IN THE PRESIDENT, DISTRICT CONSUMERS DISPUTE REDRESSAL FORUM, SAMBALPUR
C.C. No.28 of 2017
Santosh Kumar Nanda,
Son of Late Trivikram Nanda,
Aged about 63 years,
Resident of Adarsh Nagar, At/P.O.- Ainthapali
Dist-Sambalpur ……………… Petitioner
-VERSUS –
- Executive Engineer, WESCO Utility
At/P.O./P.S. - Ainthapali,
Dist-Sambalpur, Odisha.
- Superintendent Engineer WESCO Utility
At/P.O./P.S. - Burla,
Dist-Sambalpur, Odisha..………….. Opp. Parties
For Complainant : Prem Prakaash Panigrahi
For O.P.s No.1 & 2 : Sri Sudhir Ku. Dora & Associates
PRESENT:- SHRI A.P. MUND, PRESIDENT
SMT. S. TRIPATHY, MEMBER
SHRI K.D.DASH, MEMBER
Date of Order: 01.06.2018
Shri A.P. Mund, President
The case of the complainant is that, he is a senior citizen and after post-retirement, he constructed a house over plot No. 347 khata No. 241 consisting of 0.335 acre at Gopalpali chowk, Remed near N.H. - 6.
According to the complainant one high voltage 11 KV electric ware overhead line belonging to the O.Ps passed through the plot of the complainant. Another domestic over head line also passes through this plot. The high voltage electric line is danger and hazard to the complainant and his family. To ensure the safety for the consumer and the family member, the complainant met the Executive Engineer of Sambalpur Electrical Division for the removal and shifting of the electric lines on 05.07.2013. The O.P.No.1 advised to deposit Rs.500/- towards application money which the complainant complied. He also served a letter dt.05.07.2013 which was acknowledged by the O.P. No.1. The complainant also gave his consent that he will further deposit additional money as per demand by the O.Ps.
The O.P. did not respond and remain silent and did not shift the line for which the complainant with his family could not move to the new house.
That this indifferent of O.Ps in not shifting the lines amount to deficiency in service, unfair trade practice and effect the safety of the consumers. On the basis of the above the complainant prays for;
- Initiate the process of shifting the overhead electric lines as stated in para 2, with immediate effect by realizing the further money if any required as per norms/law which the complainant is ready to pay.
- Compensation of Rs. 50,000/- for deficiency service and mental agony etc.
- Rs. 20,000/- towards the cost of this proceeding. Any other relief as deemed fit and proper by the Hon’ble forum may be awarded.
To substantiatehis case the complainant has filed the following documents;
- Map showing the lie for shifting of 11 KV line which has 0.1 K.M away from the plot no. 347
- Money receipt showing payment of Rs. 500/-
- Letter dt. 05.07.2013 by the complainant to the Executive Engineer, WESCO for shifting of 11 KV line
- Letter by the complainant to the Executive Engineer, WESCO dt. 09.03.2017 for shifting of High Tension Electrical Transmission Line and Domestic line.
The O.Ps appear through their Learned Advocate and filed their show cause. Their main defence is that the 11 KV Remed and 11 KV Burla feeders are very old installations in the area for power supply to Remed area and Durgapali area. According to the O.Ps the over head line were present long before the complainant constructed the house without making any effort to shift the line before construction of the house.
The construction of the house should have been made after shifting of the line.
The complainant engaged one contractor named M/S Subhadra Electricals and Civil Construction to shift the line. He also requested for framing the estimate and agreed to deposit 6% of the estimated value for supervision the O.P. went on to aver that there is no scope of shifting both the 11 KV of HT line as well as domestic line from the premises of plot No. 347 to outside boundry line, because plot No. 347 is surrounded by other private plots. The contractor engaged by the complainant could not give this scope and accordingly estimate of shifting could not be framed by the O.P,s
According to the O.Ps the contractor engaged by the complainant had not submitted his report. This caused that shifting could not be done in the right time.
Accordingly the O.P. informed that they have never neglected in their duties and the complainant’s contractor never claimed any suggestion for changing/shifting of the line. Hence, prays that the complainant may be directed by this forum to provide the right of way for shifting the lines so that estimate can be made accordingly and after depositing and completing all the departmental formalities the work can be taken up.
No documents filed by the O.Ps.
The O.P. through their Learned Advocate filed a petition dt. 20.06.17 stating there in that, this complaint petition could not be trialed by this Forum as the complainant is not a consumer and their relationship between the complainant and O.P.s are not coming under the provision of consumer Act. Hence, prayed for dismissal of the case. This petition was not received by the Advocate of the complainant, though the copy was attached for the service of the complainant. The complainant had filed one decision of Hon’ble NCDRC in Sajjan Sachdeva and another Vrs Punjab State Electric Board and others passed in 28th August 2012. The O.Ps filed another petition dt. 24.08.17 through their Learned Advocate. The gist of the petition is that the complainant may be directed to submit Right of Way (undisputed to O.P’s) authority and accompany the O.Ps for spot verification. Only after the satisfaction of the O.Ps the shifting of 11 KV line with follow up action be made by the O.Ps. This petition was received by the complainant. The O.Ps through their Learned Advocate filed another petition dt.13.12.17 which was received by the complainant on dt. 04.05.2018.
In Para – 3 of the petition, the O.Ps argued that the impugned line was drawn in the year 1970’s. There was no dwelling house on the plot, the complainant purchased the plot and constructed this house under the over head line.
In Para 5 the O.Ps have submitted that unless a definite demarcated area is provided to the O.Ps it will be difficult for the O.Ps. to shift the high tension line.
Further the advocate for the complainant is orally submits to shift the high tension line above the boundary line of the plot of the complainant. This boundary line may change with year and will be a cause for future litigation. In this petition the O.P’s. further prays that the complainant may be directed to provide authenticated demarcated area for shifting the H.T. line.
The Advocate for the complainant filed an application for recusal of the President on dt.13.03.18 which was objected to vide petition dt. 23.03.18. Both the objections were received by the respective parties. These petitions were not taken up for hearing as both the Learned Advocates conducted their argument on 04.05.18 on the main issues involved in the case skipping the above petition.
The Learned Advocate for the complainant submitted that the 11 KV line is causing a serious hazard and putting the complainant families serious jeopardy. Further argued that the H.T over head line has been drawn over the complainant land and it should be shifted along the boundry of the existing plot of the complainant, so that, it does not invite fatalities in future. He also submitted that the decision cited is a clear case where in the Hon’ble NCDRC has asked for shifting of the HT line and applying the ratio be cited in the decision; the present HT line over the plot No. 347 of the complainant may be shifted along the boundry of the complainant.
This was strongly objected to by the Learned Advocate for the O.Ps. He restricted his argument as per his petitions dt. 20.06.17, 24.08.17 & 13.12.17 and the main thrust of the Learned Advocate for the O.P is that the complainant is not a consumer of the HT line. The Electricity Act 2003 2 (15) defines a consumer. There is no agreement made between the complainant and the O.Ps for supplying power from the H.T. line; rather in this case service line for domestic consumption is granted. Only on being recorded as a consumer of the utility the complainant becomes a consumer. Hence accordingly the complainant is not a consumer of the H.T. line drawn over head. Besides the Learned Advocate for the O.Ps argued that the complainant has not given a properly demarcated passage for the verification and satisfaction of the O.P. to redraw the line. Only in a cavaliar manner the Advocate for the complainant is arguing that the line can be shifted to the boundary of the complainant. There are four corners of the boundary and the Advocate for the complainant is not giving a proper direction as to whether it is east to west or north to south of the boundary. The Annexure-1 was earlier rejected by the O.Ps and the complainant should have been cautions enough to provide proper demarcated area which could have helped the O.Ps to draw estimate and do other necessary formalities for shifting of the H.T. Line.
On the basis of the above he vehemently argued that the complainant is not a consumer, he has not given proper instructions or co-operations in identifying the passage over which the H.T. line can be shifted; so as not to endanger the nearby plots or people in the vicinity.
O R D E R
We heard the arguments of both the sides. Perused the petitions as well as show cause. Gone through the documents filed by the complainant.
This is a peculiar case wherein the complainant has come up for shifting of the H.T. line the complainant is suppressed the following facts.
- He has not given the year of the purchase of the plot as well as the completion of the construction of the house. He has not given any indication whether the over head line was erected long before the purchase of the plot or afterwards, and whether the complainant followed the procedure specified in Rule 82 of the Indian Electricity Rules, 1956.
- On whose instruction the complainant deposited to Rs. 500/- towards application money and the letter he addressed to the O.P. No. 1.
- He has not supplied the cause as to why the contractor to be engaged; did not give any scope or right of way to the O.Ps to shift the H.T. line.
- Whether he is a consumer coming under the provision of the Consumer Protection Act. 1986.
This four points are converted into issues involved in this case. We are taking of the 4th issues i.e. whether he is a consumer or not.
Section 2 (b) of the C.P. Act 1986 define who is a consumer
(i) buy any goods;
(ii) Hirer or avails any service for a consideration.
Section 2 (e) of the C.P. Act 1986 defines that consumer dispute means, a dispute whether the person against whom a complaint has been made, derives allegation contained in the complaint.
Section C (1) of the C.P. Act 1986 defines allegation of unfair trade practice for a restrictive trade practice has been adopted by any (trader or service provider). We are one with the argument of the Learned Advocate of the O.Ps that the complainant is neither a consumer as per 2(15) of the electricity Act 2003 and under no circumstance the present complainant can be a consumer of the H.T. line. There is no consumer dispute as per our understanding after going through the complaint petition as well as the version of the O.Ps. The O.Ps have agreed to shift, subject to right of way. Hence this case is not one coming or satisfying sec 2 (e) of the CP Act 1986. The complaint petition does not reveal how unfair trade practice or deficiency in service was adopted by the O.Ps. The complainant has not explained as to how unexplained silence and indifferent attitude of the O.Ps amount to deficiency in service. The complainant has not made out the case how the above leads to deficiency in service .
Hence the issue No. 4 is answered in favour of the O.Ps.
Issue No. 2 & 3 are answered as follows;
The engaged contractor also did not provide the map for shifting of the line, which was not to the satisfaction of the O.Ps. The complainant has not provided any further instruction for giving any concrete proposal during the course of the case. He has avoided performing his part of contract and forced the O.Ps to shift the line without giving proper demarcated line. The complainant has not explained as to on whose instruction the complainant has deposited money.
The first issue is answered as follows;
The complainant has not supplied the year of purchase of the plot or the completion of the house. So we take the averment of the O.Ps in their petition dt. 13.12.17 that the line was drawn prior to 1970’s, this was not controverted by the complainant and this is the date when the H.T. line was drawn. The cited decision is on a different aspect. New Sabji Mandi at Jalandhar was constructed after requiring the plot by the Mandi Board and they had deposited the requisite amount with the Punjab Electricity Board.
The formalities was over and the Hon’ble NCDRC asked for shifting of the H.T line as all the formalities were completed before hand. In this case the complainant purchased the plot and build this house much after the drawing H.T. line. He has not given the scope or proper right of way to the O.Ps for estimating the cost of shifting of line. Hence the above cited case doesn’t help to the complainant.
In a decided case of JDA Vs The State of Rajasthan & other cited in AIR 1999 Raj 240 the Hon’ble Rajasthan High Court has categorically held that prior to construction of House, the Rules mentioned in Sec. 82 of The Indian Electricity Rules 1956 has to be followed by the complainant. If there was a dispute between the complainant & R.S.E.B., then the matter could have been referred to the Inspector. Taking the ratio, & applying it in this case we are of opinion that the complainant has not followed the guidelines of Rule 82. Let the matter be mutually settled between the complainant & the WESCO as per provisions of Rule 82 of the 1956 Rules.
Sd/- . Sd/-
SHRI A.P.MUND, I agree SMT S.TRIPATHY
PRESIDENT Member
.
. Sd/- Sd/-
SHRI K.D.DASH. Member I agree. Dictated and corrected by me.
Member.