Chandigarh

StateCommission

CC/410/2016

Jai Singh Rana - Complainant(s)

Versus

Emaar MGF Land Ltd., - Opp.Party(s)

Savinder Singh Gill Adv.

08 Dec 2016

ORDER

STATE CONSUMER DISPUTES REDRESSAL COMMISSION,

U.T., CHANDIGARH

 

Complaint case No.

:

410 of 2016

Date of Institution

:

28.07.2016

Date of Decision

:

08.12.2016

 

Jai Singh Rana s/o Sh. Major Singh r/o Flat No.B-231, Palm Court, Opposite Whispering Willows, VIP Road, Zirakpur, District Mohali.

 

……Complainant

V e r s u s

  1. Emaar MGF Land Ltd., SCO No.120-122, First Floor, Sector 17-C, Chandigarh, through its Managing Director/Authorized Signatory.
  2. Emaar MGF Land Ltd., ECE House, 28, Kasturba Gandhi Marg, New Delhi – 110001, through Managing Director/Authorized Signatory.  

                                                    .... Opposite Parties

BEFORE:         JUSTICE JASBIR SINGH (RETD.), PRESIDENT

                        MR. DEV RAJ, MEMBER.

                        MRS. PADMA PANDEY, MEMBER

 

Argued by:      

 

Sh.  Savinder Singh Gill, Advocate for the complainant.

Sh.  Ashim Aggarwal, Advocate alongwith Sh. Pankaj Khullar, Advocate for the Opposite Parties.

 

PER PADMA PANDEY, MEMBER

 

               The facts, in brief, are that the complainant was willing to own a residential plot for his family and personal use and accordingly, they applied for a plot measuring 300 sq. yards in Augusta Park, Sector 109, SAS Nagar, Mohali and paid the booking amount of Rs.10,35,000/- on 23.09.2006 vide receipt (Annexure C-1). Accordingly, plot bearing No.440 was provisionally allotted to the complainant vide provisional allotment letter dated 08.05.2007 (Annexure C-2). Subsequently, Plot Buyer’s Agreement was executed between the parties on 04.07.2007 (Annexure C-3). It was stated that as per Clause 8 of the Agreement, possession of the unit was to be delivered within a period of 2 years from the date of execution of the Agreement, but not later than 3 years i.e. latest by 03.07.2010. It was further stated that the complainant made the total payment of Rs.34,46,604/- to the Opposite Parties in respect of the unit/plot, in question by March, 2009. It was further stated that the complainant also qualified for the waiver of last 5% basic sale price payment vide letters (Annexure C-5 colly.). It was further stated that the complainant also availed loan facility from HDFC Bank for the said plot and Tripartite Agreement was also executed between the complainant, Opposite Parties and the Bank on 03.01.2009. It was further stated that the said loan was paid by the complainant and No Objection Certificate in this regard was issued by the Bank on 16.08.2013 (Annexures C-6 and C-7). It was further stated that the complainant made several correspondences with the Opposite Parties after the stipulated date of delivery of possession and requested about the date of delivery of possession of the plot but they failed to deliver the same (Annexure C-8 colly.). After repeated follow-ups through emails regarding possession, the Opposite Parties sent a letter of intimation of possession vide letter dated 28.07.2015 to the complainant, in which, it was stated that possession of the said plot would be handed over within 60 days of the said letter and further raised a demand of Rs.7,79,243/- for taking possession of the said plot (Annexure C-9). Thereafter, the complainant visited the site on 13.08.2015 and found out the development on the site to be incomplete. It was further stated that the possession could not be handed over to the complainant without having any completion certificate. It was further stated that regarding the main entrance of Sector 109, there is a matter pending before the Civil Court, Kharar under Sections 29, 33 and 63 of Indian Forest Act, 1927 and the Opposite Parties have violated the order passed by the Hon’ble Supreme Court dated 12.12.1996. Copy of intimation obtained in this regard by another allottee of the same project is Annexure C-10. It was further stated that despite lack of basic amenities such as roads/connecting roads, electricity, water, sewerage, storm water, drainage etc. the complainant was offered paper possession vide letter dated 28.07.2015. It was further stated that the aforesaid acts, on the part of the Opposite Parties, amounted to deficiency, in rendering service, and indulgence into unfair trade practice. When the grievance of the complainant, was not redressed, left with no alternative, a complaint under Section 17 of the Consumer Protection Act, 1986 (in short the ‘Act’ only), was filed.

2.           The Opposite Parties, in their joint written version, have taken objection regarding arbitration clause in the Agreement, and also they separately, moved an application u/s 8 of Arbitration and Conciliation Act, 1996 taking a specific objection in this regard for referring the matter to the Arbitrator in terms of the agreed terms and conditions of the Agreement. It was further stated that this Commission has no pecuniary jurisdiction to entertain the complaint. It was further stated that as per Clause 8 of the Agreement, possession was “endeavoured” to be handed over to the complainant within 3 years of execution of the Agreement. Thus, there was no definitive agreement stating that possession would definitely be delivered within 3 years. It is well settled principle of law that in cases of sale of immovable property and construction, time is never regarded as the essence of the contract more so when there is penalty clause under the Agreement for any alleged delay. It was further stated that possession of the unit was offered to the complainant on the completion of amenities and services as per terms of the Agreement. It is admitted regarding booking of plot and execution of the Agreement. It was further stated that the total sale consideration of the unit was Rs.36,19,104/-, out of which, the complainant paid an amount of Rs.34,46,604/-, as per statement of account (Exhibit OP/2). It was further stated that the intimation of possession of the unit was issued on 28.07.2015 when all the amenities were completed but he failed to take over the same. It was further stated that the Opposite Parties were granted exemption under the PAPRA Act and were not required to obtain completion certificate. However, in view of new policy, the Opposite Parties obtained Partial Completion Certificate (Exhibit OP/3). It was further stated that many other allottees have already taken possession of their units in the area where the unit of the complainant is located and got their units registered too. It was further stated that Opposite Parties are entitled to levy holding charges in terms of Clause 9 of the Agreement for failure of the complainant to take over possession. It was further stated that neither there was any deficiency, in rendering service, on the part of the Opposite Parties, nor they  indulged into unfair trade practice.

3.           The complainant, filed rejoinder to the written statement of the Opposite Parties, wherein he reiterated all the averments, contained in the complaint, and refuted those, contained in the written version of the Opposite Parties. 

4.           The Parties led evidence, in support of their case.

5.           We have heard the Counsel for the parties, and have gone through the evidence and record of the case, carefully. 

6.           Admittedly, plot No.440 having approximate area of 300 Sq. yds in Augusta Park, Sector 109 was allotted to the complainant vide provisional allotment letter dated 08.05.2007 (Annexure C-2). It is also the admitted fact that Plot Buyer’s Agreement was executed between the parties on 04.07.2007 (Annexure C-3). It is also the admitted fact that the complainant deposited the total amount of Rs.34,46,604/-, as is evident from statement of account (Exhibit OP/2). It is also the admitted fact intimation of possession letter was sent to the complainant vide letter dated 28.07.2015 (Annexure C-9).

7.           The first question that falls for consideration is, as to whether, in the face of existence of arbitration clause in the Agreement, to settle disputes between the parties through Arbitration, in terms of provisions of Section 8 (amended) of Arbitration Act 1996, this Commission has no jurisdiction to entertain the present complaint. It may be stated here that the objection raised by the Opposite Parties, in this regard, deserves rejection, in view of the judgment passed by this Commission in Abha Arora Vs. Puma Realtors Pvt. Ltd. and another, consumer complaint No.170 of 2015, decided on 01.04.2016, wherein this issue was dealt, in detail, while referring various judgments of the Hon'ble Supreme Court of India; the National Commission, New Delhi, and also Section 3 of the Consumer Protection Act, 1986. Ultimately it was held by this Commission that even in the face of existence of arbitration clause in the Agreement, to settle disputes between the parties through Arbitration, in terms of provisions of Section 8 (amended) of 1996 Act, this Commission has jurisdiction to entertain the consumer complaint. It was also so said by the National Commission, recently, in a case titled as Lt. Col. Anil Raj & anr. Vs. M/s. Unitech Limited, and another, Consumer Case No. 346 of 2013, decided on 02.05.2016. Relevant portion of the said case, reads thus:-

“In so far as the question of a remedy under the Act being barred because of the existence of Arbitration Agreement between the parties, the issue is no longer res-integra.  In a catena of decisions of the Hon’ble Supreme Court, it has been held that even if there exists an arbitration clause in the agreement and a Complaint is filed by the consumer, in relation to certain deficiency of service, then the existence of an arbitration clause will not be a bar for the entertainment of the Complaint by a Consumer Fora, constituted under the Act, since the remedy provided under the Act is in addition to the provisions of any other law for the time being in force. The reasoning and ratio of these decisions, particularly in Secretary, Thirumurugan Cooperative Agricultural Credit Society Vs. M. Lalitha (Dead) Through LRs. & Others  - (2004) 1 SCC 305; still holds the field, notwithstanding the recent amendments in the Arbitration and Conciliation Act, 1986.  [Also see: Skypak Couriers Ltd. Vs. Tata Chemicals Ltd. - (2000) 5 SCC 294 and National Seeds Corporation Limited Vs. M. Madhusudhan Reddy & Anr. - (2012) 2 SCC 506.] It has thus, been authoritatively held that the protection provided to the Consumers under the Act is in addition to the remedies available under any other Statute, including the consentient arbitration under the Arbitration and Conciliation Act, 1986.” 

            In view of the above, and also in the face of ratio of judgments, referred to above, passed by the National Commission and this Commission, the arguments raised by Counsel for the Opposite Parties, stands rejected.

8.            Another objection taken by the Opposite Parties in their written statement with regard to pecuniary jurisdiction, also deserves rejection. It may be stated here, that the complainant has sought refund of an amount of Rs.34,46,604/-paid by him, towards price of the plot, alongwith interest @18% p.a. from the respective dates of deposits, till realization;  compensation to the tune of Rs.5 lacs, for mental agony & harassment; and cost of litigation, to the tune of Rs.1,00,000/-, aggregate value whereof [excluding the interest claimed] fell above Rs.20 lacs and below Rs.1 crore. Thus, this Commission has got pecuniary Jurisdiction, to entertain and decide the complaint.

                As far as the interest claimed by the complainant, on the deposited amount is concerned, it is not required to be added, at this stage, to the value of the reliefs claimed, for determining the pecuniary Jurisdiction of this Commission, in view of law laid down by three Member Bench of the National Commission, in a case titled as Shahbad Cooperative Sugar Mills Ltd. Vs. National Insurance Co. Ltd. & Ors. II (2003) CPJ 81 (NC), wherein it was clearly held that since rate and the period for which interest has to be allowed, is within the discretion of Consumer Foras, and that too at the stage, when the complaint is finally disposed of, as such, the same being imaginary would not be taken into consideration, at the time of filing of the same (complaint), for the purpose of determination of pecuniary jurisdiction. Not only as above, in the case of Denis Exports Pvt. Ltd Vs. United India Insurance Co. Ltd, Consumer Case No. 196 of 2016, decided on 08 March 2016, it was clearly held by the National Commission that interest component being imaginary, will not be added in the reliefs sought by the consumers, for determining pecuniary jurisdiction of the Consumer Foras. The principles of law, laid down, in the cases referred to above, are fully applicable, to the facts of the instant case. In view of the above, the objection taken by the Opposite Parties, that this Commission lacks pecuniary Jurisdiction, being devoid of merit, must fail and the same stands rejected.

9.           Another objection raised by Counsel for the Opposite Parties that since it was mentioned in the Agreement that the Company shall endeavour to deliver possession of the plot within maximum period of three years, as such, time was not the essence of contract, is also devoid of merit. It may be stated here that it was clearly mentioned in Clause 8 of the Agreement that possession of the plot will be delivered by the Opposite Parties, within a period of maximum three years, subject to force majeure circumstances or reason beyond the control of the Opposite Parties. In the instant case, the Opposite Parties did not raise any force majeure circumstances, if any, encountered by them. In the absence of any force majeure circumstances having been faced by the Opposite Parties or any other valid and legal reason beyond their control, the stand taken by them, in this regard, for condonation of delay in delivery of possession of the unit, to the complainant, cannot be taken into consideration. Thus, under these circumstances, since as per Clause 8 of the Agreement, the Opposite Parties were bound to deliver possession of the unit, within a maximum period of three years from the date of execution of the same, as such, time was,  unequivocally made the essence of contract.

              Even otherwise, the Opposite Parties cannot evade their liability, merely by saying that since the word tentative/ proposed/tentative was mentioned in the Agreement, for delivery of possession of the unit, as such, time is not to be considered as essence of the contract. Non-mentioning of exact date of delivery of possession of the unit(s) in the Buyer’s Agreement, is an unfair trade practice, on the part of the Builder. The builder is bound to mention the exact/specific date of delivery of possession of the unit(s) to the allottees/purchasers thereof.  It was so said by the Hon’ble National Commission, in Rajeev Nohwar & Anr. V/S Sahajanand Hi Tech Construction Pvt Ltd, 2016 (2) CPR 769. Relevant portion of the said case reads thus:-

“Merely making possession by a particular date will also not meet the requirement of law and the promotor is under a legal mandate to stipulate a specific date for delivery of possession of the flat in the agreement which he executes with the flat buyer”.

In view of above, the plea of the Opposite Parties in this regard also stands rejected.

10.          The next question, that falls for consideration, is, as to whether the Opposite Parties offered possession of the unit/plot, in question, to the complainant, complete in all respects or not. As per Clause 8 of the Agreement, possession of the unit was to be delivered to the complainant within a period of 2 years from the date of execution of the Agreement but not later than 3 years. So, the period of 3 years from the date of execution of the Agreement dated 04.07.2007 has expired on 03.07.2010. However, the Opposite Parties sent letter of intimation to the complainant vide letter dated 28.07.2015 (Annexure C-9) i.e. after a delay of about 5 years. The complainant in his complaint has stated that it is only a paper possession because regarding the main entrance of Sector 109, there is a matter pending before the Civil Court, Kharar. He has also placed on record RTI Information dated 30.06.2015 (Annexure C-10) obtained by another buyer. The relevant portion of the said information reads thus :-

“1 to 4. xxxxxxx

5. Regarding the entry to Sector 109, a case is pending before Hon’ble Civil Court, Kharar from 03.07.2012 u/s 29, 33 and 63 of IFA, 1927 and for violating the Hon’ble Supreme Court’s order dated 12.12.1996. The copies of the documents in regard to the same are annexed herewith.”

From the afore-extracted information, it is clear that the case of entry to Sector 109 is pending before Civil Court, Kharar. It is also relevant to mention here that intimation of possession letter sent to the complainant vide letter dated 28.07.2015 and the Partial Completion Certificate obtained by the Opposite Parties vide memo dated 16.10.2015 i.e. after about three months of offer of possession. It may be stated here that according to the complainant, he after receipt of the intimation of possession letter, visited the site on 13.08.2015 and found out the development on the site to be incomplete. So, it is clearly proved that when the intimation of possession letter sent to the complainant, the project was not complete. Moreover, a lot of emails were sent to the Opposite Parties and requested for possession of the unit but they failed to deliver the same, despite repeated requests. Even the Opposite Parties failed to place on record any document, which could prove that all the basic amenities were complete at the site when the possession was offered. It is also relevant to note that the issues regarding project being sealed by Forest Department and other issues were already decided by this Commission in number of cases, one of which is titled as “Prabhujeev Singh Bajaj Vs. Emaar MGF Land Limited & Anr., Complaint Case No.43 of 2016, decided by this Commission vide order dated 29.06.2016”, the relevant portion of the said judgment reads thus :-.

“31. However, the main grouse of the complainant is that, despite relocation to the said units, even then, actual physical possession thereof, was not offered to him, whereas, on the other hand, paper offer was made to him, vide letters dated 25.08.2014 and 07.11.2014, because when he visited the site after receiving the said letters, to see development and basic amenities, the same were found missing and besides  that, all entry points of the project, had been sealed by the Forest Department, as opposite parties no.1 and 2, failed to take requisite permissions/sanction from it. Thus, in these circumstances, the principal question, which goes to the root of the case, and falls for consideration, is, as to whether, offer of possession made by opposite parties no.1 and 2, to the complainant, vide letters dated 25.08.2014 and 07.11.2014, in respect of the relocated units, could be said to be genuine offer or not. It is well settled law that the onus to prove that the project had been completed and the area/site, in question, is fully developed is on the builder/opposite parties no.1 and 2. It was so said by the National Commission, in Emaar MGF Land Limited and another Vs. Krishan Chander Chandna, First Appeal No.873 of 2013 decided on 29.09.2014. It is very strange that not even an iota of evidence has been placed, on record, by opposite parties no.1 and 2, to prove that when offer was made to the complainant, in respect of the units, in question, development work was complete and that all the basic amenities were in existence. On the other hand, in case, all the development activities, had been undertaken, and completed at the site, by the said dates, then it was for opposite parties no.1 and 2, which could be said to be in possession of the best evidence, to produce cogent and convincing documentary evidence, in the shape of the reports and affidavits of the Engineers/Architects, as they could be said to be the best persons, to testify, as to whether, all these development activities, had been undertaken and completed at the site or not, but they failed to do so. Opposite parties no.1 and 2 were also required to produce on record, a copy of the Completion Certificate (if obtained), having been issued by the Competent Authority, which could be said to be best evidence, to prove their case, but they miserably failed to do so. It is well settled law that before offering/delivery of possession of unit, in a project, it is mandatory to obtain completion certificate, from the Competent Authority(s), failing which the purchaser is at liberty to say no, to such an offer.

                Secondly, the complainant has placed on record, copies of the RTI Information, relating to the said project, in question. Vide RTI Information dated 29.04.2014 Annexure C-31, it was clearly intimated by Greater Mohali Area Development Authority (GMADA), that opposite parties no.1 and 2, had not even applied to them for commission of sewerage treatment plant, water supply, electricity etc. Not only this, it is further evident from  RTI Information dated 26.02.2015 Annexure C-30, issued by the Punjab State Power Corporation Limited (PSPCL), that no regular electricity connection has been released in the sector, in question, wherein the plots are situated. The said RTI Information goes unrebutted by opposite parties no.1 and 2. Not even a single document has been brought on record to prove that the information relating to non-existence of basic amenities, mentioned in the said RTI Information is false, or that the said information was fabricated by the complainant. Had the said information been false or fabricated, opposite parties no.1 and 2, could have obtained certificate from the said Authorities, to say that the same had not been supplied from their Department, but they (opposite parties no.1 and 2) failed to do so. Thus, it could safely be said that the complainant has proved his case, that opposite parties no.1 and 2 did not even obtain permission to provide basic amenities such as water, electricity etc., till  29.04.2014 or 26.02.2015, the dates when RTI information aforesaid, was issued by the Authorities concerned.

                Not only this, it is also an admitted case, that entry points of the project had been sealed by the Forest Department, as opposite parties no.1 and 2, failed to take requisite permissions/ sanction from it, which fact has also been admitted by them (Opposite Parties no.1 and 2), in paragraph No.26 of their written version. Not only this, the said fact is further corroborated from the letter dated 15.04.2015 Annexure-4 (at page 190 of the file), sent by opposite parties no.1 and 2, to the Chief Administrator, GMADA, requesting it to take up the matter with the Forest Department, regarding sealing of entry points of the project, in question, as the same had been stated to be “illegal access”. It has been clearly mentioned by opposite parties no.1 and 2, in the said letter that “…….we are bound by the agreement to give delivery within time bound manner to our various restive customers, we had applied for grant of access with your good self”. This admission of the opposite parties no.1 and 2, in the letter dated 15.04.2015 written to the Chief Administrator, GAMDA, itself clearly goes to prove that even till that date (15.04.2015), they  were not in a position, to deliver possession of the plot(s) to their customers, including the complainant, in the said project, on account of reason that the entries thereof  had been sealed by the Forest Department, stating it to be an “illegal access through the Forest Strip”,permissions/sanction, whereof has not been obtained by them. Not even a single piece of evidence has been brought on record, to prove that the said entry points have been got reopened by opposite parties no.1 and 2, after having obtained permission from the Authorities concerned. If it is so, then it remained unclarified by opposite parties no.1 and 2, as to when entry points of the project were sealed, how could they offer possession of the units, to the allottees, including the complainant, in the year 2014.

                A plea was also taken by opposite parties no.1 and 2 that only recently the Forest Department has served notice on them, alleging illegal access created by them, through the Forest land. To the contrary, perusal of RTI Information dated 05.05.2015 Annexure C-28 (colly.) (at pages 120 to 127 of the file) issued by the Government of Punjab, reveals that a court case with regard to dispute between the Forest Department and opposite parties no.1 and 2, is pending litigation before the Civil Court Kharar, since 03.07.2012, as opposite parties no.1 and 2 have violated Sections 29,33 and 63 of the Indian Forest Act 1927 and have also violated the directions passed by the Hon'ble Supreme Court of India, vide order dated 12.12.1996. The said RTI Information also goes unrebutted by opposite parties no.1 and 2. Thus, the matter with regard to entry points aforesaid, in respect of the said sector, in dispute, was an old dispute, between the Forest Department and opposite parties no.1 and 2, as they had not taken permission from the Competent Authorities, which fact was not disclosed by them, in their written version, filed before this Commission. 

                In view of above, it is held that the act of opposite parties no.1 and 2, in offering paper possession of the units, in question, vide letters 25.08.2014 and 07.11.2014, in the absence of development work; basic amenities at the site; non-obtaining of completion certificate, and also entry points of the project being sealed/closed by the Forest Department, amounted to deficiency in providing service and also adoption of unfair trade practice. It is therefore held that the offer of possession made by opposite parties no.1 and 2, vide letters dated 25.08.2014 and 07.11.2014 is nothing, but a paper possession, which is not sustainable, in the eyes of law.”

Aggrieved against the afore-extracted order passed by this Commission, the Opposite Parties filed First Appeal No.997 of 2016 in the Hon'ble National Consumer Disputes Redressal Commission, New Delhi, wherein, the matter was settled between the parties on 08.11.2016, as per the Settlement Agreement. So, in view of above, it is clearly proved that the Opposite Parties failed to offer possession of the unit complete in all respects to the complainant and it is just a paper possession only.

11.          The next question that falls for consideration, is, as to whether, the complainant was bound to accept offer of possession, in respect of the unit, in question, when the same was offered to him vide letter of intimation of possession dated 28.07.2015 (Annexure C-9), i.e. after a long delay of 5 years and that too, in the absence of any force majeure circumstances. It is pertinent to note that possession of the unit was to be delivered to the complainant within a maximum period of 3 years from the date of execution of the Agreement i.e. latest by 03.07.2010. However, the Opposite Parties sent letter of intimation of possession only vide letter dated 28.07.2015 to the complainant i.e. about 5 years  after the completion of the stipulated period. It may be stated here that non-delivery of possession of the unit, in question, by the stipulated date, is a material violation of the terms and conditions of the Agreement. It is not the case of the Opposite Parties that the said delay occurred, on account of force majeure circumstances, met by them, on account of some stay or any other valid reason. Under similar circumstances, this Commission, in the case of Brig Ajay Raina (Retd.) and another Vs. M/s Unitech Limited, Consumer Complaint No.59 of 2016, decided on 24.05.2016, while relying upon the judgments rendered by the Hon`ble National Commission, held as under:-

Further, even if, it is assumed for the sake of arguments, that offer of possession, was made to the complainants, in July 2015 i.e. after a delay of about three years, from the stipulated date, even then, it is not obligatory upon the complainants to accept the same. It was so held by the National Commission in Emaar   MGF   Land   Limited   and   another   Vs. Dilshad Gill, III (2015) CPJ 329 (NC). Recently also, under similar circumstances, in the case of M/s. Emaar MGF Land Ltd. & Anr. Vs. Dr.Manuj Chhabra, First Appeal No.1028 of 2015, decided on 19.04.2016, the National Commission, held as under:-

“I am of the prima facie view that even if the said offer was genuine, yet, the Complainant was not obliged to accept such an offer, made after a lapse of more than two years of committed date of delivery”.

The principle of law laid down in the aforesaid cases is fully applicable to the present case. It is therefore held that the complainants could not be held guilty, of filing the present complaint, seeking refund of the deposited amount, alongwith interest and compensation, as possession of the unit was not offered to them by the stipulated date.

 

Moreover, the judgment passed by the Hon'ble National Consumer Disputes Redressal Commission, New Delhi titled as ‘Emaar MGF Land Ltd. & Anr. Vs. Dyal Singh, First Appeal No.462 of 2014, decided on 03.07.2015.’ The relevant portion of the judgment reads thus :-

“16.    Admittedly, appellants did not offer possession of the apartment within  the prescribed period, in terms of Clause 21 of the “Apartment Buyer’s Agreement”,  Moreover, no explanation has been given by the appellants as to why they did not offer the possession of the apartment by the stipulated period, though respondents had paid substantial amount. As per copy of the Statement of Account filed by the appellants, as on 04-Sep-2012 (Page No.133 of Paper Book of F.A. No.462 of 2014), the respondent has paid a sum of Rs.41,45,068/- out of the total sale price of the apartment, which was Rs.48,65,580.50. Thus, deficiency on the part of the appellants started right from that very moment. It is an admitted fact, that as per the agreement possession of the apartment was to be handed over latest by 23.8.2011. But the appellants admittedly offered the possession of the apartment for the first time only  in the year 2013. When the appellants did not offer the possession of the apartment in question within the specified period, under these circumstances, the respondents were fully justified to refuse the offer of possession, as late as in the year 2013. Thus, appellants themselves have violated the relevant terms and conditions with regard to handing over of the possession. Now it does not lie in their mouth to blame  the respondents for their own negligence (i.e. of the appellants). Therefore, appellants by not delivering the legal physical possession of the apartment within the prescribed period, are not only deficient in rendering  service but are also guilty of indulging into unfair trade practice. The appellants in  the present  case are enjoying the hard earned money  of the respondents since 2008. Now on one pretext or the other, appellants do not want to refund the same, though negligence on the part of the appellants, is writ large in this case.”

The aforesaid appeal was dismissed by the Hon'ble National Consumer Disputes Redressal Commission, New Delhi with punitive damages. Aggrieved against the aforesaid order, Emaar MGF Land Limited filed Special Leave to Appeal (C) No(s). 32492/2015 before the Hon’ble Supreme Court of India and the same was also dismissed.

                   In view of the above, it is held that since there was a material violation on the part of the Opposite Parties, in not handing over physical possession of the unit, complete in all respects, by the stipulated date, as mentioned in the Agreement, the complainant was at liberty, not to accept the offer made after a long delay, and on the other hand, was right by seeking refund of the amount deposited, alongwith interest and compensation, by way of filing the instant complaint.

12.          The next question, that falls for consideration, is, as to whether, the complainant is entitled to refund of the amount of Rs.34,46,604/-, deposited by him. It is an admitted fact that the  Opposite Parties are unable to deliver  possession of the unit, in question, within the stipulated period, as mentioned in the Agreement and firm date of delivery of possession of the unit, could not be given to him (complainant). The complainant cannot be made to wait for an indefinite period, for delivery of actual physical possession of the plot purchased by him. The  Opposite Parties, therefore, had no right, to retain the hard-earned money of the complainant, deposited towards price of the unit, in question. Even the Opposite Parties sent letter of intimation of possession to the complainant, which is just a paper possession only. The complainant is thus, entitled to get refund of amount deposited by him. In view of above facts of the case, the  Opposite Parties are also under an obligation to compensate the complainant, for inflicting mental agony and causing physical harassment to him.

13.          It is to be further seen, as to whether, interest, on the amount refunded, can be granted, in favour of the  complainant. It is not in dispute that an amount of Rs.34,46,604/-, was paid by the complainant, without getting anything, in lieu thereof. The said amount has been used by the  Opposite Parties, for their own benefit. There is no dispute that for making delayed payments, the  Opposite Parties were charging heavy rate of interest (compounded @15%) as per Clause 3 of the Agreement, for the period of delay in making payment of installments.  It is well settled law that whenever money has been received by a party and when its refund is ordered, the right to get interest follows, as a matter of course. The obligation to refund money received and retained without right implies and carries with it, the said right. It was also so said by the Hon`ble Supreme Court of India, in UOI vs. Tata Chemicals Ltd (Supreme Court), (2014) 6 SCC 335 decided on March 20th, 2014 (2014) 6 SCC 335). In view of above, the  complainant is certainly entitled to get refund of the amount deposited by him, to the tune of Rs.34,46,604/-alongwith interest @15% p.a. compounded, from the respective dates of deposits till realization.

14.           As far as the plea taken by Counsel for the Opposite Parties at the time of arguments, regarding forfeiture of earnest money is concerned, it may be stated here that the same stands rejected, because it is not their (Opposite Parties) case, that they were ready with possession of the plot, to be delivered to the complainant, by the stipulated date but it was he (complainant) who wanted to rescind the contract, on account of some unavoidable circumstances/ financial constraints or for any personal reason, and is seeking refund of the amount deposited. Had this been the case of the Opposite Parties, only in those circumstances, it would have been held that since the complainant himself is rescinding the contract, as such, he is entitled to the amount deposited, after deduction of the earnest money, as per the terms and conditions of the Agreement. In this view of the matter, the plea taken by the Opposite Parties, in this regard, has no legs to stand and is accordingly rejected.

15.          Since, it has already been held that the complainant is entitled to refund of the amount deposited, alongwith interest and compensation, as such, the plea taken by the Opposite Parties to the effect that they are ready to pay penalty amount for the period of delay, in delivery of possession cannot be considered, at this stage. If the Opposite Parties are allowed to invoke Clause 8 of the Agreement, in the instant case, regarding payment of penalty, that would amount to enriching them, at the cost of the complainant. The defence taken is accordingly rejected.

16.          No other point, was urged, by Counsel for the parties.

17.          For the reasons recorded above, the complaint is partly accepted, with costs. The  Opposite Parties are jointly and severally directed as under:-

  1. To refund the amount Rs.34,46,604/-, to  the  complainant, alongwith interest @15% p.a. compounded,  from the respective  dates  of  deposits onwards.
  2. To pay compensation, in the sum of Rs.2 lacs, for causing mental agony and physical harassment, to the complainant.
  3. To pay cost of litigation, to the tune of Rs.50,000/- to the  complainant.
  4. The payment of awarded amounts mentioned at sr.nos.(i) to (iii), shall be made, within a period of 02 (two) months from the date of receipt of a certified copy of this order, failing which, the amount mentioned at sr.no.(i) shall carry penal interest @18% p.a. compounded, instead of @15% p.a. compounded, from the respective dates of deposits onwards, and interest @15% p.a. compounded, on the amounts mentioned at sr.nos.(ii) and (iii), from the date of filing of this complaint, till realization.

18.          However, it is made clear that, if the complainant has availed loan facility from any banking or financial institution, for making payment of installments towards the said unit, it will have the first charge of the amount payable, to the extent, the same is due to be paid by him (complainant).

19.          Certified Copies of this order be sent to the parties, free of charge.

20.          The file be consigned to Record Room, after completion.

Pronounced.

December 8, 2016.                                         Sd/-

[JUSTICE JASBIR SINGH (RETD.)]

[PRESIDENT]

 

Sd/-

 [DEV RAJ]

MEMBER

 

Sd/-

 (PADMA PANDEY)

        MEMBER

rb

 

 

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.