Chandigarh

StateCommission

CC/691/2016

Veena Mujral - Complainant(s)

Versus

Emaar MGF Land Ltd. - Opp.Party(s)

Sandeep Bhardwaj, Adv.

08 Mar 2017

ORDER

STATE CONSUMER DISPUTES REDRESSAL COMMISSION,

U.T., CHANDIGARH

 

Complaint case No.

:

691 of 2016

Date of Institution

:

14.10.2016

Date of Decision

:

08.03.2017

 

  1. Veena Mujral wife of Sh. K.K.Mujral.
  2. Ankur Mujral son of Sh. K.K.Mujral.
  3. Gunjot wife of Ankur Mujral.

All family members resident of House No.114, 1st floor, Phase 1, Mohali.

……Complainants

V e r s u s

  1. M/s Emaar MGF Land Private Limited (Mohali Hills), 1st Floor, Sector 17-C, SCO No. 120-122, Chandigarh – 160017, through its Managing Director/Director/ Authorized Representative.  
  2. M/s Emaar MGF Land Private Limited, ECE House, 28, Kasturba Gandhi Marg, New Delhi – 110001, through its Managing Director/Director/ Authorized Representative.

                                                    .... Opposite Parties

BEFORE:         JUSTICE JASBIR SINGH (RETD.), PRESIDENT

                        MR. DEV RAJ, MEMBER.

                        MRS. PADMA PANDEY, MEMBER

 

Argued by:      

 

Sh.  Sandeep Bhardwaj, Advocate for the complainants.

Sh.  Sanjeev Sharma, Advocate for the Opposite Parties.

 

PER PADMA PANDEY, MEMBER

 

               The facts, in brief, are that the complainants had a dream to have a residential house for their own use and for the use of their family members and, as such, they decided to purchase residential plot. The representative of the Opposite Parties allured the complainants about the salient features of their project namely Mohali Hills, Sector 109, Mohali, Punjab and alleged to be in possession of all necessary approvals/sanctions, and that possession of the same would be delivered within two years from the date of booking. On believing the assurances made by the Opposite Parties, the complainants moved an application for allotment of a plot measuring 300 sq. yards, Sector 109, Mohali Hills, Mohali, Punjab and paid the amount of Rs.10,35,000/- vide receipt (Annexure C-2). Thereafter, the Opposite Parties issued a provisional allotment letter dated 08.05.2007 (Annexure C-3), wherein, plot No.512 in Augusta Park, Sector 109 was allotted. The total sale consideration of the unit, in question, was Rs.36,19,104/- including EDC. It was further stated that the Agreement was executed between the parties on 21.09.2007 (Annexure C-4) and as per Clause 8 of the Agreement, possession was to be delivered within a period of 2 years but not later than three years i.e. by 20.09.2010. The complainants made the payment of installments, as per the demand of the Opposite Parties but inspite of receipt of the entire consideration, the Opposite Parties did not offer the possession of the plot, in time, as such, complainant No.1 issued a letter dated 03.01.2013 to the Opposite Parties to pay penalty in accordance with the terms and conditions of the Agreement (Annexure C-12). It was further stated that since the Opposite Parties failed to hand over possession of the plot in time, as such, they persuaded them to relocate the plot and an Amended Agreement was executed between the parties on 15.04.2014 (Annexure C-13), wherein, plot No.512 was got changed to plot No.116 but possession of the relocated plot was not handed over to them. Finally, the Opposite Parties issued an intimation of possession dated 09.10.2014 (Annexure C-14) , wherein, the complainants were told to pay an amount of Rs.11,70,244/- under different heads but the same was given without obtaining the necessary permission and approvals and without obtaining the completion certificate. It was further stated that as per account statement issued by the Opposite Parties, the complainants paid the total amount of Rs.34,46,604/- (Annexure C-15) in respect of the plot, in question.  It was further stated that the complainants came to know from the similar located allottees that the entry points of the said Sector 109, in which, the plot is located, were sealed/fenced by the Government of Punjab, Forest Department, which fact was never disclosed by the Opposite Parties. This fact is further fortified from the intimation obtained by similar located allottees under RTI from the Government of Punjab, Forest Department (Annexure C-16). The complainants have also placed on record RTI Informations and letters to prove the fact regarding lack of approvals, basic amenities and sealing of the project. It was further stated that the aforesaid acts, on the part of the Opposite Parties, amounted to deficiency, in rendering service, and indulgence into unfair trade practice. When the grievance of the complainants, was not redressed, left with no alternative, a complaint under Section 17 of the Consumer Protection Act, 1986 (in short the ‘Act’ only), was filed.

2.           The Opposite Parties, in their written version, have taken objection regarding arbitration clause in the Agreement, and also they separately moved an application u/s 8 of Arbitration and Conciliation Act, 1996 taking a specific objection in this regard for referring the matter to the Arbitrator in terms of the agreed terms and conditions of the Agreement. It was stated that this Commission has no pecuniary jurisdiction as well as territorial jurisdiction to try and entertain the complaint. It was further stated that the parties are bound by the terms and conditions of the Agreement and it is clearly stipulated in the Agreement that in case of failure of the allottee to perform all obligations as set out in the Agreement, the allottee has authorized the company to forfeit the earnest money as stipulated in Clause 2(f) of the Agreement alongwith any interest paid, due or payable, any amount of non refundable nature. It was further stated that the complainants did not fall within the definition of “Consumer” as prescribed under Section 2(d) of the Consumer Protection Act as the complainants purchased the plot, in question, for commercial purposes/speculation. It was further stated that possession of the unit was offered to the complainants after completion of the amenities, as per the terms and conditions of the Agreement. It was further stated that the complainants are also liable to pay holding charges, as per the Agreement, for not taking over possession. It was admitted regarding booking of the unit; relocation of the unit and execution of the Agreement and Amended Agreement. It was further stated that as per Clause 8 of the Agreement, the Company shall try and endeavor to hand over possession of the unit within 3 years from the date of execution of the Agreement and in case of delay, the Company was liable to pay compensation. It was further stated that the intimation of possession was sent to the complainants on 09.10.2014 and delayed compensation of Rs.7,12,062/- has already credited in the customer’s account, as is evident from statement of account (Annexure R-2).  It was further stated that all the necessary approvals were obtained by the Company when the unit was allotted to the complainants. It was further stated that Partial Completion Certificate has already obtained by the Opposite Parties (Annexure R-4). It was further stated that vide letter dated 11.02.2010, GMADA granted permission to the Opposite Parties for six approaches from Kharar-Banur-Tepla road in Village Raipur kalan to the project of the Opposite Parties and relevant fee was deposited by them (Annexure R-5). It was further stated that the responsibility of obtaining all statutory permissions for development of the Kharar-Banur-Tepla road is of the state authorities. It was further stated that vide letter dated 15.04.2015 the Chief Administrator, GMADA was requested by the Opposite Parties to take up issue with Forest Department to provide connectivity vide letter (Annexure R-5). It was further stated that the Forest Department has sealed certain entry points but there is still adequate access to the unit of the complainants i.e. through a motorable road and stand of the complainants that all entry points are sealed is malafide and without any basis. It was further stated that even the court case is over now and as compounded fee has been paid and the case has been withdrawn for Sector 109. It was further stated that the Opposite Parties asked the Forest Department to remove the sealing/fencing and now there is no legal impediment in removal of fencing/sealing in Sector 109. It was further stated that if the complainants seek refund after offer of possession then forfeiture clause would be applicable. It was further stated that neither there was any deficiency, in rendering service, on the part of the Opposite Parties, nor they indulged into unfair trade practice.

3.           The complainants, filed rejoinder to the written statement of the Opposite Parties, wherein they reiterated all the averments, contained in the complaint, and refuted those, contained in the written version of the Opposite Parties. 

4.           The Parties led evidence, in support of their case.

5.           We have heard the Counsel for the parties, and have gone through the evidence and record of the case, carefully. 

6.           The first question that falls for consideration is, as to whether, in the face of existence of arbitration clause in the Agreement, to settle disputes between the parties through Arbitration, in terms of provisions of Section 8 (amended) of Arbitration Act 1996, this Commission has no jurisdiction to entertain the present complaint. It may be stated here that the objection raised by the Opposite Parties, in this regard, deserves rejection, in view of the judgment passed by this Commission in Abha Arora Vs. Puma Realtors Pvt. Ltd. and another, consumer complaint No.170 of 2015, decided on 01.04.2016, wherein this issue was dealt, in detail, while referring various judgments of the Hon'ble Supreme Court of India; the National Commission, New Delhi, and also Section 3 of the Consumer Protection Act, 1986. Ultimately it was held by this Commission that even in the face of existence of arbitration clause in the Agreement, to settle disputes between the parties through Arbitration, in terms of provisions of Section 8 (amended) of 1996 Act, this Commission has jurisdiction to entertain the consumer complaint. It was also so said by the National Commission, recently, in a case titled as Lt. Col. Anil Raj & anr. Vs. M/s. Unitech Limited, and another, Consumer Case No. 346 of 2013, decided on 02.05.2016. Relevant portion of the said case, reads thus:-

“In so far as the question of a remedy under the Act being barred because of the existence of Arbitration Agreement between the parties, the issue is no longer res-integra.  In a catena of decisions of the Hon’ble Supreme Court, it has been held that even if there exists an arbitration clause in the agreement and a Complaint is filed by the consumer, in relation to certain deficiency of service, then the existence of an arbitration clause will not be a bar for the entertainment of the Complaint by a Consumer Fora, constituted under the Act, since the remedy provided under the Act is in addition to the provisions of any other law for the time being in force. The reasoning and ratio of these decisions, particularly in Secretary, Thirumurugan Cooperative Agricultural Credit Society Vs. M. Lalitha (Dead) Through LRs. & Others  - (2004) 1 SCC 305; still holds the field, notwithstanding the recent amendments in the Arbitration and Conciliation Act, 1986.  [Also see: Skypak Couriers Ltd. Vs. Tata Chemicals Ltd. - (2000) 5 SCC 294 and National Seeds Corporation Limited Vs. M. Madhusudhan Reddy & Anr. - (2012) 2 SCC 506.] It has thus, been authoritatively held that the protection provided to the Consumers under the Act is in addition to the remedies available under any other Statute, including the consentient arbitration under the Arbitration and Conciliation Act, 1986.” 

            In view of the above, and also in the face of ratio of judgments, referred to above, passed by the National Commission and this Commission, the arguments raised by Counsel for the Opposite Parties, stands rejected.

7.           The next question that falls for consideration, is, as to whether, this Commission has territorial jurisdiction to entertain and decide the complaint or not.

                According to Section 17 of the Act, a consumer complaint can be filed, by the complainants, before the State Consumer Disputes Redressal Commission, within the territorial Jurisdiction whereof, a part of cause of action arose to them. In the instant case, it is evident from the record, that Plot Buyer’s Agreement (Annexure C-4) was executed between the parties, at Chandigarh. Not only this, receipts, letters, provisional allotment letter (Annexures C-2, C-3, C-5 to C-11), intimation of possession letter dated 09.10.2014 (Annexure C-14) was sent by the Opposite Parties from their Chandigarh Office, as the same bore the address of the Company as “SCO 120-122, First Floor, Sector 17-C, Chandigarh 160017”. Since, as per the documents, referred to above, a part of cause of action arose to the complainants, at Chandigarh, this Commission has got territorial Jurisdiction to entertain and decide the complaint.  The objection taken by the Opposite Parties, in their written version, in this regard, therefore, being devoid of merit, must fail, and the same stands rejected. 

8.           Another objection taken by the Opposite Parties, with regard to pecuniary jurisdiction, also deserves rejection. It may be stated here, that the complainants sought refund of an amount of Rs.34,46,604/- deposited by them, alongwith suitable interest from the respective dates of deposits till realization ;  compensation to the tune of Rs.5 lacs, for mental agony & physical harassment and cost of litigation, to the tune of Rs.1,00,000/-, aggregate value whereof [excluding the interest claimed] fell above Rs.20 lacs and below Rs.1 crore. Thus, this Commission has got pecuniary Jurisdiction, to entertain and decide the complaint.

                As far as the interest claimed by the complainants, on the deposited amount is concerned, it is not required to be added, at this stage, to the value of the reliefs claimed, for determining the pecuniary Jurisdiction of this Commission, in view of law laid down by three Member Bench of the National Commission, in a case titled as Shahbad Cooperative Sugar Mills Ltd. Vs. National Insurance Co. Ltd. & Ors. II (2003) CPJ 81 (NC), wherein it was clearly held that since rate and the period for which interest has to be allowed, is within the discretion of Consumer Foras, and that too at the stage, when the complaint is finally disposed of, as such, the same being imaginary would not be taken into consideration, at the time of filing of the same (complaint), for the purpose of determination of pecuniary jurisdiction. Not only as above, in the case of Denis Exports Pvt. Ltd Vs. United India Insurance Co. Ltd, Consumer Case No. 196 of 2016, decided on 08 March 2016, it was clearly held by the National Commission that interest component being imaginary, will not be added in the reliefs sought by the consumers, for determining pecuniary jurisdiction of the Consumer Foras. This issue has already been elaborately dealt with by this Commission in Surjit Singh Thadwal Vs. M/s Emaar MGF Land Pvt. Ltd. & Anr., Consumer Complaint No.484 of 2016, decided on 15.12.2016. Relevant portion of the aforesaid judgment reads thus :-

“13.  Now we will deal with another contention of the opposite parties that for want of pecuniary jurisdiction, it is not open to this Commission to entertain and adjudicate this complaint.  As per admitted facts, the complainant has sought refund of amount paid i.e. Rs.48,95,264/- alongwith interest @12% p.a. from the respective date of deposits; compensation to the tune of Rs.5 lacs, for mental agony and physical harassment and cost of litigation to the tune of Rs.55,000/-. It is argued by Counsel for the opposite parties that if his entire claimed amount is added, alongwith interest claimed, it will cross Rs.1 crore and  in that event it will not be open to this Commission to entertain and adjudicate this complaint, for want of pecuniary jurisdiction. To say so, reliance has been placed upon ratio of judgment of a Larger Bench of the National Commission, in the case of Ambrish Kumar Shukla (supra). In the said case, it was specifically observed that when determining pecuniary jurisdiction of the Consumer Foras, it is the value of the goods and services, which has to be noted and not the value of deficiencies claimed. Further, that interest component also has to be taken into account, for the purpose of determining pecuniary jurisdiction.

  1.         In the first blush, if we look into the ratio of the judgment, referred to above, it appears that this Commission will not have pecuniary jurisdiction to entertain this complaint.  However, on deep analysis, we are going to differ with the argument raised by Counsel for the opposite parties.  Judgment in the case of Ambrish Kumar Shukla (supra) was rendered by Three Judges Bench of the National Commission, without noting its earlier view of the subject. This issue, whether, when determining pecuniary jurisdiction of the State Commission/ Consumer Foras, interest is to be added with other relief claimed or not, came up for consideration, before the Three Judges Bench of the National Commission in Shahbad Cooperative Sugar Mills Ltd. Vs. National Insurance Co. Ltd. And Ors., II 2003 CPJ 81 (NC). In the said case, noting similar arguments, it was observed as under:-

“3. Complaint (at pp 17-36) was filed with the following prayer :

“It is, therefore, respectfully prayed that the complaint be allowed and the opposite parties be directed to pay the claim to the tune of Rs. 18,33,000/- plus interest @ 18% from the date of claim till its realization. Also the suitable damages caused to the complainant be ordered to be paid to the complainant.”

4. Bare reading of the prayer made would show that the interest claimed by appellant pertains to the period upto the date of filing complaint, pendente lite and future. Rate and the period for which interest has to be allowed, is within the discretion of State Commission and the stage for exercise of such a discretion would be the time when the complaint is finally disposed of. Thus, the State Commission had acted erroneously in adding to the amount of Rs. 18,33,000/- the interest at the rate of 18% per annum thereon till date of filing of complaint for the purpose of determination of pecuniary jurisdiction before reaching the said stage. Order under appeal, therefore, deserves to be set aside. However, in view of change in pecuniary jurisdiction w.e.f. 15.3.2003, the complaint is now to be dealt with by the District Forum instead of State Commission.”

 

  1.         It was specifically stated that interest claimed by appellant/complainant pertained to the period upto the date of filing complaint, pendente lite and future, need not be added in the relief claimed, to determine pecuniary jurisdiction of the State Commission/Consumer Foras. It was rightly said that the rate and period for which the interest has to be allowed, is within the discretion of the particular Consumer Fora, and the stage for exercise of such discretion would be the time, when final order is passed. We are of the considered opinion that the view taken is perfectly justified. There may be cases, where the complainant may not be entitled to claim any interest upon the amount paid, like the one, where he is rescinding his contract and  further at what rate interest is to be granted will be determined by the competent Consumer Fora, by looking into the facts of each case. All cases cannot be put into a straitjacket formula, to add interest claimed, to determine pecuniary jurisdiction of the Consumer Foras. The interest, which is a discretionary relief, cannot be added to the value of the goods or services, as the case may be, for the purpose of determining the pecuniary jurisdiction of the Consumer Foras. As per provisions of the Consumer Protection Act, 1986 (Act) value of the goods purchased or services plus (+) compensation claimed needs to be added only, for determining pecuniary jurisdiction of the Consumer Foras.

                As per ratio of the judgment of the Supreme Court in the case of New India Assurance Co. Ltd. Vs. Hilli Multipurpose Cold Storage Pvt. Ltd., Civil Appeal No.10941-10942 of 2013, decided on 04.12.2015, we would like to follow the view expressed by Three Judges Bench (former Bench) of the National Commission in Shahbad Cooperative Sugar Mills Ltd. case (supra), in preference to the ratio of judgment passed by a Bench of co-equal strength (subsequent Bench) of the National Commission in the case of Ambrish Kumar Shukla case (supra).

                In New India Assurance Co. Ltd. case (supra), it was specifically observed by the Supreme Court that when a former Bench of co-equal strength has given a finding qua one legal issue, it is not open to the subsequent Bench of co-equal strength to opine qua that very legal issue and give a contrary finding. At the maximum, the subsequent Bench of co-equal strength can refer the matter to the President/Chief Justice of India to constitute a bigger Bench, to look into the matter and reconsider the legal proposition. It was further specifically held that, in case, there are two contrary views by the former and later co-equal strength Benches, the former will prevail. It was so said by looking into the ratio of judgment rendered by the Five Judges Bench of the Supreme Court of India, in Central Board of Dawoodi Bohra Community & Anr. Vs. State of Maharashtra & Anr. (2005) 2 SCC 673, wherein, when dealing with similar proposition,  it was observed as under:-

 

“12. Having carefully considered the submissions made by the learned senior counsel for the parties and having examined the law laid down by the Constitution Benches in the abovesaid decisions, we would like to sum up the legal position in the following terms :-

(1) The law laid down by this Court in a decision delivered by a Bench of larger strength is binding on any subsequent Bench of lesser or co-equal strength.

(2) A Bench of lesser quorum cannot disagree or dissent from the view of the law taken by a Bench of larger quorum. In case of doubt all that the Bench of lesser quorum can do is to invite the attention of the Chief Justice and request for the matter being placed for hearing before a Bench of larger quorum than the Bench whose decision has come up for consideration. It will be open only for a Bench of coequal strength to express an opinion  doubting the correctness of the view taken by the earlier Bench of coequal strength, whereupon the matter may be placed for hearing before a Bench consisting of a quorum larger than the one which pronounced the decision laying down the law the correctness of which is doubted.

(3) The above rules are subject to two exceptions : (i) The abovesaid rules do not bind the discretion of the Chief Justice in whom vests the power of framing the roster and who can direct any particular matter to be placed for hearing before any particular Bench of any strength; and

(ii) In spite of the rules laid down hereinabove, if the matter has already come up for hearing before a Bench of larger quorum and that Bench itself feels that the view of the law taken by a Bench of lesser quorum, which view is in doubt, needs correction or reconsideration then by way of exception (and not as a rule) and for reasons given by it, it may proceed to hear the case and examine the correctness of the previous decision in question dispensing with the need of a specific reference or the order of Chief Justice constituting the Bench and such listing. Such was the situation in Raghubir Singh and Hansoli Devi.”

  1.         In Ambrish Kumar Shukla case (supra), ratio of judgment-Shahbad Cooperative Sugar Mills Ltd. (supra) was not even discussed and considered. In view of above proposition of law laid down by the Five Judges Bench in Central Board of Dawoodi Bohra Community & Anr.`s and also Three Judges Bench of the Supreme Court, in New India Assurance Co. Ltd. Vs. Hilli Multipurpose Cold Storage Pvt. Ltd. case (supra), it is not open to the Bench of co-equal strength to give contrary findings, to the view already expressed by a Former Bench of same strength. In Shahbad Cooperative Sugar Mills Ltd. case (supra), decided on 02.04.2003, it was specifically observed by Three Judges Bench of the National Commission that when determining pecuniary jurisdiction of the Consumer Foras, interest component claimed by the complainant/party, is not to be added. We are of the considered view that in view of proposition of law, as explained above, the view taken in Shahbad Cooperative Sugar Mills Ltd. case (supra), to determine pecuniary jurisdiction without taking interest claimed, will prevail. As such, in the present case, we are not looking into the interest claimed by the complainant, when determining pecuniary jurisdiction of this Commission.  If the interest part is excluded, the amount claimed in the relief clause fell below Rs.1 crore and above Rs.20 lacs. Hence, this Commission has pecuniary jurisdiction to entertain and decide the present complaint. In view of above, the objection raised by the opposite parties, in this regard, being devoid of merit, must fail and the same stands rejected.”

The principles of law, laid down, in the cases referred to above, are fully applicable, to the facts of the instant case. In view of the above, the objection taken by the Opposite Parties, that this Commission lacks pecuniary Jurisdiction, being devoid of merit, must fail and the same stands rejected.

9.           The objection taken by the Opposite Parties, to the effect that the complainants being investors and therefore do not      fall within the definition of a consumer, as defined by Section 2 (1) (d) (ii) of the Act, also deserves rejection. It is pertinent to note that the complainants in para No.9 of their rejoinder clearly stated that the complainants are living in a joint family and the house has been purchased for the self-use and for the use of family members. It may be stated here that there is nothing, on the record, that the complainants are the property dealers, and deal in the sale and purchase of property, on regular basis, and as such, the unit, in question, was purchased by them, by way of investment, with a view to resell the same, as and when, there was escalation in the prices thereof. Thus, in the absence of any cogent evidence, in support of the objection raised by  the  Opposite Parties, mere bald assertion i.e. simply saying that the  complainants being investors, did not fall within the definition of a consumer, cannot be taken into consideration. In a case titled as Kavita Ahuja Vs. Shipra Estate Ltd. and Jai Krishna Estate Developer Pvt. Ltd. 2016 (1) CPJ 31, by the National Consumer Disputes Redressal Commission, New Delhi, it was held that the buyer(s) of the residential unit(s), would be termed as consumer(s), unless it is proved that he or she had booked the same for commercial purpose. Similar view was reiterated by the National Commission, in DLF Universal Limited Vs Nirmala Devi Gupta,  2016 (2) CPJ 316. The principle of law, laid down, in the aforesaid cases, is fully applicable to the present case. The  complainants, thus, fall within the definition of a ‘consumer’, as defined under Section 2(1)(d) of the Act. Such an objection, taken by  the Opposite Parties, in their written reply, therefore, being devoid of merit, is rejected.  

10.          Another objection raised by Counsel for the Opposite Parties that since it was mentioned in the Agreement that the Company shall try and endeavour to deliver possession of the unit within maximum period of 3 years, as such, time was not the essence of contract, is also devoid of merit. It may be stated here that it was clearly mentioned in Clause 8 of the Agreement that possession of the unit will be delivered by the Opposite Parties, within a period of two years from the date of execution of the Agreement but not later than 3 years, subject to force majeure circumstances or reason beyond the control of the Opposite Parties. In the instant case, the Opposite Parties did not raise any force majeure circumstances, if any, encountered by them. In the absence of any force majeure circumstances having been faced by the Opposite Parties or any other valid and legal reason beyond their control, the stand taken by them, in this regard, for condonation of delay in delivery of possession of the unit, to the complainants, cannot be taken into consideration. Thus, under these circumstances, since as per Clause 8 of the Agreement, the Opposite Parties were bound to deliver possession of the unit, within a maximum period of 3 years from the date of execution of the Agreement, as such, time was,  unequivocally made the essence of contract.

              Even otherwise, the Opposite Parties cannot evade their liability, merely by saying that since the word tentative/proposed was mentioned in the Agreement, for delivery of possession of the unit, as such, time is not to be considered as essence of the contract. Non-mentioning of exact date of delivery of possession of the unit(s) in the Buyer’s Agreement, is an unfair trade practice, on the part of the Builder. The builder is bound to mention the exact/specific date of delivery of possession of the unit(s) to the allottees/purchasers thereof.  It was so said by the Hon`ble National Commission, in Rajeev Nohwar & Anr. V/S Sahajanand Hi Tech Construction Pvt Ltd, 2016 (2) CPR 769. Relevant portion of the said case reads thus:-

“Merely making possession by a particular date will also not meet the requirement of law and the promotor is under a legal mandate to stipulate a specific date for delivery of possession of the flat in the agreement which he executes with the flat buyer”.

In view of above, the plea of the Opposite Parties in this regard also stands rejected.

11.         The next question, that falls for consideration, is, as to within which period, the delivery of the unit, was to be given to the complainants. It is clearly proved from Clause 8 of the Agreement that possession of the unit was to be delivered to the complainants within a maximum period of three years from the date of execution of the Agreement i.e. latest by 20.09.2010. However, the Opposite Parties issued an intimation of possession dated 09.10.2014 (Annexure C-14) i.e. after a delay of more than four years.

12.          The next question, that falls for consideration, is, as to whether,  offer of possession made by the Opposite Parties, to the complainants, vide letter dated 09.10.2014 (Annexure C-14), in respect of plot bearing No.109-MLU-116-300 in Block MLU situated at Sector 109,  Mohali Hills (Project), could be said to be genuine offer or not. It is well settled law that the onus to prove that the project had been completed and the area/site, in question, is fully developed is on the builder. It was so said by the National Commission, in Emaar MGF Land Limited and another Vs. Krishan Chander Chandna, First Appeal No.873 of 2013 decided on 29.09.2014. It is very strange that not even an iota of evidence has been placed, on record, by the Opposite Parties, to prove that development work was complete and that all the basic amenities were in existence. On the other hand, in case, all the development activities, had been undertaken, and completed at the site, by the said dates, then it was for Opposite Parties, which could be said to be in possession of the best evidence, to produce cogent and convincing documentary evidence, in the shape of the reports and affidavits of the Engineers/Architects, as they could be said to be the best persons, to testify, as to whether, all these development activities, had been undertaken and completed at the site or not, but they failed to do so.

              However, the main grouse of the complainants is that, despite receipt of the huge amount from them, actual physical possession thereof, was not offered to them, whereas, on the other hand, paper offer was made to them, vide letter of intimation of possession dated 09.10.2014 (Annexure C-14). According to the complainants, vide the aforesaid letter, the Opposite Parties illegally demanded an amount of Rs.11,70,244/- under various heads. After receipt of the aforesaid letter of intimation of possession, the complainants visited the site and found no development was there at the site at the time of intimation of possession. The Opposite Parties in their intimation of possession letter dated 09.10.2014 (Annexure C-14) informed the complainants that “process of handing over of the plots in Sector 109, Mohali Hills shall commence within 60 days of this letter, as your plot is ready to be handed over for possession.” A bare perusal of the aforesaid letter clearly reveals that the Opposite Parties only intimated the complainants regarding process of handing over of possession shall start within 60 days of this letter. The Opposite Parties have also placed on record  Partial Completion Certificate dated 16.10.2015 (Annexure R-4) to prove regarding the completion of the amenities at the site. It may be stated here that perusal of Partial Completion Certificate dated 16.10.2015 (Annexure R-4)  clearly goes to show that the same was issued subject to certain conditions i.e. the Opposite Parties shall abide by all the necessary permissions/sanctions/approvals from the PSPCL, PPCB, etc.   It is the duty of the Opposite Parties to comply with all the conditions, mentioned in the Partial Completion Certificate, before seeking final completion certificate. It is pertinent to note that a bare perusal of Partial Completion Certificate shows that the Opposite Party had applied for Partial Completion Certificate with the competent authority on 03.09.2015 and the said Partial Completion Certificate was issued by Greater Mohali Area Development Authority vide memo dated 16.10.2015. In the present case, according to the Agreement, the possession was to be delivered to the complainants within a maximum period of three years from the date of execution of the Agreement i.e. latest by 20.09.2010 but the Opposite Parties applied for Partial Completion Certificate on 03.09.2015 i.e. after the period of about five years stipulated. Even the complainants have drawn our attention to this Commission that the entry points of the said Sector i.e. Sector 109, in which, the plot is located, were sealed/fenced by the Govt. of Punjab, Forest Department, which fact was never disclosed to the complainants by the Opposite Parties. This fact is further fortified from the information obtained by similar located allottees under the Right to Information Act, 2005, from the Government of Punjab, Forest Department, in the matter, vide letter dated 05.05.2015 (at page No.122 of the complainant’s documents), which reads thus :-

“1.   The entry points of the project M/s Emaar MGF Land Ltd. (Mohali Hills) for Sector 109, 108 and 105 have been closed by the Forest Department by thorny fencing wire and digging the trenches.

2.     The above mentioned paths has been closed due to the reason that user agency has not obtained the requisite permission from Government of India for the use of land of Forest Department under FCA 1980 for the paths.

3.     The paths will be opened only after obtaining the final approval from Government of India.

4.     The Case for the paths of Sector 109 is pending adjudication since 03.07.2012 before the Civil Court, Kharar x x x x x”

This fact is further fortified from a letter dated 15.04.2015 (Annexure C-17) sent by the Opposite Parties to the Chief Administrator, GMADA, PUDA to take up the matter of sealing of entries of the project, in question, with the Govt. of Punjab i.e. regarding “illegal access” to their projects. Under these circumstances, a similar question, in a similar project Mohali Hills, Sector 109 came up for consideration before this Commission in the case titled as “Prabhujeev Singh Bajaj Vs. Emaar MGF Land Limited, Complaint case No.43 of 2016, decided on 29.06.2016, this Commission held as under :-

“31.        However, the main grouse of the complainant is that, despite relocation to the said units, even then, actual physical possession thereof, was not offered to him, whereas, on the other hand, paper offer was made to him, vide letters dated 25.08.2014 and 07.11.2014, because when he visited the site after receiving the said letters, to see development and basic amenities, the same were found missing and besides  that, all entry points of the project, had been sealed by the Forest Department, as opposite parties no.1 and 2, failed to take requisite permissions/sanction from it. Thus, in these circumstances, the principal question, which goes to the root of the case, and falls for consideration, is, as to whether, offer of possession made by opposite parties no.1 and 2, to the complainant, vide letters dated 25.08.2014 and 07.11.2014, in respect of the relocated units, could be said to be genuine offer or not. It is well settled law that the onus to prove that the project had been completed and the area/site, in question, is fully developed is on the builder/opposite parties no.1 and 2. It was so said by the National Commission, in Emaar MGF Land Limited and another Vs. Krishan Chander Chandna, First Appeal No.873 of 2013 decided on 29.09.2014. It is very strange that not even an iota of evidence has been placed, on record, by opposite parties no.1 and 2, to prove that when offer was made to the complainant, in respect of the units, in question, development work was complete and that all the basic amenities were in existence. On the other hand, in case, all the development activities, had been undertaken, and completed at the site, by the said dates, then it was for opposite parties no.1 and 2, which could be said to be in possession of the best evidence, to produce cogent and convincing documentary evidence, in the shape of the reports and affidavits of the Engineers/Architects, as they could be said to be the best persons, to testify, as to whether, all these development activities, had been undertaken and completed at the site or not, but they failed to do so. Opposite parties no.1 and 2 were also required to produce on record, a copy of the Completion Certificate (if obtained), having been issued by the Competent Authority, which could be said to be best evidence, to prove their case, but they miserably failed to do so. It is well settled law that before offering/delivery of possession of unit, in a project, it is mandatory to obtain completion certificate, from the Competent Authority(s), failing which the purchaser is at liberty to say no, to such an offer.

                Secondly, the complainant has placed on record, copies of the RTI Information, relating to the said project, in question. Vide RTI Information dated 29.04.2014 Annexure C-31, it was clearly intimated by Greater Mohali Area Development Authority (GMADA), that opposite parties no.1 and 2, had not even applied to them for commission of sewerage treatment plant, water supply, electricity etc. Not only this, it is further evident from  RTI Information dated 26.02.2015 Annexure C-30, issued by the Punjab State Power Corporation Limited (PSPCL), that no regular electricity connection has been released in the sector, in question, wherein the plots are situated. The said RTI Information goes unrebutted by opposite parties no.1 and 2. Not even a single document has been brought on record to prove that the information relating to non-existence of basic amenities, mentioned in the said RTI Information is false, or that the said information was fabricated by the complainant. Had the said information been false or fabricated, opposite parties no.1 and 2, could have obtained certificate from the said Authorities, to say that the same had not been supplied from their Department, but they (opposite parties no.1 and 2) failed to do so. Thus, it could safely be said that the complainant has proved his case, that opposite parties no.1 and 2 did not even obtain permission to provide basic amenities such as water, electricity etc., till  29.04.2014 or 26.02.2015, the dates when RTI information aforesaid, was issued by the Authorities concerned.

                Not only this, it is also an admitted case, that entry points of the project had been sealed by the Forest Department, as opposite parties no.1 and 2, failed to take requisite permissions/ sanction from it, which fact has also been admitted by them (Opposite Parties no.1 and 2), in paragraph No.26 of their written version. Not only this, the said fact is further corroborated from the letter dated 15.04.2015 Annexure-4 (at page 190 of the file), sent by opposite parties no.1 and 2, to the Chief Administrator, GMADA, requesting it to take up the matter with the Forest Department, regarding sealing of entry points of the project, in question, as the same had been stated to be “illegal access”. It has been clearly mentioned by opposite parties no.1 and 2, in the said letter that “…….we are bound by the agreement to give delivery within time bound manner to our various restive customers, we had applied for grant of access with your good self”. This admission of the opposite parties no.1 and 2, in the letter dated 15.04.2015 written to the Chief Administrator, GAMDA, itself clearly goes to prove that even till that date (15.04.2015), they  were not in a position, to deliver possession of the plot(s) to their customers, including the complainant, in the said project, on account of reason that the entries thereof  had been sealed by the Forest Department, stating it to be an “illegal access through the Forest Strip”, permissions/sanction, whereof has not been obtained by them. Not even a single piece of evidence has been brought on record, to prove that the said entry points have been got reopened by opposite parties no.1 and 2, after having obtained permission from the Authorities concerned. If it is so, then it remained unclarified by opposite parties no.1 and 2, as to when entry points of the project were sealed, how could they offer possession of the units, to the allottees, including the complainant, in the year 2014.

                A plea was also taken by opposite parties no.1 and 2 that only recently the Forest Department has served notice on them, alleging illegal access created by them, through the Forest land. To the contrary, perusal of RTI Information dated 05.05.2015 Annexure C-28 (colly.) (at pages 120 to 127 of the file) issued by the Government of Punjab, reveals that a court case with regard to dispute between the Forest Department and opposite parties no.1 and 2, is pending litigation before the Civil Court Kharar, since 03.07.2012, as opposite parties no.1 and 2 have violated Sections 29,33 and 63 of the Indian Forest Act 1927 and have also violated the directions passed by the Hon'ble Supreme Court of India, vide order dated 12.12.1996. The said RTI Information also goes unrebutted by opposite parties no.1 and 2. Thus, the matter with regard to entry points aforesaid, in respect of the said sector, in dispute, was an old dispute, between the Forest Department and opposite parties no.1 and 2, as they had not taken permission from the Competent Authorities, which fact was not disclosed by them, in their written version, filed before this Commission. 

                In view of above, it is held that the act of opposite parties no.1 and 2, in offering paper possession of the units, in question, vide letters 25.08.2014 and 07.11.2014, in the absence of development work; basic amenities at the site; non-obtaining of completion certificate, and also entry points of the project being sealed/closed by the Forest Department, amounted to deficiency in providing service and also adoption of unfair trade practice. It is therefore held that the offer of possession made by opposite parties no.1 and 2, vide letters dated 25.08.2014 and 07.11.2014 is nothing, but a paper possession, which is not sustainable, in the eyes of law.”

Aggrieved against the afore-extracted order passed by this Commission, the Opposite Parties filed First Appeal No.997 of 2016 in the Hon'ble National Consumer Disputes Redressal Commission, New Delhi, wherein, the matter was settled between the parties on 08.11.2016, as per the Settlement Agreement.

              It is pertinent to note that the Opposite Parties  (Emaar MGF) filed appeal in another case i.e. First Appeal bearing No. 709 of 2016 titled as ‘Emaar MGF Land Limited Vs. Mandeep Saini’ before the Hon'ble National Consumer Disputes Redressal Commission, New Delhi, against the order of this Commission and the Hon'ble National Consumer Disputes Redressal Commission, New Delhi passed the order dated 14.09.2016, which reads thus :-

“x x x x xx

It is vehemently argued by Mr.Aditya Narain, learned counsel appearing for the Appellant that since the delay in delivery of possession of the flats in Sectors 104, 106, 108 and 109 is directly attributed to the sealing of the main access road to these Sectors by the Forest Department, one of the factors which weighed with the State Commission, falls within the ambit of force majeure clause in the agreement, there is no deficiency in service on the part of the Appellant in its alleged failure to deliver the possession of the subject flats in question by the committed time.  He thus prays that ex parte ad interim stay may to be continued. 

Prima facie, we are not convinced with the submission.  Hence, without expressing final opinion on the issue but having regard to the fact that the sealing orders have not yet been revoked and the Appellant is still not in a position to deliver possession of the fully developed flats with proper access, to the Complainants, we direct that the Appellant shall deposit in this Commission the principal amount(s) deposited by the Complainants with them, within 6 weeks from today.  On deposit of the said amount(s), it will be open to the Complainants to withdraw the said amount, on filing affidavits, undertaking to this Commission that they will refund the amount(s) withdrawn, if so directed at the time of final disposal of the Appeals.  Subject to the said deposits, the operation of the remaining directions, regarding interest, compensation, etc., in the impugned order shall remain stayed.

X x x x x xx x”

From the afore-extracted order, it is clearly proved that Counsel for the Opposite Parties admitted before the Hon'ble National Consumer Disputes Redressal Commission, New Delhi that the delay in delivery of possession to these Sectors i.e. Sectors 104, 106, 108 & 109 was due to the sealing of main access road by the Forest Department. It is clearly proved that the Hon'ble National Consumer Disputes Redressal Commission, New Delhi without expressing final opinion on the issue but having regard to the fact that the sealing orders have not yet been revoked and the Appellant i.e. Emaar MGF Land Limited is still not in a position to deliver possession of the fully developed units with proper access, to the complainants i.e. till the passing of the afore-extracted order dated 14.09.2016.

              Not only this, the complainants have placed on record the information under RTI dated 14.12.2016 (Annexure C-32) alongwith their rejoinder, which was obtained by the other allottee from Department of Forests & Wildlife Preservation, Punjab, which reads thus :-

“As per record of this office, there is no NOC/approval has been issued by MoEF, Government of India regarding approach road under Forest Conservation Act, 1980 to Emaar MGF, Sector 109.”

In view of the aforesaid information under RTI, it is clearly proved that till 14.12.2016 there was no approval/NOC issued by MoEF, Government of India regarding approach road under Forest Conservation Act, 1980 to Sector 109 of the Opposite Parties. So, in view of all the aforesaid RTI informations annexed by the complainants, it is clearly proved that the possession offered by the Opposite Parties vide letter dated 09.10.2014 is only a paper possession and not more than that.

13.          The next question that falls for consideration, is, as to whether, the complainants were bound to accept offer of possession, in respect of the unit, in question, when the same was offered to them vide letter of intimation of possession dated 09.10.2014 (Annexure C-14), i.e. after long delay of more than 4 years, and that too, in the absence of any force majeure circumstances. It may be stated here that non-delivery of possession of the unit, in question, by the stipulated date, is a material violation of the terms and conditions of the Agreement. It is not the case of the Opposite Parties that the said delay occurred, on account of force majeure circumstances, met by them, on account of some stay or any other valid reason. Under similar circumstances, this Commission, in the case of Brig Ajay Raina (Retd.) and another Vs. M/s Unitech Limited, Consumer Complaint No.59 of 2016, decided on 24.05.2016, while relying upon the judgments rendered by the Hon`ble National Commission, held as under:-

Further, even if, it is assumed for the sake of arguments, that offer of possession, was made to the complainants, in July 2015 i.e. after a delay of about three years, from the stipulated date, even then, it is not obligatory upon the complainants to accept the same. It was so held by the National Commission in Emaar   MGF   Land   Limited   and   another   Vs. Dilshad Gill, III (2015) CPJ 329 (NC). Recently also, under similar circumstances, in the case of M/s. Emaar MGF Land Ltd. & Anr. Vs. Dr.Manuj Chhabra, First Appeal No.1028 of 2015, decided on 19.04.2016, the National Commission, held as under:-

“I am of the prima facie view that even if the said offer was genuine, yet, the Complainant was not obliged to accept such an offer, made after a lapse of more than two years of committed date of delivery”.

The principle of law laid down in the aforesaid cases is fully applicable to the present case. It is therefore held that the complainants could not be held guilty, of filing the present complaint, seeking refund of the deposited amount, alongwith interest and compensation, as possession of the unit was not offered to them by the stipulated date.

 

In the case titled as ‘Emaar MGF Land Ltd. & Anr. Vs. Dyal Singh, First Appeal No.462 of 2014, decided by the Hon'ble National Consumer Disputes Redressal Commission, New Delhi on 03.07.2015.’ The relevant portion of the judgment reads thus :-

“16.    Admittedly, appellants did not offer possession of the apartment within  the prescribed period, in terms of Clause 21 of the “Apartment Buyer’s Agreement”,  Moreover, no explanation has been given by the appellants as to why they did not offer the possession of the apartment by the stipulated period, though respondents had paid substantial amount. As per copy of the Statement of Account filed by the appellants, as on 04-Sep-2012 (Page No.133 of Paper Book of F.A. No.462 of 2014), the respondent has paid a sum of Rs.41,45,068/- out of the total sale price of the apartment, which was Rs.48,65,580.50. Thus, deficiency on the part of the appellants started right from that very moment. It is an admitted fact, that as per the agreement possession of the apartment was to be handed over latest by 23.8.2011. But the appellants admittedly offered the possession of the apartment for the first time only  in the year 2013. When the appellants did not offer the possession of the apartment in question within the specified period, under these circumstances, the respondents were fully justified to refuse the offer of possession, as late as in the year 2013. Thus, appellants themselves have violated the relevant terms and conditions with regard to handing over of the possession. Now it does not lie in their mouth to blame  the respondents for their own negligence (i.e. of the appellants). Therefore, appellants by not delivering the legal physical possession of the apartment within the prescribed period, are not only deficient in rendering  service but are also guilty of indulging into unfair trade practice. The appellants in  the present  case are enjoying the hard earned money  of the respondents since 2008. Now on one pretext or the other, appellants do not want to refund the same, though negligence on the part of the appellants, is writ large in this case.”

The aforesaid appeal was dismissed by the Hon'ble National Consumer Disputes Redressal Commission, New Delhi with punitive damages. Aggrieved against the aforesaid order, Emaar MGF Land Limited filed Special Leave to Appeal (C) No(s). 32492/2015 before the Hon’ble Supreme Court of India and the same was also dismissed.

                   In view of the above, it is held that since there was a material violation on the part of the Opposite Parties, in not handing over physical possession of the unit, complete in all respects, by the stipulated date, as mentioned in the Agreement, the complainants were at liberty, not to accept the offer made after a long delay, and on the other hand, was right by seeking refund of the amount deposited, alongwith interest and compensation, by way of filing the instant complaint.

14.          The next question, that falls for consideration, is, as to whether, the complainants are entitled to refund of the amount of Rs.34,46,604/-, deposited by them. It is not in dispute that the complainants deposited the total amount of Rs.34,46,604/-. It is also not in dispute that the Opposite Parties credited an amount of Rs.7,12,062/- vide credit memo (compensation), as is evident from statement of account (Annexure R-2). It is an admitted fact that the  Opposite Parties are unable to deliver  possession of the unit, in question, complete in all respects, within the stipulated timeframe, as mentioned in the Agreement and the possession offered to the complainants vide letter dated 09.10.2014 is only a paper possession and not more than that. The complainants cannot be made to wait for an indefinite period, for delivery of actual physical possession of the unit, in question. The  Opposite Parties, therefore, had no right, to retain the hard-earned money of the complainants, deposited towards price of the unit, in question. The complainants are thus, entitled to get refund of amount deposited by them. In view of above facts of the case, the Opposite Parties are also under an obligation to compensate the complainants, for inflicting mental agony and causing physical harassment to them.

15.          It is to be further seen, as to whether, interest, on the amount refunded, can be granted, in favour of the  complainants. It is not in dispute that an amount of Rs.34,46,604/-, was paid by the complainants, without getting anything, in lieu thereof. The said amount has been used by the  Opposite Parties, for their own benefit. There is no dispute that for making delayed payments, the  Opposite Parties were charging heavy rate of interest (compounded @15% p.a.) as per Clause 3 of the Agreement, for the period of delay in making payment of installments.  It is well settled law that whenever money has been received by a party and when its refund is ordered, the right to get interest follows, as a matter of course. The obligation to refund money received and retained without right implies and carries with it, the said right. It was also so said by the Hon`ble Supreme Court of India, in UOI vs. Tata Chemicals Ltd (Supreme Court), (2014) 6 SCC 335 decided on March 20th, 2014 (2014) 6 SCC 335). In view of above, the  complainants are certainly entitled to get refund of the amount deposited by them, to the tune of Rs.34,46,604/-alongwith interest @15% p.a. compounded, from the respective dates of deposits till realization. 

16.          As far as the plea taken by the Opposite Parties, regarding forfeiture of earnest money is concerned, it may be stated here that the same stands rejected, because it is not their (Opposite Parties) case, that they were ready with possession of the unit/plot, to be delivered to the complainants, by the stipulated date but it was they (complainants) who wanted to rescind the contract, on account of some unavoidable circumstances/ financial constraints or for any personal reason, and are seeking refund of the amount deposited. Had this been the case of the Opposite Parties, only in those circumstances, it would have been held that since the complainants themselves are rescinding the contract, as such, they are entitled to the amount deposited, after deduction of the earnest money, as per the terms and conditions of the Agreement. In this view of the matter, the plea taken by the Opposite Parties, in this regard, has no legs to stand and is accordingly rejected.

17.          No other point, was urged, by the Counsel for the parties.

18.          For the reasons recorded above, the complaint is partly accepted, with costs. The Opposite Parties are jointly and severally directed, as under:-

  1. To  refund   the  amount Rs.34,46,604/-, to  the complainants, alongwith interest compounded @ 15% p.a., from the respective  dates of deposits onwards, within 45 days, from   the  date of receipt of a certified copy of  this   order.
  2. To pay compensation, in the sum of Rs.2,00,000/- for causing mental agony and harassment, to the complainants, within 45 days, from the date of receipt of a certified copy of this order.
  3. To pay cost of litigation, to the tune of Rs.50,000/- to the complainants.
  4. In case, the payment of amounts, mentioned in Clauses (i) and (ii), is not made, within the stipulated period, then the Opposite Parties shall be liable to pay the amount mentioned in Clause (i) with interest compounded     @18% p.a., instead of interest compounded @ 15% p.a., from the respective dates of deposits, till realization, and interest compounded @15% p.a., on the  amounts mentioned at Clause (ii) & (iii), from the date of filing the complaint, till realization.

 

19.          Certified Copies of this order be sent to the parties, free of charge.

20.          The file be consigned to Record Room, after completion.

Pronounced.

March 8, 2017.                                Sd/-

[JUSTICE JASBIR SINGH (RETD.)]

[PRESIDENT]

 

Sd/-

 [DEV RAJ]

MEMBER

 

Sd/-

 (PADMA PANDEY)

        MEMBER

rb

 

                    

 

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.