
View 280 Cases Against Bcl Homes
Devki Nandan Kapoor filed a consumer case on 14 Sep 2016 against BCL Homes Ltd. in the StateCommission Consumer Court. The case no is CC/231/2016 and the judgment uploaded on 19 Sep 2016.
STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
U.T., CHANDIGARH
Complaint No. | : | 231 of 2016 |
Date of Institution | : | 24.05.2016 |
Date of Decision | : | 14.09.2016 |
…Complainants
....Opposite Parties
Complaint under Section 17 of the Consumer Protection Act, 1986.
BEFORE: JUSTICE JASBIR SINGH (RETD.), PRESIDENT.
MR. DEV RAJ, MEMBER.
MRS. PADMA PANDEY, MEMBER
Argued by:- Sh.Varun Chawla, Advocate for the complainants.
Sh.Puneet Tuli, Advocate for opposite parties.
PER JUSTICE JASBIR SINGH (RETD.), PRESIDENT
The complainants are husband and wife. Allured by false promises made by representatives of the opposite parties, the complainants purchased one built-up flat bearing no.603, A, Type 3 BHK, 6th Floor, Tower No.2, measuring 2170 square feet, in a project launched by them (opposite parties), under the name and style of “Chinar Homes”, Kishanpura, Zirakpur. Allotment letter was issued in favour of the complainants on 02.01.2013. The said unit was purchased for an amount of Rs.50.50 lacs. It was stated that by 02.01.2013, the complainants had paid the entire amount, towards sale consideration of the said unit, in the following manner:-
Sr.No. | Particulars | Received against Receipt No. and date | Amount |
Cheque no.000362 dated 16.01.2013 drawn of Bank of Maharashtra | No.5726 dated 01.01.2013 | 10,00,000/- | |
Cheque no.000361 dated 01.01.2013 drawn of Bank of Maharashtra | No.5727 dated 01.01.2013 | 40,00,000/- | |
In Cash | No.5728 dated 02.01.2013 | 50,000/- |
To support above contention, receipts have been placed on record as Annexures C-2 to C-4. It is stated that possession of the flat was to be handed over to the complainants, after fully developing the project area. Detail of facilities promised to be provided in the said project is given in para no.3 of the complaint. As per clause 9 of the allotment letter, possession of the unit, in question, was to be delivered to the complainants, by the opposite parties, within a period of 18 to 24 months, with a grace period of three months (total 27 months), from the date of issuance of allotment letter i.e. on or before 01.04.2015, after providing all the basic amenities. It was further stipulated in clause 9 that, in case, the opposite parties, failed to deliver possession of the unit by the said date, they were liable to make payment of Rs.10,000/- per month, to the complainants, towards rent, for the period of delay, beyond 27 months aforesaid.
Again to know status of construction, letter was written on 30.11.2015 Annexure C-7. In the said letter, it was specifically stated that if flat is not ready for possession then rent amount alongwith amount paid be refunded to the complainants. Under similar circumstances, another letter was sent on 30.12.2015 Annexure C-8. Thereafter, many emails were sent by the complainants claiming possession/refund, however, without any result. Neither possession of the unit was delivered, nor rent amount @Rs.10,000/- per month for the delayed period, was paid to the complainants. It is further stated that internal development at the project site is not complete. Under above circumstances, legal notice dated 25.03.2016 to hand over physical possession of the flat or in the alternative refund the amount paid alongwith interest, was served upon the opposite parties but to no avail. To show that development/ construction work was not complete at the site, photographs taken at the site have been placed on record.
It is proved on record that the complainants purchased a built-up unit referred to above, for an amount of Rs.50.50 lacs, in a project launched by the opposite parties. Allotment letter was issued in their favour on 02.01.2013. Clause 9 of the said allotment letter reads thus:-
“The possession of the said flat shall be delivered to the Allottee(s) in 18-24 months from the date of this Agreement/allotment, with a grace period of 03 months. However, in the event there is a delay in offering the possession/permissive possession of the Flat in the said period, for any reason not directly attributable to BCL Homes Ltd. shall be entitled to reasonable extension in time for delivery of possession/permissive possession. In the event of completion of the said Flat being delayed beyond 27 months from the date of this Agreement/allotment, for reasons directly attributable to BCL Homes Ltd. shall be liable to pay to the Allottee(s) monthly rent of Rs.10,000/- for the period of delay beyond the said 27 months period on the amount paid to BCL Homes Ltd. by the Allottee. The possession of the Flat shall be handed over on receipt of the all dues, documents, and on fulfillment of conditions as stipulated herein. If the physical possession is not taken over at site within 45 days of the issue of the possession letter, the Allottee shall pay watch and ward charges @0.1% of the total cost of the flat per month. Notwithstanding anything contained in this Agreement, if the allottee fails to take over possession of the said flat within six months from the date of issue of possession letter, even if other portions of Project are not complete or are in the course of construction the allotment would be liable for cancellation”.
It is virtually admitted on record that till today, no offer has been made to hand over possession of the constructed unit by the opposite parties to the complainants. Rather perusal of documents on record depicts that the project is not complete and construction is virtually stopped at the site. In a case titled as Chand Berry and another Vs. BCL Homes Limited and others, consumer complaint no.292 of 2015, decided by this Commission on 19.02.2016, under similar circumstances, when deciding that complaint filed by the complainants stating that for non-delivery of possession, directions be issued to refund amount with interest, this Commission has observed as under:-
“It is a case of failed promise and virtually deceit has been committed by opposite parties no.1 to 3, with the complainants. It was never disclosed to the complainants, by opposite parties no.1 to 3, that the entire project land and construction to be raised thereon, stood mortgaged with opposite party no.5. Virtually after making more than 95% of the price of unit, delivery of possession thereof is not expected even in near future. Above fact clearly amounted to deficiency in providing service on the part of opposite parties no.1 to 3, which entitles the complainants to get refund of amount paid by them, towards the unit.”
It may be stated here that as regards the alleged shortage of construction material like sand etc. in the market, nothing has been placed on record, by the opposite parties, to prove that they were unable to procure the said construction material, in adequate quantity. There is no evidence of the opposite parties having invited tenders for supply of construction material and there being no response to such tenders. At the same time, it has also been submitted by Counsel for the opposite parties, at the time of arguments that the opposite parties have now started handing over possession of the units to the customers. It is also submitted by Counsel for the opposite parties that construction at the site is almost complete. If it is assumed to be true, that it remained unexplained by the opposite parties, as to how, they had been able to cover up the shortage of construction material, when there was ban on mining, as alleged. A similar plea for delay in delivery of possession of the units, was taken by a builder, before the Hon'ble National Consumer Disputes Redressal Commission, New Delhi, in Consumer Case No.347 of 2014, titled as Swaran Talwar & 2 others v. M/s Unitech Limited (along three connected complaints), decided on 14 Aug 2015, which was rejected and the complaint was allowed in favour of the complainant. The principle of law, laid down, in the aforesaid case is fully applicable to be present case. In the present case also, the opposite parties failed to convince this Commission, that they encountered force majeure circumstances, as a result whereof, delay in handing over possession of the unit occurred. As such, the stand taken by them, in this regard, is rejected.
“If some of the allottees had not made timely payment, it was for the opposite party to arrange the requisite finance either by taking loan or from its own resources or by liquidating Inventory at a lower price”.
No help, therefore, can be drawn by the opposite parties out of the plea, raised by them, in this regard.
According to Section 17 of the Act, a consumer complaint can be filed, by the complainants, before the State Consumer Disputes Redressal Commission, within the territorial Jurisdiction whereof, a part of cause of action arose to them. In the instant case, it is evident from the record, that payment in the sum of Rs.10 lacs vide receipt dated 01.01.2013 (at page 27), Rs.40 lacs vide receipt dated 01.01.2013 (at page 28) and Rs.50,000/-, vide receipt dated 02.01.2013 (at page 29) was received by the Registered Office of the opposite parties at Chandigarh i.e. Shop No.140, Railway Road, Village Dariya, U.T., Chandigarh. Since, as per the documents, referred to above, a part of cause of action, arose to the complainants, at Chandigarh, this Commission has got territorial Jurisdiction to entertain and decide the complaint. The objection taken by the opposite parties, in their written version, in this regard, therefore, being devoid of merit, must fail, and the same stands rejected.
The complainants hired the services of the opposite parties, for purchasing the unit, in question, and they were allotted the same for consideration. According to clause 9 of the allotment letter, the opposite parties were required to hand over possession of the unit, in question, to the complainants, within a period of 18 to 24 months, with a grace period of three months (total 27 months), from the date of issuance of the same (allotment letter), after completing all the basic amenities. It was not that the complainants purchased the unit, in an open auction, on “as is where is basis”. Section 2 (1) (o) of the Act, defines service as under:-
“service” means service of any description which is made available to potential users and includes, but not limited to, the provision of facilities in connection with banking, financing insurance, transport, processing, supply of electrical or other energy, board or lodging or both, housing construction, entertainment, amusement or the purveying of news or other information, but does not include the rendering of any service free of charge or under a contract of personal service”
As stated above, according to the clause 9 of the allotment letter, possession of the unit, in question, was to be delivered, to the complainants, within a period of 18 to 24 months, with a grace period of three months, from the date of issuance of the same (allotment letter) i.e. on or before 01.04.2015. Neither possession of the unit was offered nor delivered to the complainants, by the stipulated date for want of construction and basic amenities at the site, as has been frankly admitted by the opposite parties, in their written version nor the penalty amount, as provided in allotment letter, was paid to them nor the amount deposited by the complainants was refunded to them. There was, thus, a continuing cause of action, in favour of the complainants, to file the complaint. In Lata Construction & Ors. Vs. Dr. Rameshchandra Ramniklal Shah And Anr., II 2000 (1) CPC 269=AIR 1999 SC 380, wherein, the facts and circumstances were similar to the one, involved, in the instant case, it was held that there was a continuing cause of action, and the complaint was not barred by time. In Meerut Development Authority Vs. Mukesh Kumar Gupta, IV (2012) CPJ 12 (SC), the complainant applied for a plot, in the year 1992, on the basis of inducement made in the advertisements of the opposite party/builder. It was known to the opposite party that the land, in question, was under litigation. Consumer Complaint was filed, in the year 2009, claiming relief of execution of the sale deed, which was granted to him. An objection was taken that the complaint was barred by time. The Hon'ble Supreme Court held that there was a continuing cause of action, and, as such, the complaint was not barred by time. The principle of law, laid down, in the aforesaid cases, is fully applicable to the facts of the instant case. Under these circumstances, it is held that the complaint was not at all barred by time. The objection taken by the opposite parties, in this regard, being devoid of merit, must fail and the same stands rejected.
In view of above facts of the case, the opposite parties are also under an obligation to compensate the complainants, for inflicting mental agony and causing physical harassment to them, as also escalation in prices.
Pronounced.
14.09.2016
Sd/-
[JUSTICE JASBIR SINGH (RETD.)]
PRESIDENT
Sd/-
[DEV RAJ]
MEMBER
Sd/-
(PADMA PANDEY)
MEMBER
Rg.
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.