CHANDIGARH

 

Complaint case No.

:

839 of 2016

Date of Institution

:

23.11.2016

Date of Decision

:

28.03.2017

 

Harbrinder Singh Sandhu S/o Gurbax Singh Sandhu, resident of H.No. 1024, IInd Floor, Sector 39-B, CHB Flats, Chandigarh – 160036.

……Complainant

V e r s u s

  1. Emaar MGF Land Private Limited, through its Managing Director having its corporate office at SCO No. 120-122, 1st Floor, Sector 17-C, Chandigarh – 160017.  
  2. General Manager, Emaar MGF Land Private  Limited having its corporate office at SCO No.120-122, 1st Floor, Sector 17-C, Chandigarh – 160017.

                                                    .... Opposite Parties

BEFORE:         JUSTICE JASBIR SINGH (RETD.), PRESIDENT

                        MR. DEV RAJ, MEMBER.

                        MRS. PADMA PANDEY, MEMBER

 

Argued by:      

 

Sh.  Arif Qureshi, Advocate for the complainant.

Sh.  Sanjeev Sharma, Advocate for the Opposite Parties.

 

PER PADMA PANDEY, MEMBER

 

               The facts, in brief, are that on the basis of advertisement widely published in the newspapers and brochures by the Opposite Parties, the complainant got interested in their project. The officials of the Opposite Parties introduced the complainant to Mr.Kanwar Pal Singh Kochhar, who had booked a plot measuring 400 sq. yards approximately in the project namely “Pinewood Greens” at Sector 108, Mohali, Punjab. Plot Buyer’s Agreement was executed between the original allottee and the Opposite Parties on 04.07.2007 (Annexure C-1). Thereafter, the complainant executed Agreement to Sell (Annexure C-2) with the original allottee and he applied for transfer of the plot in his favour, for which, the Opposite Parties issued “No Objection Certificate” (Annexure C-3). The plot was endorsed in favour of the complainant on 30.04.2008. The complainant availed loan of Rs.48,00,000/- from HDFC Ltd. Copy of Loan Agreement is Annexure C-4.  As per Clause 8 of the Agreement, possession of the unit was to be delivered within a period of 2 years from the date of execution of the said Agreement i.e. latest by 03.07.2009 but not later than 03.07.2010. It was further stated that the Opposite Parties issued undated letter in the mid of 2009 to the complainant that the area of the plot has been increased to 457 sq. yards and also raised demand of Rs.14,34,282/- on account of increased area and also additional EDC. It was further stated that the complainant contacted the Opposite Parties to know about the development of the project but to his utter dismay, there was no development, at all. The complainant continued to discharge his obligations in terms of the Agreement and deposited all the installments on time, for which, the Opposite Parties offered 5% rebate to the complainant (Annexure C-7). The complainant sent an email to the Opposite Parties asking them to clarify the project timeline. He was shocked to receive a reply stating the basic amenities are still not in place and the Opposite Parties are expecting to get completion by the end of 2013 (Annexure C-8). Thereafter, the complainant wrote another email to the Opposite Parties asking them to clarify about penalty, to which, they admitted the delay and proposed to give penalty, as per the Agreement (Annexures C-9 & C-10). It was further stated that the Opposite Parties sent a letter dated 05.05.2014 (Annexure C-13) to the complainant intimating about the settlement of final dues but when he visited the site, he noticed that there was hardly any development because there were no roads, parks, shopping complex, STP, club etc. in sight. It was further stated that a lot of correspondence were exchanged between the parties regarding the different issues. It was further stated that when the complainant visited India in December, 2014, he was advised to sign indemnity by way of affidavit indemnifying the Opposite Parties against any legal issues arising in future, to which, the complainant had genuine reasons to object for because it being one sided document favouring the interest of Opposite Parties only and is against the public policy. Copy of indemnity cum Undertaking is Annexure C-18. It was further stated that the complainant paid the total amount of Rs.66,95,197/- in respect of the plot, in question but despite receipt of the huge amount, the Opposite Parties after almost 6 years from the date of booking of the plot, failed to offer actual possession of the plot. It was further stated that the aforesaid acts, on the part of the Opposite Parties, amounted to deficiency, in rendering service, and indulgence into unfair trade practice. When the grievance of the complainant, was not redressed, left with no alternative, a complaint under Section 17 of the Consumer Protection Act, 1986 (in short the ‘Act’ only), was filed.

2.           The Opposite Parties, in their joint written version, have taken objection regarding arbitration clause in the Agreement, and also they separately, moved an application u/s 8 of Arbitration and Conciliation Act, 1996 taking a specific objection in this regard for referring the matter to the Arbitrator in terms of the agreed terms and conditions of the Agreement.  It was stated that the plot was earlier allotted to Kanwar Pal Singh Kochhar and the complainant purchased the plot from open market, as such, he did not fall within the definition of “Consumer”, as envisaged in the Consumer Protection Act, 1986. It was further stated that as per Clause 8 of the Agreement, in case of any delay in handing over of possession, the Opposite Parties shall be liable to pay to the allottee penalty, as per the terms of the Agreement and the same has already been credited in the name of the complainant, as per the intimation of possession letter. It was further stated that this Commission has no territorial jurisdiction to try and entertain the complaint, as the unit is situated at Mohali, Punjab and as per the Agreement, only the Courts having territorial jurisdiction over the unit/property shall have the territorial jurisdiction. It was further stated that this Commission has no pecuniary jurisdiction to try and entertain the complaint, in view of the judgment of Ambrish Kumar Shukla vs. Ferrous Infrastructure, the interest is to be added to the relief claimed and in the present case, the amount, as claimed, alongwith interest certainly exceeds the pecuniary jurisdiction of this Commission. It was further stated that both the parties are bound by the terms and conditions of the Agreement and in case of failure of the allottee to perform all obligations as set out in the Agreement, the allottee has authorized the Company to forfeit the earnest money, as stipulated in Clause 2(f) of the Agreement alongwith any interest paid, due or payable, any amount of non refundable nature. It was further stated that the present complaint is not maintainable, as the complainant has failed to implead HDFC Bank, from which, he took a loan, as a party to the complaint. It was admitted regarding purchase of the plot by the complainant from the original allottee. It was further stated that the Company received an amount of Rs.67,14,206/- (out of which Rs.43,000/- were paid against delayed payment charges) against unit No.108-PG-85-400. It was further stated that as per the Agreement, the Company was supposed to try and hand over possession of the unit within 36 months from the date of execution of the Agreement. It was further stated that the compensation is payable for delay in possession (@Rs.50/- sq. yds. per month) as per Clause 8 of the Agreement and the same is payable at the time of IOP. It was averred that the intimation of possession was sent to the complainant on 29.11.2009, so no compensation is payable to him. It was admitted regarding endorsement of the plot in favour of the complainant on 30.04.2008. It was further averred that all the emails of the complainant are duly responded to. The complainant qualified for OTPR (on time payment rebate) as per letter dated 03.02.2009 and credit of the same has been duly given to him. The allegations made by the complainant regarding basic amenities were denied by the Opposite Parties. It was further stated that the Opposite Parties were exempted from seeking completion certificate for their project (Annexure R-3 colly.) and it was only in September, 2014 that the mega projects, which were earlier exempted from seeking completion certificate have been asked to apply for completion certificate and get completion/partial completion certificate. The Opposite Parties duly applied for the completion certificate and have obtained the partial completion certificate for their project. Copy of partial completion certificate is Annexure R-4. It was further stated that the complainant has been duly offered possession of the plot to him on 29.11.2009, however, the complainant, failed to take over the possession and even refused to submit the possession undertaking. It was further stated that the area of the plot is tentative in nature and is subject to change as per Clause No.F of the Agreement. It was further stated that possession was handed over within time and without any delay, and therefore no compensation is payable. It was further stated that neither there was any deficiency, in rendering service, on the part of the Opposite Parties, nor they indulged into unfair trade practice.

3.           The Parties led evidence, in support of their case.

4.           We have heard the Counsel for the parties, and have gone through the evidence and record of the case, carefully. 

5.           The first question, that falls for consideration, is, as to whether, in the face of existence of arbitration clause in the Agreement, to settle disputes between the parties through Arbitration, in terms of provisions of Section 8 (amended) of 1996 Act, this Commission has no jurisdiction to entertain the consumer complaint. This question has already been elaborately dealt with by this Commission in case titled ‘Sarbjit Singh Vs. Puma Realtors Private Limited’, IV (2016) CPJ 126. Paras 25 to 35 of the said order, inter-alia, being relevant, are extracted hereunder:-

25.        The next question, that falls for consideration, is, as to whether, in the face of existence of arbitration Clause in the Agreement, to settle disputes between the parties through Arbitration, in terms of provisions of Section 8 (amended) of  1996 Act, this Commission has no jurisdiction to entertain the consumer complaint.

26.        To decide above said question, it is necessary to reproduce the provisions of  Section 3 of the Consumer Protection Act 1986 (in short the Act), which reads as under;

“3. Act not in derogation of any other law.—

The provisions of this Act shall be in addition to and not in derogation of the provisions of any other law for the time being in force.”

27.                It is also desirable to reproduce unamended provisions of Section 8 of 1996 Act, which reads thus:- 

“8. Power to refer parties to arbitration where there is an  arbitration agreement.—

(1) A judicial authority before which an action is brought in a matter which is the subject of an arbitration agreement shall, if a party so applies not later than when submitting his first statement on the substance of the dispute, refer the parties to arbitration.

(2) The application referred to in sub-section (1) shall not be entertained unless it is accompanied by the original arbitration agreement or a duly certified copy thereof.

(3) Notwithstanding that an application has been made under sub-section (1) and that the issue is pending before the judicial authority, an arbitration may be commenced or continued and an arbitral award made.”

28.      Many a times, by making reference to the provisions of Section 8 of 1996 Act, in the past also, such objections were raised and the Hon'ble Supreme Court of India, when interpreting the provisions of Section 3 of 1986 Act, in the cases of Fair Air Engg. Pvt. Ltd. & another Vs. N. K. Modi (1996) 6  SCC 385, C.C.I Chambers Coop. Housing Society Ltd. Vs Development Credit Bank Ltd. (2003) 7 SCC 233Rosedale Developers Private Limited Vs. Aghore Bhattacharya and others, (Civil Appeal No.20923 of 2013) etc., came to a conclusion that the remedy provided under Section 3 of 1986 Act, is an independent and additional remedy and existence of an arbitration clause in the agreement, to settle disputes, will not debar the Consumer Foras, to entertain the complaints, filed by the consumers.

29.       In the year 2015, many amendments were effected in the provisions of 1996 Act. After amendment, Section 8 of 1996 Act, reads as under:-

 “8. Power to refer parties to arbitration where there is an arbitration agreement.—

(1) A judicial authority, before which an action is brought in a matter which is the subject of an arbitration agreement shall, if a party to the arbitration agreement or any person claiming through or under him, so applies not later than the date of submitting his first statement on the substance of the dispute, then, notwithstanding any judgment, decree or order of the Supreme Court or any Court, refer the parties to arbitration unless it finds that prima facie no valid arbitration agreement exists.”

30.     Now it is to be seen, whether, after amendment in Section 8 of the principal Act, any additional right has accrued to the service provider(s), to say that on account of existence of arbitration agreement, for settling the disputes through an Arbitrator, the Consumer Foras have no jurisdiction to entertain a consumer complaint. As has been held by Hon'ble Supreme Court of India, in various cases, and also of the National Commission, in large number of judgments, Section 3 of the 1986 Act, provides additional remedy, notwithstanding any other remedy available to a consumer. The said remedy is also not in derogation to any other Act/Law.

31.        Now, we will have to see what difference has been made by the amendment, in the provisions of Section 8 of 1996 Act. After amendment, it reads that a Judicial Authority is supposed to refer the matter to an Arbitrator, if there exists an arbitration clause in the agreement, notwithstanding any judgment, decree, order of the Hon'ble Supreme Court of India, or any other Court, unless it finds that prima facie, no valid arbitration agreement exists. The legislation was alive to the ratio of the judgments, as referred to above, in earlier part of this order. Vide those judgments, it is specifically mandated that under Section 3 of 1986 Act, an additional remedy is available to the consumer(s), which is not in derogation to any other Act. As and when any argument was raised, the Hon'ble Supreme Court of India and the National Commission in the judgments, referred to above, have made it very clear that in the face of Section 8 of 1996 Act and existence of arbitration agreement, it is still opened to the Consumer Foras to entertain the consumer complaints. None of the judgments ever conferred any jurisdiction upon the Consumer Foras to entertain such like complaints. Only the legal issues, as existed in the Statute Book, were explained vide different judgments. If we look into amended provisions of Section 8 of the principal Act, it explains  that judicial Authority needs to refer dispute, in which arbitration agreement exist to settle the disputes notwithstanding any judgment/decree or order of any Court. That may be true where in a case,  some order has been passed by any Court, making arbitration Agreement non-applicable to a dispute/parties. However, in the present case, the above said argument is not available. The jurisdiction of Consumer Foras to entertain consumer complaints, in the face of arbitration clause in the Agreement, is in-built in 1986 Act. It was not given to these Foras, by any judgment ever. The provisions of Section 3 of 1986 Act interpreted vide judgments vis a vis Section 8 of un-amended 1996 Act, were known to the legislature, when the amended Act 2015 was passed. If there was any intention on the part of the legislature, then it would have been very conveniently provided that notwithstanding any remedy available in 1986 Act, it would be binding upon the judicial Authority to refer the matter to an Arbitrator, in case of existence of arbitration agreement, however, it was not so said.

32.        We can deal with this issue, from another angle also. If this contention raised is accepted, it will go against the basic spirit of 1986 Act. The said Act (1986) was enacted to protect poor consumers against might of the service providers/multinational companies/traders. As in the present case, the complainant has spent his life savings to get a unit, for his residential purpose. His hopes were shattered. Litigation in the Consumer Fora is cost effective. It does not involve huge expenses and further it is very quick. A complaint in the State Commission can be filed, by making payment between Rs.2000/- to Rs.4000/- (in the present case Rs.4000/-). As per the mandate of 1986 Act,  a complaint is supposed to be decided within three months, from the date of service to the opposite party. In cases involving ticklish issues (like the present one, maximum not more than six months to seven months time can be consumed), whereas, to the contrary, as per the principal Act (1996 Act),  the consumer will be forced to incur huge expenses towards his/her share of Arbitrator’s fees. Not only as above, it is admissible to an Arbitrator, to decide a dispute within one year. Thereafter, the Court wherever it is challenged may also take upto one year and then there is likelihood that the matter will go to the High Court or the Hon'ble Supreme Court of India. Such an effort will be a time consuming and costly one. Taking note of fee component and time consumed in arbitration, it can safely be said that if the matter is referred to an Arbitrator, as prayed, in the present case, it will defeat the very purpose of the provisions of 1986 Act.

33.        The 1986 Act provides for better protection of interests and rights of the consumers. For the said purpose, the Consumer Foras were created under the Act. In Section 3 of 1986 Act, it is clearly provided that the said provision is in addition to and not in derogation of any provisions of any other law, for the time being in force. The 1986 Act is special legislation qua the consumers. The poor consumers are not expected to fight the might of multinational companies/traders, as those entities have lot of resources at their command. As stated above, in the present case, the complainant has spent his entire  life earnings to purchase the plot, in the said project, launched by the opposite party. However, his hopes were shattered, when despite making substantial payment of the sale consideration, he failed to get possession of the  plot, in question, in a developed project. As per ratio of the judgments in the case of Secretary, Thirumurugan Cooperative Agricultural Credit Society v. M. Lalitha (2004) 1 SCC 305 and United India Insurance Co. Ltd. Vs. M/s Pushpalaya Printers, I (2004) CPJ 22 (SC),  and LIC of India and another Vs. Hira Lal, IV (2011) CPJ 4 (SC), the consumers are always in a weak position, and in cases where two interpretations are possible, the one beneficial to the consumer needs to be accepted. The opinion expressed above, qua applicability of Section 8 (amended) of 1996 Act, has been given keeping in mind the above said principle.

34.        Not only this, recently, it was also so said by the National Commission, in a case titled as Lt. Col. Anil Raj & anr. Vs. M/s. Unitech Limited, and another, Consumer Case No.346 of 2013, decided on 02.05.2016. Relevant portion of the said case, reads thus:-

“In so far as the question of a remedy under the Act being barred because of the existence of Arbitration Agreement between the parties, the issue is no longer res-integra.  In a catena of decisions of the Hon’ble Supreme Court, it has been held that even if there exists an arbitration clause in the agreement and a Complaint is filed by the consumer, in relation to certain deficiency of service, then the existence of an arbitration clause will not be a bar for the entertainment of the Complaint by a Consumer Fora, constituted under the Act, since the remedy provided under the Act is in addition to the provisions of any other law for the time being in force. The reasoning and ratio of these decisions, particularly in  Secretary, Thirumurugan Cooperative Agricultural Credit Society Vs. M. Lalitha  (Dead) Through LRs. & Others  - (2004) 1 SCC 305; still holds the field, notwithstanding the recent amendments in the Arbitration and Conciliation Act, 1986.  [Also see: Skypak Couriers Ltd. Vs. Tata Chemicals Ltd. - (2000) 5 SCC 294 and National Seeds Corporation Limited Vs. M. Madhusudhan Reddy & Anr. - (2012) 2 SCC 506.] It has thus, been authoritatively held that the protection provided to the Consumers under the Act is in addition to the remedies available under any other Statute, including the consentient arbitration under the Arbitration and Conciliation Act, 1986.”

35.     In  view of the above, the plea taken by the opposite party, that in the face of existence of arbitration clause in the Agreement, to settle disputes between the parties through Arbitration, in terms of provisions of Section 8 (amended) of 1996 Act, this Commission has no jurisdiction to entertain the consumer complaint, being devoid of merit, is rejected.”

            In view of the above, the objection raised by Counsel for the Opposite Parties, being devoid of merit, is rejected.

6.             The next question that falls for consideration, is, as to whether, this Commission has territorial jurisdiction to entertain and decide the complaint or not.

                According to Section 17 of the Act, a consumer complaint can be filed, by the complainant, before the State Consumer Disputes Redressal Commission, within the territorial Jurisdiction whereof, a part of cause of action arose to him. In the instant case, it is evident from the record, that Plot Buyer’s Agreement was executed between the initial allottee and the Opposite Parties, at Chandigarh, on 04.07.2007 (Annexure C-1). Not only this, No Objection Certificate (Annexure C-3), possession letter (Annexure C-6) and letter (Annexure C-7) were sent by the Opposite Parties from their Chandigarh Office, as the same bore the address of the Company as “SCO 120-122, First Floor, Sector 17-C, Chandigarh 160017”. Since, as per the documents, referred to above, a part of cause of action arose to the complainant, at Chandigarh, this Commission has got territorial Jurisdiction to entertain and decide the complaint.  The objection taken by the Opposite Parties, in their written version, in this regard, therefore, being devoid of merit, must fail, and the same stands rejected. 

7.             Another objection taken by the Opposite Parties, with regard to pecuniary jurisdiction, also deserves rejection.  As per admitted facts, the complainant has sought refund of amount paid i.e. Rs.66,95,197/- with penalty @18% from the respective dates of deposit; compensation to the tune of Rs.3 lacs on account of mental agony and physical harassment and cost of litigation to the tune of Rs.2 lacs. It is argued by Counsel for the Opposite Parties that if the entire claimed amount is added, alongwith interest claimed, it will cross Rs.1 crore and in that event, it will not be open to this Commission to entertain and adjudicate this complaint, for want of pecuniary jurisdiction. To say so, reliance has been placed upon ratio of judgment of a Larger Bench of the National Commission, in the case of Ambrish Kumar Shukla (supra). This issue, whether interest is to be counted when looking into pecuniary jurisdiction of this Commission, came up for consideration in the case of Surjit Singh Vs. M/s Emaar MGF Land Pvt. Ltd. and another, Consumer Case no. 484 of 2016 decided on 15.12.2016, wherein, after noting similar objections it was observed as under:-

“13.        Now we will deal with another contention of the opposite parties that for want of pecuniary jurisdiction, it is not open to this Commission to entertain and adjudicate this complaint.  As per admitted facts, the complainant has sought refund of amount paid i.e. Rs.48,95,264/- alongwith interest @12% p.a. from the respective date of deposits; compensation to the tune of Rs.5 lacs, for mental agony and physical harassment and cost of litigation to the tune of Rs.55,000/-. It is argued by Counsel for the opposite parties that if his entire claimed amount is added, alongwith interest claimed, it will cross Rs.1 crore and  in that event it will not be open to this Commission to entertain and adjudicate this complaint, for want of pecuniary jurisdiction. To say so, reliance has been placed upon ratio of judgment of a Larger Bench of the National Commission, in the case of Ambrish Kumar Shukla (supra). In the said case, it was specifically observed that when determining pecuniary jurisdiction of the Consumer Foras, it is the value of the goods and services, which has to be noted and not the value of deficiencies claimed. Further, that interest component also has to be taken into account, for the purpose of determining pecuniary jurisdiction.

14.        In the first blush, if we look into the ratio of the judgment, referred to above, it appears that this Commission will not have pecuniary jurisdiction to entertain this complaint.  However, on deep analysis, we are going to differ with the argument raised by Counsel for the opposite parties.  Judgment in the case of Ambrish Kumar Shukla (supra) was rendered by Three Judges Bench of the National Commission, without noting its earlier view of the subject. This issue, whether, when determining pecuniary jurisdiction of the State Commission/ Consumer Foras, interest is to be added with other relief claimed or not, came up for consideration, before the Three Judges Bench of the National Commission in Shahbad Cooperative Sugar Mills Ltd. Vs. National Insurance Co. Ltd. And Ors., II 2003 CPJ 81 (NC). In the said case, noting similar arguments, it was observed as under:-

“3. Complaint (at pp 17-36) was filed with the following prayer :

“It is, therefore, respectfully prayed that the complaint be allowed and the opposite parties be directed to pay the claim to the tune of Rs. 18,33,000/- plus interest @ 18% from the date of claim till its realization. Also the suitable damages caused to the complainant be ordered to be paid to the complainant.”

4. Bare reading of the prayer made would show that the interest claimed by appellant pertains to the period upto the date of filing complaint, pendente lite and future. Rate and the period for which interest has to be allowed, is within the discretion of State Commission and the stage for exercise of such a discretion would be the time when the complaint is finally disposed of. Thus, the State Commission had acted erroneously in adding to the amount of Rs. 18,33,000/- the interest at the rate of 18% per annum thereon till date of filing of complaint for the purpose of determination of pecuniary jurisdiction before reaching the said stage. Order under appeal, therefore, deserves to be set aside. However, in view of change in pecuniary jurisdiction w.e.f. 15.3.2003, the complaint is now to be dealt with by the District Forum instead of State Commission.”

15.       It was specifically stated that interest claimed by appellant/complainant pertained to the period upto the date of filing complaint, pendente lite and future, need not be added in the relief claimed, to determine pecuniary jurisdiction of the State Commission/Consumer Foras. It was rightly said that the rate and period for which the interest has to be allowed, is within the discretion of the particular Consumer Fora, and the stage for exercise of such discretion would be the time, when final order is passed. We are of the considered opinion that the view taken is perfectly justified. There may be cases, where the complainant may not be entitled to claim any interest upon the amount paid, like the one, where he is rescinding his contract and  further at what rate interest is to be granted will be determined by the competent Consumer Fora, by looking into the facts of each case. All cases cannot be put into a straitjacket formula, to add interest claimed, to determine pecuniary jurisdiction of the Consumer Foras. The interest, which is a discretionary relief, cannot be added to the value of the goods or services, as the case may be, for the purpose of determining the pecuniary jurisdiction of the Consumer Foras. As per provisions of the Consumer Protection Act, 1986 (Act) value of the goods purchased or services plus (+) compensation claimed needs to be added only, for determining pecuniary jurisdiction of the Consumer Foras.

                As per ratio of the judgment of the Supreme Court in the case of New India Assurance Co. Ltd. Vs. Hilli Multipurpose Cold Storage Pvt. Ltd., Civil Appeal No.10941-10942 of 2013, decided on 04.12.2015, we would like to follow the view expressed by Three Judges Bench (former Bench) of the National Commission in Shahbad Cooperative Sugar Mills Ltd. case (supra), in preference to the ratio of judgment passed by a Bench of co-equal strength (subsequent Bench) of the National Commission in the case of Ambrish Kumar Shukla case (supra).

                In New India Assurance Co. Ltd. case (supra), it was specifically observed by the Supreme Court that when a former Bench of co-equal strength has given a finding qua one legal issue, it is not open to the subsequent Bench of co-equal strength to opine qua that very legal issue and give a contrary finding. At the maximum, the subsequent Bench of co-equal strength can refer the matter to the President/Chief Justice of India to constitute a bigger Bench, to look into the matter and reconsider the legal proposition. It was further specifically held that, in case, there are two contrary views by the former and later co-equal strength Benches, the former will prevail. It was so said by looking into the ratio of judgment rendered by the Five Judges Bench of the Supreme Court of India, in Central Board of Dawoodi Bohra Community & Anr. Vs. State of Maharashtra & Anr. (2005) 2 SCC 673, wherein, when dealing with similar proposition,  it was observed as under:-

 “12. Having carefully considered the submissions made by the learned senior counsel for the parties and having examined the law laid down by the Constitution Benches in the abovesaid decisions, we would like to sum up the legal position in the following terms :-

 (1) The law laid down by this Court in a decision delivered by a Bench of larger strength is binding on any subsequent Bench of lesser or co-equal strength.

 (2) A Bench of lesser quorum cannot disagree or dissent from the view of the law taken by a Bench of larger quorum. In case of doubt all that the Bench of lesser quorum can do is to invite the attention of the Chief Justice and request for the matter being placed for hearing before a Bench of larger quorum than the Bench whose decision has come up for consideration. It will be open only for a Bench of coequal strength to express an opinion  doubting the correctness of the view taken by the earlier Bench of coequal strength, whereupon the matter may be placed for hearing before a Bench consisting of a quorum larger than the one which pronounced the decision laying down the law the correctness of which is doubted.

 (3) The above rules are subject to two exceptions : (i) The abovesaid rules do not bind the discretion of the Chief Justice in whom vests the power of framing the roster and who can direct any particular matter to be placed for hearing before any particular Bench of any strength; and

 (ii) In spite of the rules laid down hereinabove, if the matter has already come up for hearing before a Bench of larger quorum and that Bench itself feels that the view of the law taken by a Bench of lesser quorum, which view is in doubt, needs correction or reconsideration then by way of exception (and not as a rule) and for reasons given by it, it may proceed to hear the case and examine the correctness of the previous decision in question dispensing with the need of a specific reference or the order of Chief Justice constituting the Bench and such listing. Such was the situation in Raghubir Singh and Hansoli Devi.”

16.         In Ambrish Kumar Shukla case (supra), ratio of judgment-Shahbad Cooperative Sugar Mills Ltd. (supra) was not even discussed and considered. In view of above proposition of law laid down by the Five Judges Bench in Central Board of Dawoodi Bohra Community & Anr.`s and also Three Judges Bench of the Supreme Court, in New India Assurance Co. Ltd. Vs. Hilli Multipurpose Cold Storage Pvt. Ltd. case (supra), it is not open to the Bench of co-equal strength to give contrary findings, to the view already expressed by a Former Bench of same strength. In Shahbad Cooperative Sugar Mills Ltd. case (supra), decided on 02.04.2003, it was specifically observed by Three Judges Bench of the National Commission that when determining pecuniary jurisdiction of the Consumer Foras, interest component claimed by the complainant/party, is not to be added. We are of the considered view that in view of proposition of law, as explained above, the view taken in Shahbad Cooperative Sugar Mills Ltd. case (supra), to determine pecuniary jurisdiction without taking interest claimed, will prevail. As such, in the present case, we are not looking into the interest claimed by the complainant, when determining pecuniary jurisdiction of this Commission.  If the interest part is excluded, the amount claimed in the relief clause fell below Rs.1 crore and above Rs.20 lacs. Hence, this Commission has pecuniary jurisdiction to entertain and decide the present complaint. In view of above, the objection raised by the opposite parties, in this regard, being devoid of merit, must fail and the same stands rejected.”

            In view of above, this objection taken by the Opposite Parties that this Commission lacks pecuniary jurisdiction, being devoid of merit, fails and the same stands rejected.

8.             The objection taken by the Opposite Parties, to the effect that the plot was earlier allotted to Kanwar Pal Singh Kochhar and the complainant purchased the said plot from open market, as such, he is speculator and did not fall within the definition of “Consumer”, as defined by Section 2 (1) (d) (ii) of the Act, also deserves rejection. It may be stated here that there is nothing, on the record, that the complainant is the property dealer, and deals in the sale and purchase of property, on regular basis, and as such, the unit, in question, was purchased by him, by way of investment, with a view to resell the same, as and when, there was escalation in the prices thereof. Thus, in the absence of any cogent evidence, in support of the objection raised by the  Opposite Parties, mere bald assertion i.e. simply saying that the  complainant being speculator, did not fall within the definition of a consumer, cannot be taken into consideration. In a case titled as Kavita Ahuja Vs. Shipra Estate Ltd. and Jai Krishna Estate Developer Pvt. Ltd. 2016 (1) CPJ 31, by the National Consumer Disputes Redressal Commission, New Delhi, it was held that the buyer(s) of the residential unit(s), would be termed as consumer(s), unless it is proved that he or she had booked the same for commercial purpose. Similar view was reiterated by the National Commission, in DLF Universal Limited Vs Nirmala Devi Gupta,  2016 (2) CPJ 316. The principle of law, laid down, in the aforesaid cases, is fully applicable to the present case. The  complainant, thus, falls within the definition of a ‘consumer’, as defined under Section 2(1)(d) of the Act. Such an objection, taken by  the Opposite Parties, in their written reply, therefore, being devoid of merit, is rejected. 

9.           Another objection raised by the Opposite Parties that since it was mentioned in the Agreement that the Company shall endeavour to deliver possession of the plot/unit within maximum period of three years, as such, time was not the essence of contract, is also devoid of merit. It may be stated here that it was clearly mentioned in Clause 8 of the Agreement that possession of the unit will be delivered by the Opposite Parties, within a period of two years from the execution of the Agreement but not later than three years, subject to force majeure circumstances or reason beyond the control of the Opposite Parties. In the instant case, the Opposite Parties did not raise any force majeure circumstances, if any, encountered by them. In the absence of any force majeure circumstances having been faced by the Opposite Parties or any other valid and legal reason beyond their control, the stand taken by them, in this regard, for condonation of delay in delivery of possession of the unit, to the complainant, cannot be taken into consideration. Thus, under these circumstances, since as per Clause 8 of the Agreement, the Opposite Parties were bound to deliver possession of the unit, within a maximum period of three years from the date of execution of the Agreement i.e. latest by 03.07.2010 and not more than that and, as such, time was,  unequivocally made the essence of contract.

              Even otherwise, the Opposite Parties cannot evade their liability, merely by saying that since the word tentative/ proposed was mentioned in the Agreement, for delivery of possession of the unit and, as such, time is not to be considered as essence of the contract. Non-mentioning of exact date of delivery of possession of the unit(s) in the Buyer’s Agreement, is an unfair trade practice, on the part of the Builder. The builder is bound to mention the exact/specific date of delivery of possession of the unit(s) to the allottees/purchasers thereof.  It was so said by the Hon`ble National Commission, in Rajeev Nohwar & Anr. V/S Sahajanand Hi Tech Construction Pvt Ltd, 2016 (2) CPR 769. Relevant portion of the said case reads thus:-

“Merely making possession by a particular date will also not meet the requirement of law and the promotor is under a legal mandate to stipulate a specific date for delivery of possession of the flat in the agreement which he executes with the flat buyer”.

In view of above, the plea of the Opposite Parties in this regard also stands rejected.

10.         The next question, that falls for consideration, is, as to whether the Opposite Parties offered possession of the unit/plot, in question, to the complainant, complete in all respects or not. Initially, plot was booked by Kanwar Pal Singh Kochhar, therefore, plot bearing No.85 in Pinewood Greens, Sector 108 was allotted to him. Thereafter, the said plot was purchased by the complainant and endorsed in favour of the complainant vide endorsement dated 30.04.2008. Therefore, the complainant stepped into the shoes of the original allottee. As per Clause 8 of the Agreement, possession of the unit was to be delivered within a period of 2 years from the date of execution of the Agreement but not later than 3 years. So, the period of 3 years from the date of execution of the Agreement dated 04.07.2007 has expired on 03.07.2010. No doubt, a plea is taken by Counsel for the Opposite Parties that since the Opposite Parties have already obtained Partial Completion Certificate  in respect of the project, in question, as such, it could very well be said that the development at site was complete and that the Opposite Parties were in possession of all the necessary approvals/sanctions and were ready to offer/deliver possession of the unit to the complainant. It may be stated here that perusal of Partial Completion Certificate dated 16.10.2015   (Annexure R-4) clearly goes to show that the same was issued subject to certain conditions i.e. the Opposite Parties shall abide by all the necessary permissions/sanctions/approvals from the PSPCL, PPCB, etc.   It is the duty of the Opposite Parties to comply with all the conditions, mentioned in the Partial Completion Certificate, before seeking final completion certificate.  The plea of the Counsel for the Opposite Parties is that the Opposite Parties offered possession of the plot to the complainant on 29.11.2009 (Annexure C-6), after completion of the amenities. On the other hand, Counsel for the complainant denied regarding offer of possession, as alleged by the Opposite Parties, because firstly it was undated and stated that it was only an updation regarding status of the project. Counsel for the complainant further stated that after the receipt of the said possession letter, the complainant sent a number of emails to the Opposite Parties regarding possession of the unit, complete in all respects but they failed to do so. A bare perusal of the said possession letter (Annexure C-6) clearly reveals that the said letter, which was written by the Opposite Parties to the complainant was undated and the relevant portion of the said letter reads thus :-

“This has reference to the plot allotted to you in the Project. We take this opportunity to update you on the status of the development work of the Project and in particular about the Plot situated in Pinewood Greens Sector 108 of the Project.

X x x x xx

The development activities in all three sectors of Mohali Hills i.e. Sectors 105, 108 and 109 are in full swing and we are pleased to inform you that significant progress has been made with respect to development of basic infrastructure like water pipelines, sewer pipelines and development of roads, parks in these sectors. X x x x x.

In view of the above development and our constant endeavor to enhance our customer’s satisfaction, we are prepared to hand over possession of the Plot to you, subject to your making payments mentioned hereunder :

On the basis of ground demarcation, the area for your plot has increased/decreased and as a consequence the revised area is 457 sq. yards.

X x x x x x”

 In view of the afore-extracted letter, it is clearly revealed that the Opposite Parties only informed the complainant regarding updation of the status of the development work of the project. It is not a possession letter because the Opposite Parties clearly stated that they are prepared to hand over possession of the plot and not offered actual physical possession of the plot to the complainant, complete in all respects. Not only this, the complainant sent an email dated 26.06.2013 (Annexure C-8) after about four years of the said possession letter, wherein, he clarified the project completion time from the Opposite Parties. The Opposite Parties duly replied vide email dated 26.06.2013 to the complainant (Annexure C-8), which reads thus :-

“We would like to inform that work is being carried out for the completion of infrastructure amenities within the sectors and we expect to obtain the Completion Certificate by end of this year. Subsequently, we shall initiate the progress of registration and shall sent you a communication in this regard accordingly…..”

Even   the  Opposite  Parties sent    email dated 27.08.2013 (Annexure C-11) to the complainant, which reads thus :-

“As communicated earlier, we would like to reaffirm that we have initiated the process of installation of Sewage Treatment Plant (STP) in the sector. We have also laid the transformers and work is being expedited to energies the same at the earliest. Also necessary works on the water tanks and rain water harvesting system has already been completed. The Company is expediting the completion of overall development across all sectors to make the place habitable and we shall keep you updated on the status at regular intervals.

Further, please be informed that we expect to initiate the registration processes by the end of this year and an official communication will be sent to all the customers in this regard, accordingly……”

The Opposite Parties further sent an email dated 28.01.2014 (Annexure C-12) to the complainant, which reads thus :-

“We would like to inform that we shall be sending you the offer of possession alongwith the registration charges within 30 days time…..”

The complainant in his complaint has stated that when the Opposite Parties sent a letter dated 05.05.2013 (Annexure C-13) to him intimating about the settlement of final dues, he visited the site and noticed that there was hardly any development because there were no roads, parks, shopping complex, STP, club etc. From the afore-extracted emails, it is crystal clear that the Opposite Parties were unable to deliver possession in the year 2014, what to talk of possession letter sent by the Opposite Parties to the complainant in the year 2009. As per the Agreement, the possession was required to be delivered to the complainant by July, 2010 but till the year 2014, they failed to deliver possession of the plot to the complainant, complete in all respects. Even the Opposite Parties failed to place on record any document, which could prove that all the basic amenities were complete at the site or they sent any letter to the complainant after the aforesaid letter, that the unit is complete in all respects and they are ready for possession. Not only this, it is also relevant to note that a number of cases of Sector 108 of the Opposite Parties Company have already been decided by this Commission, in which, the basic amenities were not available at the site.

11.          It is pertinent to note that the Opposite Parties  (Emaar MGF) filed appeal in another case i.e. First Appeal bearing No. 709 of 2016 titled as ‘Emaar MGF Land Limited Vs. Mandeep Saini’ before the Hon'ble National Consumer Disputes Redressal Commission, New Delhi, against the order of this Commission and the Hon'ble National Consumer Disputes Redressal Commission, New Delhi passed the order dated 14.09.2016, which reads thus :-

“x x x x xx

It is vehemently argued by Mr.Aditya Narain, learned counsel appearing for the Appellant that since the delay in delivery of possession of the flats in Sectors 104, 106, 108 and 109 is directly attributed to the sealing of the main access road to these Sectors by the Forest Department, one of the factors which weighed with the State Commission, falls within the ambit of force majeure clause in the agreement, there is no deficiency in service on the part of the Appellant in its alleged failure to deliver the possession of the subject flats in question by the committed time.  He thus prays that ex parte ad interim stay may to be continued. 

Prima facie, we are not convinced with the submission.  Hence, without expressing final opinion on the issue but having regard to the fact that the sealing orders have not yet been revoked and the Appellant is still not in a position to deliver possession of the fully developed flats with proper access, to the Complainants, we direct that the Appellant shall deposit in this Commission the principal amount(s) deposited by the Complainants with them, within 6 weeks from today.  On deposit of the said amount(s), it will be open to the Complainants to withdraw the said amount, on filing affidavits, undertaking to this Commission that they will refund the amount(s) withdrawn, if so directed at the time of final disposal of the Appeals.  Subject to the said deposits, the operation of the remaining directions, regarding interest, compensation, etc., in the impugned order shall remain stayed.

X x x x x xx x”

From the afore-extracted order, it is clearly proved that Counsel for the Opposite Parties admitted before the Hon'ble National Consumer Disputes Redressal Commission, New Delhi that the delay in delivery of possession to these Sectors i.e. Sectors 104, 106, 108 & 109 was due to the sealing of main access road by the Forest Department. It is clearly proved that the Hon'ble National Consumer Disputes Redressal Commission, New Delhi without expressing final opinion on the issue but having regard to the fact that the sealing orders have not yet been revoked and the Appellant i.e. Emaar MGF Land Limited is still not in a position to deliver possession of the fully developed units with proper access, to the complainant i.e. till the passing of the afore-extracted order dated 14.09.2016. So, we are of the view that in the present case, the possession offered by the Opposite Parties is only a paper possession and not more than that.

12.         The next question, that falls for consideration, is, as to whether, the complainant is entitled to refund of the deposited amount. The complainant, in the prayer clause of the complaint, sought refund of the amount of Rs.66,95,197/-, whereas, the Opposite Parties stated in their written statement that the complainant deposited the total amount of Rs.67,14,206/-, as is evident from the statement of account  (Annexure R-1) in respect of the unit, in question. As per Clause 8 of the Agreement, possession of the unit was to be delivered by the Opposite Parties within a maximum period of three years from the date of execution of the Agreement, which expired on 03.07.2010 but the Opposite Parties offered possession of the unit to the complainant in the year 2009, which was only a paper possession and not more than that. So, the complainant is thus, entitled to get refund of amount, as prayed by him, in the prayer clause of the complaint i.e. Rs.66,95,197/-. In view of above facts of the case, the Opposite Parties are also under an obligation to compensate the complainant, for inflicting mental agony and causing physical harassment to him.

13.         It is to be further seen, as to whether, interest, on the amount refunded, can be granted, in favour of the  complainant. In the prayer clause of the complaint, the complainant sought refund of the amount of Rs.66,95,197/-, which was paid by him in respect of the unit, in question, without getting anything, in lieu thereof. The said amount has been used by the Opposite Parties, for their own benefit. The  Opposite Parties were charging interest @15% p.a. compounded, as per Clause 3 of the Agreement, for the period of delay in making payment of installments.  It is well settled law that whenever money has been received by a party and when its refund is ordered, the right to get interest follows, as a matter of course. The obligation to refund money received and retained without right implies and carries with it, the said right. In the facts and circumstances of the case, the complainant is held entitled to get refund of the amount deposited by him, to the tune of Rs.66,95,197/- alongwith interest @15% p.a. compounded, from the date of endorsement of the unit in favour of the complainant i.e. 30.04.2008 till realization. 

14.         As far as the plea taken by the Counsel for the Opposite Parties, regarding forfeiture clause is concerned, it may be stated here that the same stands rejected, because it is not their (Opposite Parties) case, that they were ready with possession of the unit, to be delivered to the complainant, complete in all respects, as per terms and conditions contained in the Agreement, by the stipulated date but it was he (complainant) who wanted to rescind the contract, on account of some unavoidable circumstances/ financial constraints or on account of deficiency on the part of the Opposite Parties by not handing over the possession complete in all respects to the complainant within the stipulated time period or for any personal reason, and are seeking refund of the amount deposited. Had this been the case of the Opposite Parties, only in those circumstances, it would have been held that since the complainant himself is rescinding the contract, as such, he is entitled to the amount deposited, after deduction of some amount, as per the terms and conditions of the Agreement. In this view of the matter, the plea taken by the Opposite Parties, in this regard, has no legs to stand and is accordingly rejected.

15.         No other point, was urged, by the Counsel for the parties.

16.         For the reasons recorded above, the complaint is partly accepted, with costs. The Opposite Party is directed, as under:-

  1. To  refund   the  amount of Rs.66,95,197/-, to  the complainant, alongwith interest @ 15% p.a. compounded, from the date of endorsement of the unit in favour of the complainant i.e. from 30.04.2008 onwards, within 45 days, from   the  date of receipt of a certified copy of  this   order.
  2. To pay compensation, in the sum of Rs.2,00,000/- for causing mental agony and harassment, to the complainant, within 45 days, from the date of receipt of a certified copy of this order.
  3. To pay cost of litigation, to the tune of Rs.50,000/- to the complainant.
  4. In case, the payment of amounts, mentioned in Clauses (i) and (ii), is not made, within the stipulated period, then the Opposite Parties shall be liable to pay the amount mentioned in Clause (i) with interest @18% p.a. compounded, instead of interest @ 15% p.a. compounded, from the date of endorsement of the unit in favour of the complainant, mentioned above, till realization, and interest @15% p.a. compounded, on the  amount of compensation, mentioned in Clause (ii), from the date of filing the complaint, till realization, besides payment of litigation costs.

17.          However, it is made clear that, if the  complainant has availed loan facility from any banking or financial institution, for making payment of installments towards the said unit, it will have the first charge of the amount payable, to the extent, the same is due to be paid by the complainant.

18.         Certified Copies of this order be sent to the parties, free of charge.

19.         The file be consigned to Record Room, after completion.

Pronounced.

March 28, 2017.                                     Sd/-

[JUSTICE JASBIR SINGH (RETD.)]

[PRESIDENT]

 

Sd/-

 [DEV RAJ]

MEMBER

 

Sd/-

 (PADMA PANDEY)

        MEMBER

rb

 

         

 

 

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.