
Surinder Bains filed a consumer case on 28 Mar 2017 against Emaar MGF Land Limited in the StateCommission Consumer Court. The case no is CC/353/2016 and the judgment uploaded on 28 Mar 2017.
STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
U.T., CHANDIGARH
Complaint case No. | : | 353 of 2016 |
Date of Institution | : | 15.07.2016 |
Date of Decision | : | 28.03.2017 |
Surinder Bains w/o Late Sh. R.S.Bains, K.No. 127, Phase 3B1, SAS Nagar, Mohali.
……Complainant
.... Opposite Parties
BEFORE: JUSTICE JASBIR SINGH (RETD.), PRESIDENT
MR. DEV RAJ, MEMBER.
MRS. PADMA PANDEY, MEMBER
Argued by:
Sh. R.S.Pandher, Advocate for the complainant.
Sh. Ashim Aggarwal, Advocate for the Opposite Parties.
PER PADMA PANDEY, MEMBER
The facts, in brief, are that the complainant was induced by the representative of the Opposite Parties in November, 2005, as such, she agreed to purchase plot No.69 in Augusta Greens in Sector 109 and she was promised to deliver plot within the period of two years. As per Advance Registration Form, allotment of the plot would be made within the period of nine months from the date of application. Copy of Advance Registration Form submitted on 19.11.2005 alongwith cheque is Annexure C-1 (Colly.). Then the Opposite Parties delayed the issuance of allotment letter, asked the complainant to pay the amount of Rs.13,80,000/-, which was paid by her on 30.09.2006 and after a long delay, allotment letter was issued on 09.05.2007 (Annexure C-1/1). The total sale consideration, as per provisional allotment letter dated 09.05.2007 is Rs.51,75,000/- plus PLC and additional EDC. Plot Buyer’s Agreement was executed between the parties, at Chandigarh, on 18.06.2007 (Annexure C-2). As per Clause 8 of the Agreement, possession of the plot was to be delivered within a period of two years from the date of execution of the Agreement but not later than three years i.e. latest by 17.06.2009 or not later than 17.06.2010. It was further stated that the complainant paid the amount of Rs.60,04,216/- till 13.01.2010, as mentioned in the statement of account (Annexure C-3). It was further stated that there was lack of development at project site, regarding which, the complainant submitted letters dated 05.05.2008, 05.01.2009, 17.04.2009 etc., copies of which are at Annexure C-4 (Colly.). It was further stated that vide letter dated 28.12.2009 (Annexure C-5), the Opposite Parties informed the complainant that the development activities in Sector 105, 108 and 109 are in full swing and temporary electricity & water connections were sanctioned for the project and he was asked to deposit more amount for revised area alongwith due amount and delayed interest, thereafter possession of the plot would be handed over to her. It was further stated that the Opposite Parties were sending such misleading letters inspite of the fact that development work was not complete and the Opposite Parties were not having necessary permissions for the project from the Government Authorities. As per the demand of the Opposite Parties, the complainant deposited an amount of Rs.20,58,285/- on 13.01.2010 and amount of Rs.1,50,931/- on 23.02.2010. Thereafter, the Opposite Parties sent letter dated 16.12.2011 (Annexure C-6) mentioning that upon receipt of completion certificate from GMADA, they were to commence the process and execution of the sale deed. The complainant visited number of times to the office of the Opposite Parties and complained regarding lack of development at the project site but they kept on delaying by promising that possession would be delivered soon. The Opposite Parties issued letter dated 13.06.2014 stating that they would be commencing the process of execution and registration of conveyance deed in favour of the complainant shortly and asked her to make the payment by 16.07.2014 to hand over the possession of the plot to her (Annexure C-7). Thereafter, the Opposite Parties sent a letter dated 23.07.2014 asking the complainant to deposit the amount of Rs.8,85,906/- (Annexure C-8). It was further stated that by including enhanced area sale price, the total basic sale price came to Rs.58,02,972/- for which he paid the amount of Rs.60,04,216/-. It was further stated that the Opposite Parties were playing fraud with the complainant, just to extract more money from her, as they were not having mandatory completion certificate issued by GMADA in their favour. Despite receipt of the huge amount from the complainant, the Opposite Parties failed to offer legal and actual possession of the plot to the complainant. The project site still lacks proper facilities of access, electricity and water supply etc. The Opposite Parties remained involved in dispute with Forest Authorities and the entry and exit points of the project remained closed. It was further stated that the Opposite Parties made offer of paper/unlawful possession of the plot for 16.07.2014 and, thereafter, sent letters dated 23.07.2014 and 26.08.2014 for payment of amount. It was further stated that the aforesaid acts, on the part of the Opposite Parties, amounted to deficiency, in rendering service, and indulgence into unfair trade practice. When the grievance of the complainant, was not redressed, left with no alternative, a complaint under Section 17 of the Consumer Protection Act, 1986 (in short the ‘Act’ only), was filed.
2. The Opposite Parties, in their written version, have stated that the complaint is time barred as it has been filed more than two years after accrual of alleged cause of action i.e. on 28.12.2009 when the possession was offered to the complainant for the first time and thereafter, reminder was sent to her on 16.12.2011 (Annexure C-6) to take over possession and initiate construction, which they have failed to do. It was further stated that the complainant did not fall within the definition of “Consumer” as per the Consumer Protection Act, 1986, as she purchased the plot for investment/commercial purposes. It was further stated that this Commission has no pecuniary jurisdiction to entertain the complaint as the claim amount together with interest exceeds Rs.1 crore. It was averred that the intimation of possession was admittedly sent to the complainant in 2009 upon completion of amenities, as per the Agreement but she failed to take possession for the reasons best known to her. It was further stated that the complainant has not led any evidence to prove that the area was not developed in 2010. The complainant is entitled to levy holding charges, in terms of Clause 9 of the Agreement, for failure of the complainant to take over possession. It was denied regarding any inducement by the representative of the Opposite Parties. It was admitted regarding booking of the plot, execution of the Agreement. It was further stated that as per Clause 8 of the Agreement, possession was endeavoured to be handed over within 3 years of execution of the Agreement. Thus, there was no definitive agreement stating that possession would definitely be delivered within 3 years. It was further stated that it is well settled principle of law that in cases of sale of immovable property and construction, time is never regarded as the essence of the contract more so when there is penalty clause under the Agreement for any alleged delay. It was further stated that the total sale consideration of the unit was mentioned as Rs.54,00,472/- and the complainant paid an amount of Rs.58,53,285/- towards the principal and Rs.1,50,931/- towards the delayed interest against the unit. Thus, total payment made by the complainant is Rs.60,04,216/-. It was further stated that the amount of Rs.8,35,626/- is outstanding against the complainant, for which, manifold reminders have been sent. However, the complainant failed to make the payments and is a defaulter. It was admitted that the Opposite Parties informed the complainant regarding increase in area of the unit. It was denied that the complainant ever visited the office of the Opposite Parties regarding lack of development. It was further stated that all the amenities, as per Clause 23 of the Agreement, have been completed and internal roads, water, sewerage and electrical lines have been laid in the area and such amenities were completed in 2009, when possession was offered. It was further stated that there was no requirement for the Opposite Parties to obtain any completion certificate, as it was exempted from provisions of the PAPRA Act. However, the Opposite Parties obtained Partial Completion Certificate from the Opposite Parties (Exhibit OP/4). It was further stated that this Commission has no jurisdiction to entertain the complaint. It was further stated that neither there was any deficiency, in rendering service, on the part of the Opposite Parties, nor they indulged into unfair trade practice.
3. Even during the pendency of the complaint, the Opposite Parties separately moved an application u/s 8 of Arbitration and Conciliation Act, 1996 taking a specific objection in this regard for referring the matter to the Arbitrator in terms of the agreed terms and conditions of the Agreement. The said application was disposed of vide order dated 14.09.2016 passed in MA/298/2016 and stated that question qua arbitration will be considered at the time of final arguments in the main case.
4. The complainant filed replication to the written statement of the Opposite Parties, wherein she reiterated all the averments, contained in the complaint, and refuted those, contained in the written version of the Opposite Parties.
5. The Parties led evidence, in support of their case.
6. We have heard the Counsel for the parties, and have gone through the evidence and record of the case, carefully.
7. The first question, that falls for consideration, is, as to whether, in the face of existence of arbitration clause in the Agreement, to settle disputes between the parties through Arbitration, in terms of provisions of Section 8 (amended) of 1996 Act, this Commission has no jurisdiction to entertain the consumer complaint. This question has already been elaborately dealt with by this Commission in case titled ‘Sarbjit Singh Vs. Puma Realtors Private Limited’, IV (2016) CPJ 126. Paras 25 to 35 of the said order, inter-alia, being relevant, are extracted hereunder:-
25. The next question, that falls for consideration, is, as to whether, in the face of existence of arbitration Clause in the Agreement, to settle disputes between the parties through Arbitration, in terms of provisions of Section 8 (amended) of 1996 Act, this Commission has no jurisdiction to entertain the consumer complaint.
26. To decide above said question, it is necessary to reproduce the provisions of Section 3 of the Consumer Protection Act 1986 (in short the Act), which reads as under;
“3. Act not in derogation of any other law.—
The provisions of this Act shall be in addition to and not in derogation of the provisions of any other law for the time being in force.”
27. It is also desirable to reproduce unamended provisions of Section 8 of 1996 Act, which reads thus:-
“8. Power to refer parties to arbitration where there is an arbitration agreement.—
(1) A judicial authority before which an action is brought in a matter which is the subject of an arbitration agreement shall, if a party so applies not later than when submitting his first statement on the substance of the dispute, refer the parties to arbitration.
(2) The application referred to in sub-section (1) shall not be entertained unless it is accompanied by the original arbitration agreement or a duly certified copy thereof.
(3) Notwithstanding that an application has been made under sub-section (1) and that the issue is pending before the judicial authority, an arbitration may be commenced or continued and an arbitral award made.”
28. Many a times, by making reference to the provisions of Section 8 of 1996 Act, in the past also, such objections were raised and the Hon'ble Supreme Court of India, when interpreting the provisions of Section 3 of 1986 Act, in the cases of Fair Air Engg. Pvt. Ltd. & another Vs. N. K. Modi (1996) 6 SCC 385, C.C.I Chambers Coop. Housing Society Ltd. Vs Development Credit Bank Ltd. (2003) 7 SCC 233, Rosedale Developers Private Limited Vs. Aghore Bhattacharya and others, (Civil Appeal No.20923 of 2013) etc., came to a conclusion that the remedy provided under Section 3 of 1986 Act, is an independent and additional remedy and existence of an arbitration clause in the agreement, to settle disputes, will not debar the Consumer Foras, to entertain the complaints, filed by the consumers.
29. In the year 2015, many amendments were effected in the provisions of 1996 Act. After amendment, Section 8 of 1996 Act, reads as under:-
“8. Power to refer parties to arbitration where there is an arbitration agreement.—
(1) A judicial authority, before which an action is brought in a matter which is the subject of an arbitration agreement shall, if a party to the arbitration agreement or any person claiming through or under him, so applies not later than the date of submitting his first statement on the substance of the dispute, then, notwithstanding any judgment, decree or order of the Supreme Court or any Court, refer the parties to arbitration unless it finds that prima facie no valid arbitration agreement exists.”
30. Now it is to be seen, whether, after amendment in Section 8 of the principal Act, any additional right has accrued to the service provider(s), to say that on account of existence of arbitration agreement, for settling the disputes through an Arbitrator, the Consumer Foras have no jurisdiction to entertain a consumer complaint. As has been held by Hon'ble Supreme Court of India, in various cases, and also of the National Commission, in large number of judgments, Section 3 of the 1986 Act, provides additional remedy, notwithstanding any other remedy available to a consumer. The said remedy is also not in derogation to any other Act/Law.
31. Now, we will have to see what difference has been made by the amendment, in the provisions of Section 8 of 1996 Act. After amendment, it reads that a Judicial Authority is supposed to refer the matter to an Arbitrator, if there exists an arbitration clause in the agreement, notwithstanding any judgment, decree, order of the Hon'ble Supreme Court of India, or any other Court, unless it finds that prima facie, no valid arbitration agreement exists. The legislation was alive to the ratio of the judgments, as referred to above, in earlier part of this order. Vide those judgments, it is specifically mandated that under Section 3 of 1986 Act, an additional remedy is available to the consumer(s), which is not in derogation to any other Act. As and when any argument was raised, the Hon'ble Supreme Court of India and the National Commission in the judgments, referred to above, have made it very clear that in the face of Section 8 of 1996 Act and existence of arbitration agreement, it is still opened to the Consumer Foras to entertain the consumer complaints. None of the judgments ever conferred any jurisdiction upon the Consumer Foras to entertain such like complaints. Only the legal issues, as existed in the Statute Book, were explained vide different judgments. If we look into amended provisions of Section 8 of the principal Act, it explains that judicial Authority needs to refer dispute, in which arbitration agreement exist to settle the disputes notwithstanding any judgment/decree or order of any Court. That may be true where in a case, some order has been passed by any Court, making arbitration Agreement non-applicable to a dispute/parties. However, in the present case, the above said argument is not available. The jurisdiction of Consumer Foras to entertain consumer complaints, in the face of arbitration clause in the Agreement, is in-built in 1986 Act. It was not given to these Foras, by any judgment ever. The provisions of Section 3 of 1986 Act interpreted vide judgments vis a vis Section 8 of un-amended 1996 Act, were known to the legislature, when the amended Act 2015 was passed. If there was any intention on the part of the legislature, then it would have been very conveniently provided that notwithstanding any remedy available in 1986 Act, it would be binding upon the judicial Authority to refer the matter to an Arbitrator, in case of existence of arbitration agreement, however, it was not so said.
32. We can deal with this issue, from another angle also. If this contention raised is accepted, it will go against the basic spirit of 1986 Act. The said Act (1986) was enacted to protect poor consumers against might of the service providers/multinational companies/traders. As in the present case, the complainant has spent his life savings to get a unit, for his residential purpose. His hopes were shattered. Litigation in the Consumer Fora is cost effective. It does not involve huge expenses and further it is very quick. A complaint in the State Commission can be filed, by making payment between Rs.2000/- to Rs.4000/- (in the present case Rs.4000/-). As per the mandate of 1986 Act, a complaint is supposed to be decided within three months, from the date of service to the opposite party. In cases involving ticklish issues (like the present one, maximum not more than six months to seven months time can be consumed), whereas, to the contrary, as per the principal Act (1996 Act), the consumer will be forced to incur huge expenses towards his/her share of Arbitrator’s fees. Not only as above, it is admissible to an Arbitrator, to decide a dispute within one year. Thereafter, the Court wherever it is challenged may also take upto one year and then there is likelihood that the matter will go to the High Court or the Hon'ble Supreme Court of India. Such an effort will be a time consuming and costly one. Taking note of fee component and time consumed in arbitration, it can safely be said that if the matter is referred to an Arbitrator, as prayed, in the present case, it will defeat the very purpose of the provisions of 1986 Act.
33. The 1986 Act provides for better protection of interests and rights of the consumers. For the said purpose, the Consumer Foras were created under the Act. In Section 3 of 1986 Act, it is clearly provided that the said provision is in addition to and not in derogation of any provisions of any other law, for the time being in force. The 1986 Act is special legislation qua the consumers. The poor consumers are not expected to fight the might of multinational companies/traders, as those entities have lot of resources at their command. As stated above, in the present case, the complainant has spent his entire life earnings to purchase the plot, in the said project, launched by the opposite party. However, his hopes were shattered, when despite making substantial payment of the sale consideration, he failed to get possession of the plot, in question, in a developed project. As per ratio of the judgments in the case of Secretary, Thirumurugan Cooperative Agricultural Credit Society v. M. Lalitha (2004) 1 SCC 305 and United India Insurance Co. Ltd. Vs. M/s Pushpalaya Printers, I (2004) CPJ 22 (SC), and LIC of India and another Vs. Hira Lal, IV (2011) CPJ 4 (SC), the consumers are always in a weak position, and in cases where two interpretations are possible, the one beneficial to the consumer needs to be accepted. The opinion expressed above, qua applicability of Section 8 (amended) of 1996 Act, has been given keeping in mind the above said principle.
34. Not only this, recently, it was also so said by the National Commission, in a case titled as Lt. Col. Anil Raj & anr. Vs. M/s. Unitech Limited, and another, Consumer Case No.346 of 2013, decided on 02.05.2016. Relevant portion of the said case, reads thus:-
“In so far as the question of a remedy under the Act being barred because of the existence of Arbitration Agreement between the parties, the issue is no longer res-integra. In a catena of decisions of the Hon’ble Supreme Court, it has been held that even if there exists an arbitration clause in the agreement and a Complaint is filed by the consumer, in relation to certain deficiency of service, then the existence of an arbitration clause will not be a bar for the entertainment of the Complaint by a Consumer Fora, constituted under the Act, since the remedy provided under the Act is in addition to the provisions of any other law for the time being in force. The reasoning and ratio of these decisions, particularly in Secretary, Thirumurugan Cooperative Agricultural Credit Society Vs. M. Lalitha (Dead) Through LRs. & Others - (2004) 1 SCC 305; still holds the field, notwithstanding the recent amendments in the Arbitration and Conciliation Act, 1986. [Also see: Skypak Couriers Ltd. Vs. Tata Chemicals Ltd. - (2000) 5 SCC 294 and National Seeds Corporation Limited Vs. M. Madhusudhan Reddy & Anr. - (2012) 2 SCC 506.] It has thus, been authoritatively held that the protection provided to the Consumers under the Act is in addition to the remedies available under any other Statute, including the consentient arbitration under the Arbitration and Conciliation Act, 1986.”
35. In view of the above, the plea taken by the opposite party, that in the face of existence of arbitration clause in the Agreement, to settle disputes between the parties through Arbitration, in terms of provisions of Section 8 (amended) of 1996 Act, this Commission has no jurisdiction to entertain the consumer complaint, being devoid of merit, is rejected.”
In view of the above, the objection raised by Counsel for the Opposite Parties, being devoid of merit, is rejected.
8. The next question that falls for consideration, is, as to whether, this Commission has territorial jurisdiction to entertain and decide the complaint or not.
According to Section 17 of the Act, a consumer complaint can be filed, by the complainant, before the State Consumer Disputes Redressal Commission, within the territorial Jurisdiction whereof, a part of cause of action arose to her. In the instant case, it is evident from the record, that Plot Buyer’s Agreement was executed between the allottee(s) and the Opposite Parties at Chandigarh on 18.06.2007 (Annexure C-2). Not only this, even the provisional allotment letter (Annexure C-1/1), possession letter dated 28.12.2009 (Annexure C-5) and letters (Annexures C-6 to C-9) were also sent by the Opposite Parties from their Chandigarh Office, as the same bore the address of the Company as “SCO 120-122, First Floor, Sector 17-C, Chandigarh”. Since, as per the documents, referred to above, a part of cause of action arose to the complainant, at Chandigarh, this Commission has got territorial Jurisdiction to entertain and decide the complaint. The objection taken by the Opposite Parties, in their written version, in this regard, therefore, being devoid of merit, must fail, and the same stands rejected.
9. Another objection taken by the Opposite Parties, with regard to pecuniary jurisdiction, also deserves rejection. As per admitted facts, the complainant has sought refund of the whole amount of Rs.60,04,216/- alongwith interest @15% p.a. compounded ; compensation to the tune of Rs.5 lacs on account of mental agony and physical harassment and cost of litigation to the tune of Rs.50,000/-. It is argued by Counsel for the Opposite Parties that if the entire claimed amount is added, alongwith interest claimed, it will cross Rs.1 crore and in that event, it will not be open to this Commission to entertain and adjudicate this complaint, for want of pecuniary jurisdiction. This issue, whether interest is to be counted when looking into pecuniary jurisdiction of this Commission, came up for consideration in the case of Surjit Singh Vs. M/s Emaar MGF Land Pvt. Ltd. and another, Consumer Case no. 484 of 2016 decided on 15.12.2016, wherein, after noting similar objections it was observed as under:-
“13. Now we will deal with another contention of the opposite parties that for want of pecuniary jurisdiction, it is not open to this Commission to entertain and adjudicate this complaint. As per admitted facts, the complainant has sought refund of amount paid i.e. Rs.48,95,264/- alongwith interest @12% p.a. from the respective date of deposits; compensation to the tune of Rs.5 lacs, for mental agony and physical harassment and cost of litigation to the tune of Rs.55,000/-. It is argued by Counsel for the opposite parties that if his entire claimed amount is added, alongwith interest claimed, it will cross Rs.1 crore and in that event it will not be open to this Commission to entertain and adjudicate this complaint, for want of pecuniary jurisdiction. To say so, reliance has been placed upon ratio of judgment of a Larger Bench of the National Commission, in the case of Ambrish Kumar Shukla (supra). In the said case, it was specifically observed that when determining pecuniary jurisdiction of the Consumer Foras, it is the value of the goods and services, which has to be noted and not the value of deficiencies claimed. Further, that interest component also has to be taken into account, for the purpose of determining pecuniary jurisdiction.
14. In the first blush, if we look into the ratio of the judgment, referred to above, it appears that this Commission will not have pecuniary jurisdiction to entertain this complaint. However, on deep analysis, we are going to differ with the argument raised by Counsel for the opposite parties. Judgment in the case of Ambrish Kumar Shukla (supra) was rendered by Three Judges Bench of the National Commission, without noting its earlier view of the subject. This issue, whether, when determining pecuniary jurisdiction of the State Commission/ Consumer Foras, interest is to be added with other relief claimed or not, came up for consideration, before the Three Judges Bench of the National Commission in Shahbad Cooperative Sugar Mills Ltd. Vs. National Insurance Co. Ltd. And Ors., II 2003 CPJ 81 (NC). In the said case, noting similar arguments, it was observed as under:-
“3. Complaint (at pp 17-36) was filed with the following prayer :
“It is, therefore, respectfully prayed that the complaint be allowed and the opposite parties be directed to pay the claim to the tune of Rs. 18,33,000/- plus interest @ 18% from the date of claim till its realization. Also the suitable damages caused to the complainant be ordered to be paid to the complainant.”
4. Bare reading of the prayer made would show that the interest claimed by appellant pertains to the period upto the date of filing complaint, pendente lite and future. Rate and the period for which interest has to be allowed, is within the discretion of State Commission and the stage for exercise of such a discretion would be the time when the complaint is finally disposed of. Thus, the State Commission had acted erroneously in adding to the amount of Rs. 18,33,000/- the interest at the rate of 18% per annum thereon till date of filing of complaint for the purpose of determination of pecuniary jurisdiction before reaching the said stage. Order under appeal, therefore, deserves to be set aside. However, in view of change in pecuniary jurisdiction w.e.f. 15.3.2003, the complaint is now to be dealt with by the District Forum instead of State Commission.”
15. It was specifically stated that interest claimed by appellant/complainant pertained to the period upto the date of filing complaint, pendente lite and future, need not be added in the relief claimed, to determine pecuniary jurisdiction of the State Commission/Consumer Foras. It was rightly said that the rate and period for which the interest has to be allowed, is within the discretion of the particular Consumer Fora, and the stage for exercise of such discretion would be the time, when final order is passed. We are of the considered opinion that the view taken is perfectly justified. There may be cases, where the complainant may not be entitled to claim any interest upon the amount paid, like the one, where he is rescinding his contract and further at what rate interest is to be granted will be determined by the competent Consumer Fora, by looking into the facts of each case. All cases cannot be put into a straitjacket formula, to add interest claimed, to determine pecuniary jurisdiction of the Consumer Foras. The interest, which is a discretionary relief, cannot be added to the value of the goods or services, as the case may be, for the purpose of determining the pecuniary jurisdiction of the Consumer Foras. As per provisions of the Consumer Protection Act, 1986 (Act) value of the goods purchased or services plus (+) compensation claimed needs to be added only, for determining pecuniary jurisdiction of the Consumer Foras.
As per ratio of the judgment of the Supreme Court in the case of New India Assurance Co. Ltd. Vs. Hilli Multipurpose Cold Storage Pvt. Ltd., Civil Appeal No.10941-10942 of 2013, decided on 04.12.2015, we would like to follow the view expressed by Three Judges Bench (former Bench) of the National Commission in Shahbad Cooperative Sugar Mills Ltd. case (supra), in preference to the ratio of judgment passed by a Bench of co-equal strength (subsequent Bench) of the National Commission in the case of Ambrish Kumar Shukla case (supra).
In New India Assurance Co. Ltd. case (supra), it was specifically observed by the Supreme Court that when a former Bench of co-equal strength has given a finding qua one legal issue, it is not open to the subsequent Bench of co-equal strength to opine qua that very legal issue and give a contrary finding. At the maximum, the subsequent Bench of co-equal strength can refer the matter to the President/Chief Justice of India to constitute a bigger Bench, to look into the matter and reconsider the legal proposition. It was further specifically held that, in case, there are two contrary views by the former and later co-equal strength Benches, the former will prevail. It was so said by looking into the ratio of judgment rendered by the Five Judges Bench of the Supreme Court of India, in Central Board of Dawoodi Bohra Community & Anr. Vs. State of Maharashtra & Anr. (2005) 2 SCC 673, wherein, when dealing with similar proposition, it was observed as under:-
“12. Having carefully considered the submissions made by the learned senior counsel for the parties and having examined the law laid down by the Constitution Benches in the abovesaid decisions, we would like to sum up the legal position in the following terms :-
(1) The law laid down by this Court in a decision delivered by a Bench of larger strength is binding on any subsequent Bench of lesser or co-equal strength.
(2) A Bench of lesser quorum cannot disagree or dissent from the view of the law taken by a Bench of larger quorum. In case of doubt all that the Bench of lesser quorum can do is to invite the attention of the Chief Justice and request for the matter being placed for hearing before a Bench of larger quorum than the Bench whose decision has come up for consideration. It will be open only for a Bench of coequal strength to express an opinion doubting the correctness of the view taken by the earlier Bench of coequal strength, whereupon the matter may be placed for hearing before a Bench consisting of a quorum larger than the one which pronounced the decision laying down the law the correctness of which is doubted.
(3) The above rules are subject to two exceptions : (i) The abovesaid rules do not bind the discretion of the Chief Justice in whom vests the power of framing the roster and who can direct any particular matter to be placed for hearing before any particular Bench of any strength; and
(ii) In spite of the rules laid down hereinabove, if the matter has already come up for hearing before a Bench of larger quorum and that Bench itself feels that the view of the law taken by a Bench of lesser quorum, which view is in doubt, needs correction or reconsideration then by way of exception (and not as a rule) and for reasons given by it, it may proceed to hear the case and examine the correctness of the previous decision in question dispensing with the need of a specific reference or the order of Chief Justice constituting the Bench and such listing. Such was the situation in Raghubir Singh and Hansoli Devi.”
16. In Ambrish Kumar Shukla case (supra), ratio of judgment-Shahbad Cooperative Sugar Mills Ltd. (supra) was not even discussed and considered. In view of above proposition of law laid down by the Five Judges Bench in Central Board of Dawoodi Bohra Community & Anr.`s and also Three Judges Bench of the Supreme Court, in New India Assurance Co. Ltd. Vs. Hilli Multipurpose Cold Storage Pvt. Ltd. case (supra), it is not open to the Bench of co-equal strength to give contrary findings, to the view already expressed by a Former Bench of same strength. In Shahbad Cooperative Sugar Mills Ltd. case (supra), decided on 02.04.2003, it was specifically observed by Three Judges Bench of the National Commission that when determining pecuniary jurisdiction of the Consumer Foras, interest component claimed by the complainant/party, is not to be added. We are of the considered view that in view of proposition of law, as explained above, the view taken in Shahbad Cooperative Sugar Mills Ltd. case (supra), to determine pecuniary jurisdiction without taking interest claimed, will prevail. As such, in the present case, we are not looking into the interest claimed by the complainant, when determining pecuniary jurisdiction of this Commission. If the interest part is excluded, the amount claimed in the relief clause fell below Rs.1 crore and above Rs.20 lacs. Hence, this Commission has pecuniary jurisdiction to entertain and decide the present complaint. In view of above, the objection raised by the opposite parties, in this regard, being devoid of merit, must fail and the same stands rejected.”
In view of above, this objection taken by the Opposite Parties that this Commission lacks pecuniary jurisdiction, being devoid of merit, fails and the same stands rejected.
10. The objection taken by the Opposite Parties, to the effect that the complainant did not fall within the definition of “Consumer”, as per the Consumer Protection Act, 1986, as there is no averment that the complainant does not have any other plot/unit in her name, as such, the unit purchased by the complainant in the project of the Opposite Parties for investment purposes, also deserves rejection. It is clearly stated in para No.16 of the complaint that the complainant purchased the said plot for residential purposes for her family. The complainant in her rejoinder has clearly stated that the husband of the complainant died on 04.08.2013 and she is surviving on savings of her husband only and have no other source of income. The complainant further stated that she is residing in House No.127, Phase 3B1, SAS Nagar, Mohali and except for the plot in the present dispute, there is no other plot in the name of the complainant. The complainant further stated that she purchased the said plot for giving one plot/house each to her children. It may be stated here that there is nothing, on the record, that the complainant is the property dealer, and deals in the sale and purchase of property, on regular basis, and as such, the plot/unit, in question, was purchased by her, by way of investment, with a view to resell the same, as and when, there was escalation in the prices thereof. Thus, in the absence of any cogent evidence, in support of the objection raised by the Opposite Parties that the complainant purchased the plot for investment purposes, as such, did not fall within the definition of a consumer, cannot be taken into consideration. In a case titled as Kavita Ahuja Vs. Shipra Estate Ltd. and Jai Krishna Estate Developer Pvt. Ltd. 2016 (1) CPJ 31, by the National Consumer Disputes Redressal Commission, New Delhi, it was held that the buyer(s) of the residential unit(s), would be termed as consumer(s), unless it is proved that he or she had booked the same for commercial purpose. Similar view was reiterated by the National Commission, in DLF Universal Limited Vs Nirmala Devi Gupta, 2016 (2) CPJ 316. The principle of law, laid down, in the aforesaid cases, is fully applicable to the present case. The complainant, thus, falls within the definition of a ‘consumer’, as defined under Section 2(1)(d) of the Act. Such an objection, taken by the Opposite Parties, in their written reply, therefore, being devoid of merit, is rejected.
11. The next question, that falls for consideration, is, as to whether the Opposite Parties offered possession of the unit/plot, in question, to the complainant, complete in all respects or not. As per Clause 8 of the Agreement, possession of the plot/unit was to be delivered within a period of 2 years from the date of execution of the Agreement but not later than 3 years. So, the period of 3 years from the date of execution of the Agreement dated 18.06.2007 has expired on 17.06.2010. According to the Opposite Parties, they sent letter of offer of possession of plot No.69, Augusta Greens, Mohali Hills, Sector 109, to the complainant vide letter dated 28.12.2009 (Annexure C-5) i.e. within the stipulated time frame with all the basic amenities, as mentioned in the Agreement. At the time of arguments, Counsel for the complainant stated that possession offered by the Opposite Parties is only updation letter/paper possession and not more than that because the complainant in her complaint has specifically stated that she visited number of times to the office of the Opposite Parties and complained regarding lack of development at project site, however, every time they kept on delaying by promising that possession would be delivered soon after completion of development work of the project. The complainant further stated that she sent various letters, emails and also sent legal notice to the Opposite Parties, however, they failed to pay any heed to the grievances of the complainant. She further stated that the project site still lacks proper facilities of acess, electricity and water supply etc. She further stated that the Opposite Parties remained involved in dispute with Forest Authorities and the entry and exit points of the project remained closed. At the time of arguments, Counsel for the complainant came to the knowledge of this Commission the relevant portion of the said possession letter (Annexure C-5) which reads thus :-
“This has reference to the plot allotted to you in the Project. We take this opportunity to update you on the status of the development work of the Project and in particular about the Plot situated in Augusta Greens Sector 109 of the Project.
X x x x xx
The development activities in all three sectors of Mohali Hills i.e. Sectors 105, 108 and 109 are in full swing and we are pleased to inform you that significant progress has been made with respect to development of basic infrastructure like water pipelines, sewer pipelines and development of roads, parks in these sectors. X x x x x.
In view of the above development and our constant endeavor to enhance our customer’s satisfaction, we are prepared to hand over possession of the Plot to you, subject to your making payments mentioned hereunder :
On the basis of ground demarcation, the area for your plot has increased/decreased and as a consequence the revised area is 435 sq. yards. X x x x x x”
In view of the afore-extracted letter, it is clearly revealed that the Opposite Parties only informed the complainant regarding updation of the status of the development work of the project. It is not a possession letter because the Opposite Parties clearly stated that they are prepared to hand over possession of the plot. Thereafter, the Opposite Parties sent a letter dated 16.12.2011 (Annexure C-6) to the complainant. The relevant portion of the said letter reads thus :-
“Pursuant to the offer of possession sent to you, we are pleased to confirm that you may apply to the Estate Officer, GMADA for the sanction of building plans to initiate construction on your said plot.
X x x x xx x
We have already initiated community development works like parks, golf course, roads, electrical lighting and setting up of STP (Sewer Treatment Plant), Rain water harvesting system and the electrical sub stations.
Upon completion of the above and receipt of Completion Certificate from GMADA, we shall commence the process of the execution and registration of sale deeds and shall keep you updated on further developments in relation.”
Thereafter, the Opposite Parties sent settlement of final dues letter dated 13.06.2014 (Annexure C-7) i.e. after about 5 years from the offer of possession letter and about 3 ½ years from the last letter sent by the Opposite Parties (Annexure C-6). It is relevant to mention here that the complainant sent a letter dated 05.07.2014 (at page No.50 of the complainant’s documents) to the Opposite Parties, which reads thus :-
“x x x x x
I have personally visited the site some days ago and found no such amenity is provided by you at the sites. I inquired about Sewerage Treatment Plant (STP) from certain sources. This facility is not available in your sector, nor is any overhead/underground water tank provided by the builder.
I have inquired from Punjab State Power Corporation Ltd., at SAS Nagar and have been informed that no government electricity connection has been sanctioned for Sector 109 up till date.
X x x x x”
Due to non-completion of the project, the complainant sent a letter dated 30.05.2016 (at page No.54 of the complainant’s documents) to the Opposite Parties and sought refund of the deposited amount with interest. Thereafter, the complainant also sent a legal notice through registered post to the Opposite Parties but they failed to refund the deposited amount. From the afore-extracted emails/letters, it is crystal clear that the Opposite Parties were unable to deliver possession of the plot, complete in all respects, to the complainant. Even the Opposite Parties failed to place on record any document, which could prove that all the basic amenities were complete at the site or they sent any letter to the complainant after the aforesaid letter, that the unit is complete in all respects and they are ready for possession. Not only this, it is also relevant to note that a number of cases of Sector 109 of Emaar MGF Land Limited have already been decided by this Commission regarding the issue of sealing of project by Forest Department and other issues in Sector 109, one of which is titled as “Prabhujeev Singh Bajaj Vs. Emaar MGF Land Limited & Anr., Complaint Case No.43 of 2016, decided by this Commission vide order dated 29.06.2016”, the relevant portion of the said judgment reads thus :-
“31. However, the main grouse of the complainant is that, despite relocation to the said units, even then, actual physical possession thereof, was not offered to him, whereas, on the other hand, paper offer was made to him, vide letters dated 25.08.2014 and 07.11.2014, because when he visited the site after receiving the said letters, to see development and basic amenities, the same were found missing and besides that, all entry points of the project, had been sealed by the Forest Department, as opposite parties no.1 and 2, failed to take requisite permissions/sanction from it. Thus, in these circumstances, the principal question, which goes to the root of the case, and falls for consideration, is, as to whether, offer of possession made by opposite parties no.1 and 2, to the complainant, vide letters dated 25.08.2014 and 07.11.2014, in respect of the relocated units, could be said to be genuine offer or not. It is well settled law that the onus to prove that the project had been completed and the area/site, in question, is fully developed is on the builder/opposite parties no.1 and 2. It was so said by the National Commission, in Emaar MGF Land Limited and another Vs. Krishan Chander Chandna, First Appeal No.873 of 2013 decided on 29.09.2014. It is very strange that not even an iota of evidence has been placed, on record, by opposite parties no.1 and 2, to prove that when offer was made to the complainant, in respect of the units, in question, development work was complete and that all the basic amenities were in existence. On the other hand, in case, all the development activities, had been undertaken, and completed at the site, by the said dates, then it was for opposite parties no.1 and 2, which could be said to be in possession of the best evidence, to produce cogent and convincing documentary evidence, in the shape of the reports and affidavits of the Engineers/Architects, as they could be said to be the best persons, to testify, as to whether, all these development activities, had been undertaken and completed at the site or not, but they failed to do so. Opposite parties no.1 and 2 were also required to produce on record, a copy of the Completion Certificate (if obtained), having been issued by the Competent Authority, which could be said to be best evidence, to prove their case, but they miserably failed to do so. It is well settled law that before offering/delivery of possession of unit, in a project, it is mandatory to obtain completion certificate, from the Competent Authority(s), failing which the purchaser is at liberty to say no, to such an offer.
Secondly, the complainant has placed on record, copies of the RTI Information, relating to the said project, in question. Vide RTI Information dated 29.04.2014 Annexure C-31, it was clearly intimated by Greater Mohali Area Development Authority (GMADA), that opposite parties no.1 and 2, had not even applied to them for commission of sewerage treatment plant, water supply, electricity etc. Not only this, it is further evident from RTI Information dated 26.02.2015 Annexure C-30, issued by the Punjab State Power Corporation Limited (PSPCL), that no regular electricity connection has been released in the sector, in question, wherein the plots are situated. The said RTI Information goes unrebutted by opposite parties no.1 and 2. Not even a single document has been brought on record to prove that the information relating to non-existence of basic amenities, mentioned in the said RTI Information is false, or that the said information was fabricated by the complainant. Had the said information been false or fabricated, opposite parties no.1 and 2, could have obtained certificate from the said Authorities, to say that the same had not been supplied from their Department, but they (opposite parties no.1 and 2) failed to do so. Thus, it could safely be said that the complainant has proved his case, that opposite parties no.1 and 2 did not even obtain permission to provide basic amenities such as water, electricity etc., till 29.04.2014 or 26.02.2015, the dates when RTI information aforesaid, was issued by the Authorities concerned.
Not only this, it is also an admitted case, that entry points of the project had been sealed by the Forest Department, as opposite parties no.1 and 2, failed to take requisite permissions/ sanction from it, which fact has also been admitted by them (Opposite Parties no.1 and 2), in paragraph No.26 of their written version. Not only this, the said fact is further corroborated from the letter dated 15.04.2015 Annexure-4 (at page 190 of the file), sent by opposite parties no.1 and 2, to the Chief Administrator, GMADA, requesting it to take up the matter with the Forest Department, regarding sealing of entry points of the project, in question, as the same had been stated to be “illegal access”. It has been clearly mentioned by opposite parties no.1 and 2, in the said letter that “…….we are bound by the agreement to give delivery within time bound manner to our various restive customers, we had applied for grant of access with your good self”. This admission of the opposite parties no.1 and 2, in the letter dated 15.04.2015 written to the Chief Administrator, GAMDA, itself clearly goes to prove that even till that date (15.04.2015), they were not in a position, to deliver possession of the plot(s) to their customers, including the complainant, in the said project, on account of reason that the entries thereof had been sealed by the Forest Department, stating it to be an “illegal access through the Forest Strip”,permissions/sanction, whereof has not been obtained by them. Not even a single piece of evidence has been brought on record, to prove that the said entry points have been got reopened by opposite parties no.1 and 2, after having obtained permission from the Authorities concerned. If it is so, then it remained unclarified by opposite parties no.1 and 2, as to when entry points of the project were sealed, how could they offer possession of the units, to the allottees, including the complainant, in the year 2014.
A plea was also taken by opposite parties no.1 and 2 that only recently the Forest Department has served notice on them, alleging illegal access created by them, through the Forest land. To the contrary, perusal of RTI Information dated 05.05.2015 Annexure C-28 (colly.) (at pages 120 to 127 of the file) issued by the Government of Punjab, reveals that a court case with regard to dispute between the Forest Department and opposite parties no.1 and 2, is pending litigation before the Civil Court Kharar, since 03.07.2012, as opposite parties no.1 and 2 have violated Sections 29,33 and 63 of the Indian Forest Act 1927 and have also violated the directions passed by the Hon'ble Supreme Court of India, vide order dated 12.12.1996. The said RTI Information also goes unrebutted by opposite parties no.1 and 2. Thus, the matter with regard to entry points aforesaid, in respect of the said sector, in dispute, was an old dispute, between the Forest Department and opposite parties no.1 and 2, as they had not taken permission from the Competent Authorities, which fact was not disclosed by them, in their written version, filed before this Commission.
In view of above, it is held that the act of opposite parties no.1 and 2, in offering paper possession of the units, in question, vide letters 25.08.2014 and 07.11.2014, in the absence of development work; basic amenities at the site; non-obtaining of completion certificate, and also entry points of the project being sealed/closed by the Forest Department, amounted to deficiency in providing service and also adoption of unfair trade practice. It is therefore held that the offer of possession made by opposite parties no.1 and 2, vide letters dated 25.08.2014 and 07.11.2014 is nothing, but a paper possession, which is not sustainable, in the eyes of law.”
Aggrieved against the afore-extracted order passed by this Commission, the Opposite Parties filed First Appeal No.997 of 2016 in the Hon'ble National Consumer Disputes Redressal Commission, New Delhi, wherein, the matter was settled between the parties on 08.11.2016, as per the Settlement Agreement.
12. It is pertinent to note that the Opposite Parties (Emaar MGF) filed appeal in another case i.e. First Appeal bearing No. 709 of 2016 titled as ‘Emaar MGF Land Limited Vs. Mandeep Saini’ before the Hon'ble National Consumer Disputes Redressal Commission, New Delhi, against the order of this Commission and the Hon'ble National Consumer Disputes Redressal Commission, New Delhi passed the order dated 14.09.2016, which reads thus :-
“x x x x xx
It is vehemently argued by Mr.Aditya Narain, learned counsel appearing for the Appellant that since the delay in delivery of possession of the flats in Sectors 104, 106, 108 and 109 is directly attributed to the sealing of the main access road to these Sectors by the Forest Department, one of the factors which weighed with the State Commission, falls within the ambit of force majeure clause in the agreement, there is no deficiency in service on the part of the Appellant in its alleged failure to deliver the possession of the subject flats in question by the committed time. He thus prays that ex parte ad interim stay may to be continued.
Prima facie, we are not convinced with the submission. Hence, without expressing final opinion on the issue but having regard to the fact that the sealing orders have not yet been revoked and the Appellant is still not in a position to deliver possession of the fully developed flats with proper access, to the Complainants, we direct that the Appellant shall deposit in this Commission the principal amount(s) deposited by the Complainants with them, within 6 weeks from today. On deposit of the said amount(s), it will be open to the Complainants to withdraw the said amount, on filing affidavits, undertaking to this Commission that they will refund the amount(s) withdrawn, if so directed at the time of final disposal of the Appeals. Subject to the said deposits, the operation of the remaining directions, regarding interest, compensation, etc., in the impugned order shall remain stayed.
X x x x x xx x”
From the afore-extracted order, it is clearly proved that Counsel for the Opposite Parties admitted before the Hon'ble National Consumer Disputes Redressal Commission, New Delhi that the delay in delivery of possession to these Sectors i.e. Sectors 104, 106, 108 & 109 was due to the sealing of main access road by the Forest Department. It is clearly proved that the Hon'ble National Consumer Disputes Redressal Commission, New Delhi without expressing final opinion on the issue but having regard to the fact that the sealing orders have not yet been revoked and the Appellant i.e. Emaar MGF Land Limited is still not in a position to deliver possession of the fully developed flats with proper access, to the complainant i.e. till the passing of the afore-extracted order dated 14.09.2016. So, we are of the view that in the present case, the possession offered by the Opposite Parties in the year 2009 is only a paper possession and not more than that.
13. The next question, that falls for consideration, is, as to whether, the complaint filed by the complainant, was within limitation or not. The Opposite Parties in their written statement stated that the complaint is time barred as it has been filed more than two years after accrual of alleged cause of action i.e. on 28.12.2009 when the possession was offered to the complainant for the first time and thereafter, reminder sent to her on 16.12.2011 (Annexure C-6) to take over possession and initiate construction, which they have failed to do. It is clear from the aforesaid paragraph that paper possession was offered to the complainant on 28.12.2009 (Annexure C-5). Not only this, the Opposite Parties sent a letter dated 06.12.2011 (Annexure C-6) to the complainant and also sent a letter dated 13.06.2014 (Annexure C-7) for settlement of final dues. Moreover, the Opposite Parties sent payment request reminder dated 23.07.2014 and 26.08.2014. The complainant also sent a legal notice dated 30.05.2016 through registered post to the Opposite Parties (at page No.55 of the complainant’s documents) but the same was never replied by her. So, it is clearly proved that lot of correspondence was exchanged between the parties till August, 2014. Neither the actual physical possession of the plot was handed over to the complainant nor refund of the deposited amount to her, when request for the same was made by her, vide letter and legal notice dated 30.05.2016, as such, there is continuing cause of action, in her favour, in view of principle of law laid down, in Lata Construction & Ors. Vs. Dr. Rameshchandra Ramniklal Shah and Anr., II 2000 (1) CPC 269=AIR 1999 SC 380 and Meerut Development Authority Vs. Mukesh Kumar Gupta, IV (2012) CPJ 12 (SC). Under these circumstances, it is held that the complaint is not at all barred by time. The submission of Counsel for the Opposite Parties, in this regard, being devoid of merit, must fail, and the same stands rejected.
14. Another objection raised by Counsel for the Opposite Parties that since it was mentioned in the Agreement that the Company shall endeavour to deliver possession of the plot within maximum period of three years, as such, time was not the essence of contract, is also devoid of merit. It may be stated here that it was clearly mentioned in Clause 8 of the Agreement that possession of the plot will be delivered by the Opposite Parties, within a period of maximum three years, subject to force majeure circumstances or reason beyond the control of the Opposite Parties. In the instant case, the Opposite Parties did not raise any force majeure circumstances, if any, encountered by them. In the absence of any force majeure circumstances having been faced by the Opposite Parties or any other valid and legal reason beyond their control, the stand taken by them, in this regard, for condonation of delay in delivery of possession of the plot/unit, to the complainant, cannot be taken into consideration. Thus, under these circumstances, since as per Clause 8 of the Agreement, the Opposite Parties were bound to deliver possession of the unit, within a maximum period of three years from the date of execution of the same i.e. latest by 17.06.2010, as such, time was, unequivocally made the essence of contract.
Even otherwise, the opposite parties cannot evade their liability, merely by saying that since the word tentative/ proposed was mentioned in the Agreement, for delivery of possession of the unit, as such, time is not to be considered as essence of the contract. Non-mentioning of exact date of delivery of possession of the unit(s) in the Buyer’s Agreement, is an unfair trade practice, on the part of the Builder. The builder is bound to mention the exact/specific date of delivery of possession of the unit(s) to the allottees/purchasers thereof. It was so said by the Hon`ble National Commission, in Rajeev Nohwar & Anr. V/S Sahajanand Hi Tech Construction Pvt Ltd, 2016 (2) CPR 769. Relevant portion of the said case reads thus:-
“Merely making possession by a particular date will also not meet the requirement of law and the promotor is under a legal mandate to stipulate a specific date for delivery of possession of the flat in the agreement which he executes with the flat buyer”.
In view of above, the plea of the Opposite Parties in this regard also stands rejected.
15. The next question, that falls for consideration, is, as to whether, the complainant is entitled to refund of the amount of Rs.60,04,216/-, as claimed by her. It is an admitted fact that the complainant deposited an amount of Rs.60,04,216/-, as is evident from statement of account (Annexure C-3) and after receipt of the aforesaid huge amount, the Opposite Parties failed to deliver actual physical possession of the plot/unit, complete in all respects, to the complainant. The complainant cannot be made to wait for an indefinite period, for delivery of actual physical possession of the unit. The Opposite Parties, therefore, had no right, to retain the hard-earned money of the complainant, deposited towards price of the unit, in question. The complainant is thus, entitled to get refund of amount deposited by her. In view of above facts of the case, the Opposite Parties are also under an obligation to compensate the complainant, for inflicting mental agony and causing physical harassment to her.
16. It is to be further seen, as to whether, interest, on the amount refunded, can be granted, in favour of the complainant. It is not in dispute that an amount of Rs.60,04,216/-, was paid by the complainant, without getting anything, in lieu thereof. The said amount has been used by the Opposite Parties, for their own benefit. There is no dispute that for making delayed payments, the Opposite Parties were charging heavy rate of interest (compounded @15% p.a.) as per Clause 3 of the Agreement, for the period of delay in making payment of installments. It is well settled law that whenever money has been received by a party and when its refund is ordered, the right to get interest follows, as a matter of course. The obligation to refund money received and retained without right implies and carries with it, the said right. It was also so said by the Hon`ble Supreme Court of India, in UOI vs. Tata Chemicals Ltd (Supreme Court), (2014) 6 SCC 335 decided on March 20th, 2014 (2014) 6 SCC 335). In view of above, the complainant is certainly entitled to get refund of the amount deposited by her, to the tune of Rs.60,04,216/- alongwith interest compounded @15% p.a., from the respective dates of deposit, till realization.
17. As far as the plea taken by the Counsel for the Opposite Parties, at the time of arguments, regarding forfeiture of earnest money is concerned, it may be stated here that the same stands rejected, because it is not their (Opposite Parties) case, that it was ready with possession of the unit, to be delivered to the complainant, by the stipulated date but it was he (complainant) who wanted to rescind the contract, on account of some unavoidable circumstances/ financial constraints, due to deficiency in the services of the Opposite Parties or for any personal reason, and is seeking refund of the amount deposited. Had this been the case of the Opposite Parties, that they were willing to offer possession complete in all respects by the stipulated time, only in those circumstances, it would have been held that since the complainant herself is rescinding the contract, as such, she is entitled to the amount deposited, after deduction of the earnest money, as per the terms and conditions of the Agreement. In this view of the matter, the plea taken by the Opposite Parties, in this regard, has no legs to stand and is accordingly rejected.
18. No other point, was urged, by the Counsel for the parties.
19. For the reasons recorded above, the complaint is partly accepted, with costs. The Opposite Parties are jointly and severally directed, as under:-
20. However, it is made clear that, if the complainant, has availed loan facility from any banking or financial institution, for making payment of installments towards the said unit, it will have the first charge of the amount payable, to the extent, the same is due to be paid by the complainant.
21. Certified Copies of this order be sent to the parties, free of charge.
22. The file be consigned to Record Room, after completion.
Pronounced.
March 28, 2017. Sd/-
[JUSTICE JASBIR SINGH (RETD.)]
[PRESIDENT]
Sd/-
[DEV RAJ]
MEMBER
Sd/-
(PADMA PANDEY)
MEMBER
rb
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.